Projects · REAL TOWN PROPERTIES PVT LTD
83 Avenue
Real Town Properties · Sector 83, Gurugram
Registered with RERA: Jan 2019
Is it legal?
- RERA registered, valid till Sep 2020 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit quarterly progress report, per Authority show-cause notice dated 31 May 2022 (May 2022, open)
- Did not apply to extend registration or submit completion or occupation certificate with documents (Jun 2022, open)
- Did not complete the project within the completion time it declared (Jun 2022, open)
- 2 more cases: reply 4
- 17 complaints about this project decided by HRERA since Nov 2023 (1 delay interest ordered, 9 refund ordered, 5 assured return ordered, 1 other order, 1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Sep 2020, never extended (date has passed)
- Occupation certificate (Sep 2024) covers: Commercial building, ground to 10th floor only (no flats listed)
- Construction, as certified by the architect (Jan–Mar 2024):
- Done: 83 avenue: sub structure, 83 avenue: super structure, 83 avenue: plumbing and firefighting, 83 avenue: internal finishing, 83 avenue: external finishing
- In progress: 83 avenue: electrical 87%, 83 avenue: mechanical 85%
- Money: ₹139.1 crore spent of ₹144.6 crore; ₹5.5 crore still to spend (CA certificate, Mar 2024)
Location
- Nearest metro: Millennium City Centre Gurugram, 18.8 km by road (50 min by car)
- Cyber City 58 min · Airport 43 min by car at 9:30 am
- Within 3 km: 2 hospitals, 1 school, 0 malls
The builder: Real Town Properties
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 9 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | 83 AVENUE |
|---|
| Builder (promoter) | REAL TOWN PROPERTIES PVT LTD |
|---|
| Location | SECTOR-83, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-125-2018 |
|---|
| Registration certificate number | GGM/310/42/2019/04 DATED 16.01.2019 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/09/2020 |
|---|
| Registered with | HRERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 2.3625 acres |
|---|
| Licence | 12 OF 2013 (13-03-2013) |
|---|
| Estimated cost of the project | ₹15,725.25 lakh (₹157.25 crore) |
|---|
| Total units (plots, apartments, shops) | 382 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 221 |
|---|
| Units unsold when registered | 161 |
|---|
| Layout plan approved on | 31-10-2013 |
|---|
| Building plans approved on | 31-10-2013 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 01-01-2017 |
|---|
| Revised completion date | 30-09-2020 |
|---|
| Infrastructure: projected completion | 30-09-2020 |
|---|
| Infrastructure: percentage complete when registered | 0% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/03/2024 (JAN-MAR) |
|---|
| Latest report submitted on | 10-Jun-2024 |
|---|
| Quarterly reports listed on the portal | 20 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2024 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹-5.85 lakh (₹-0.06 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹481 lakh (₹4.81 crore) |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹252.06 lakh (₹2.52 crore) |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹198.04 lakh (₹1.98 crore) |
|---|
| Project bank account (escrow): balance at quarter end | ₹54.08 lakh (₹0.54 crore) |
|---|
| Units in the project (apartments / plots) | 382 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹1,384 lakh (₹13.84 crore) paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 13-03-2013
- Zoning Plan: Obtained Approval 13-03-2013
- Service Plans: Obtained Approval 18-10-2018
- Electricity Plans: Obtained Approval 01-05-2013
- Site Plans: Obtained Approval 31-10-2013
- Building Plans: Obtained Approval 31-10-2013
- Fire NOC: Obtained Approval 16-01-2024
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 25 Mar 2024, for 31 Mar 2024 |
|---|
| By part | - 83 Avenue: Sub structure: 100%, Excavation completed; raft and basement levels 1 and 2 under progress; no work done in the quarter
- 83 Avenue: Super structure: 100%, Building is G+12; no work done in the quarter
- 83 Avenue: Mechanical (MEP): 85%, Lifts and ventilation; 250 work value done in the quarter
- 83 Avenue: Electrical (MEP): 87%, Conduiting, wiring and fixtures; 231 work value done in the quarter
- 83 Avenue: Plumbing and firefighting (MEP): 100%, No work done in the quarter
- 83 Avenue: Internal finishing: 100%, Plaster, tiling, flooring and painting; no work done in the quarter
- 83 Avenue: External finishing: 100%, Plaster, painting and facade; no work done in the quarter
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 5 |
|---|
| By status | Scrutinized: 1; First Hearing: 3; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2163-2020: The Authority started this proceeding itself against the promoter, Real Town Properties Pvt Ltd, by issuing a notice under Section 42. The page does not state the reason for the notice. Status: Scrutinized. The case was listed for a hearing on 14 Aug 2020 with the status 'HARERA NEW COMPLAINT'. The next date of hearing is shown as NA. Latest: 14 Aug 2020, Case was listed for hearing with status 'HARERA NEW COMPLAINT'. No proceedings of the day, bench order or uploaded order is recorded on the page.
- RERA-GRG-3259-2022: A compliance proceeding started by the Authority against the promoter, Real Town Properties Pvt Ltd, under a notice citing 'Compliance us 42ld'. The page does not state what the alleged non-compliance is. Status: First hearing listed for 30 Jun 2022. No proceedings, bench order or uploaded order are shown on the page. Latest: 30 Jun 2022, First hearing was listed for this date, and the page shows the status as 'First Hearing'. A document was received at the Authority (Dak ID 36696) on this date with the remark 'New Complaint'.
- RERA-GRG-3610-2022: Show cause notice issued by the Authority to the promoter for not submitting a quarterly progress report, with a hearing set for 27 Jun 2022 Status: First hearing listed for 27 Jun 2022. The page shows no proceedings or order for that date. Latest: 27 Jun 2022, First hearing listed. The page records the status as 'FIRST HEARING', with no proceedings or order recorded.
- RERA-GRG-3948-2022: The Authority started this case against the promoter, Real Town Properties Pvt Ltd, through a show cause notice. The notice concerns not applying for extension of registration, and not submitting a completion certificate, part completion certificate or occupation certificate, as the case may be, along with the requisite documents. The registration certificate is shown as expired. Status: First hearing listed for 28 Jun 2022. The listing shows the status as FIRST HEARING, with no proceedings, bench or order recorded. Latest: 28 Jun 2022, First hearing listed. The listing shows no proceedings of the day and no order uploaded.
- RERA-GRG-3950-2022: Suo motu action by the Authority against the promoter for not finishing the project within the time it declared, under section 4(2)(l)(C) of the Act. The project is 83 Avenue, and the promoter is Real Town Properties Pvt Ltd. Status: Pending. The next hearing is fixed for 23 Jul 2025. The promoter has not appeared at several hearings. Latest: 10 Jun 2025, Matter listed to come up on 23 Jul 2025.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 17 |
|---|
| Cases | - RERA-GRG-4074-2025 (complaint, decided 17-Jul-2026): Possession delayed since 2017; builder ordered to pay 10.80% interest and hand over alternative unit.
- RERA-GRG-2528-2025 (complaint, decided 30-Jan-2026): Buyer's unit cancelled for unpaid dues; builder ordered to refund after 10% deduction with 10.80% interest.
- RERA-GRG-2498-2025 (complaint, decided 30-Jan-2026): Buyer's unit cancelled for non-payment; HRERA upheld cancellation and ordered refund after 10% deduction with 10.80% interest.
- RERA-GRG-2539-2025 (complaint, decided 30-Jan-2026): Buyer's unit cancelled for non-payment; authority upheld cancellation, ordered refund less 10% with 10.80% interest.
- RERA-GRG-2526-2025 (complaint, decided 30-Jan-2026): Buyer's unit cancelled for unpaid dues; HRERA upheld cancellation, ordered refund after 10% deduction with 10.80% interest.
- RERA-GRG-2503-2025 (complaint, decided 30-Jan-2026): Buyer's unit cancelled for non-payment; HRERA upheld cancellation, ordered refund after 10% deduction with 10.80% interest.
- RERA-GRG-2523-2025 (complaint, decided 30-Jan-2026): Buyer's unit cancelled for non-payment; HRERA upheld cancellation and ordered refund after 10% deduction with 10.80% interest.
- RERA-GRG-2529-2025 (complaint, decided 30-Jan-2026): Buyers challenged unit cancellation over unpaid dues; HRERA upheld cancellation, ordered refund after 10% deduction with 10.80% interest.
- RERA-GRG-2538-2025 (complaint, decided 30-Jan-2026): Buyer's unit was cancelled for non-payment; builder ordered to refund after 10% deduction with 10.80% interest.
- RERA-GRG-2506-2025 (complaint, decided 30-Jan-2026): Buyer sought relief against unit cancellation; HRERA upheld cancellation, ordered refund after 10% deduction with 10.80% interest.
- RERA-GRG-212-2025 (complaint, decided 13-Jan-2026): Buyer sought possession and assured returns; builder ordered to pay 10.80% delay interest and hand over unit in 30 days.
- RERA-GRG-210-2025 (complaint, decided 13-Jan-2026): Buyer sought possession after delay; builder ordered to pay 10.80% delay interest, hand over possession and execute conveyance deed.
- RERA-GRG-211-2025 (complaint, decided 13-Jan-2026): Buyer sought possession after delay; builder ordered to pay 10.80% delay interest and hand over unit within 30 days.
- RERA-GRG-3285-2022 (complaint, decided 09-Jul-2024): Buyer sought possession and assured return after delay; builder ordered to hand over unit, pay arrears and outstanding assured return.
- RERA-GRG-5367-2022 (complaint, decided 15-May-2024): Buyer sought refund of paid amount after earlier complaint; HRERA dismissed the new complaint as barred by res judicata.
- RERA-GRG-6619-2022 (complaint, decided 15-Feb-2024): Buyer sought reinstatement after cancellation for non-payment; builder ordered to restore unit and issue a fresh statement at 10.85% interest.
- RERA-GRG-2357-2022 (complaint, decided 15-Dec-2023): Buyers sought possession and assured return after delay; HRERA ordered builder to pay delay interest at 10.85% p.a. from 25 Nov 2017.
|
|---|
| Decided cases against REAL TOWN PROPERTIES PVT LTD (all its projects) | 9 (Complaint: 9) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in