RERA’d by NeevHQ

Projects · 4S DEVELOPERS PRIVATE LIMITED

4S The Aurrum

4S Developers · Sector 59 & 63A, Gurugram

Registered with RERA: Jul 2024

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: 4S Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project name4S THE AURRUM
Builder (promoter)4S DEVELOPERS PRIVATE LIMITED
LocationVILLAGE ULLAHWAS & BEHRAMPUR, SECTOR 59 & 63A GURUGRAM
RERA project IDRERA-GRG-1572-2024
Registration certificate numberGGM/849/581/2024/76 DATED 15.07.2024
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/10/2029
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area5.42957 acres
Licence225 OF 2023 (30.10.2023)
Estimated cost of the project₹69,113.32 lakh (₹691.13 crore)
Total units (plots, apartments, shops)243
Unit sizes (carpet area, as declared)40 units of 1,324 sq ft carpet; 120 units of 1,443 sq ft carpet; 40 units of 1,791 sq ft carpet; 40 units of 1,959 sq ft carpet; 1 unit of 2,854 sq ft carpet (1 tower); 1 unit of 2,973 sq ft carpet (1 tower); 1 unit of 3,822 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on29-04-2024
Building plans approved on29-04-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-07-2024
Likely completion date31-10-2030

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2026 (APR-JUN)
Latest report submitted on15-Jul-2026
Quarterly reports listed on the portal7

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹1,443.56 lakh (₹14.44 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1,146.95 lakh (₹11.47 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹1,156.85 lakh (₹11.57 crore)
Project bank account (escrow): deposited in the quarter₹1,443.56 lakh (₹14.44 crore)
Project bank account (escrow): withdrawn in the quarter₹1,443.56 lakh (₹14.44 crore)
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)243 apartments
Sold in the quarter6 apartments
EDC (development charges): paid / due as on date₹1,172.29 lakh (₹11.72 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 31-10-2023
  • Zoning Plan: Obtained Approval 01-08-2024
  • Service Plans: Obtained Approval 24-01-2024
  • Electricity Plans: Obtained Approval 29-06-2024
  • Site Plans: Obtained Approval 29-06-2024
  • Building Plans: Obtained Approval 29-05-2024
  • Fire NOC: Obtained Approval 26-10-2023

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 15 Jul 2026, for 30 Jun 2026
By part
  • Tower 1 to 3: Sub-structure: 70% of total proposed work done to date (5% done in the quarter). Super-structure: 10% done to date (3% in the quarter). All MEP, internal and external finishing items: 0%. Site work status shows most tasks yet to be started.
Unclear in the certificate
  • Table A gives total floors as '243 Units', which appears to be a data entry error and is unclear.
  • Number of basements is left blank in the certificate.
  • The certificate gives no single overall percentage for the project; figures are given per work component only.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project1
Cases
Decided cases against 4S DEVELOPERS PRIVATE LIMITED (all its projects)5 (Complaint: 5)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in