Projects · SHINE BUILDCON PVT. LTD.

70 Grandwalk

Shine Buildcon · Sector 70, Gurugram

Registered with RERA: Jul 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Shine Buildcon

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project name70 GRANDWALK
Builder (promoter)SHINE BUILDCON PVT. LTD.
LocationSECTOR-70, GURUGRAM
RERA project IDRERA-GRG-286-2019
Registration certificate number28 OF 2017 DATED 28.07.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/12/2027
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area2.893 acres
Licence34 OF 2012 (15-04-2012)
Estimated cost of the project₹17,900 lakh (₹179 crore)
Total units (plots, apartments, shops)511
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered232
Units unsold when registered279
Layout plan approved on14-03-2018
Building plans approved on14-03-2018

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date14-03-2022
Revised completion date30-06-2022
Infrastructure: projected completion30-06-2022
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on17-Oct-2026
Quarterly reports listed on the portal32

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0.06 lakh (₹0 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹430 lakh (₹4.3 crore)
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹281.08 lakh (₹2.81 crore)
Other costs in the quarter (EDC, taxes, etc.)₹8.21 lakh (₹0.08 crore)
Project bank account (escrow): deposited in the quarter₹0.04 lakh (₹0 crore)
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0.84 lakh (₹0.01 crore)
Units in the project (apartments / plots)511 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 29-09-2011
  • Zoning Plan: Obtained Approval 25-08-2015
  • Site Plans: Obtained Approval 14-03-2018
  • Building Plans: Obtained Approval 14-03-2018

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 04 Oct 2026, for 30 Sep 2026
By part
  • 70 Grandwalk - Sub structure: 100%, Excavation and raft completed; basements 1 to 3 completed; pile foundation not done
  • 70 Grandwalk - Super structure: 100%, G+12 floors, machine rooms and mumty; all 16 slabs cast by end of quarter
  • 70 Grandwalk - Mechanical (lifts, ventilation): 99.2%
  • 70 Grandwalk - Electrical (conducting, wiring, fixtures): 99.5%
  • 70 Grandwalk - Plumbing and fire fighting (piping, pumps, fixtures): 99.6%
  • 70 Grandwalk - Internal finishing (plaster, tiling, flooring, painting): 93%, Internal plaster in progress and painting or whitewashing in progress
  • 70 Grandwalk - External finishing (plaster, painting, facade): 92%, External paint or whitewashing in progress
  • 70 Grandwalk - Internal/external development (external road works): 100%
  • 70 Grandwalk - Common area facilities and amenities (fire safety, signage): 97.5%
  • 70 Grandwalk - Entrance lobby finishing: 80%, In progress
  • 70 Grandwalk - Waterproofing of terraces: 95.5%, Completed for 4th, 5th, 12th and 13th floor terraces
  • 70 Grandwalk - Lifts installation: 90%, In progress
  • 70 Grandwalk - Compound wall: 100%, Done

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed4
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project14
Cases
Decided cases against SHINE BUILDCON PVT. LTD. (all its projects)17 (Complaint: 16; Execution of an earlier order: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026