Aarohan Phase I
Vipul · Sector 53, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jun 2022)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Failed to submit quarterly progress report; show-cause notice issued to builder (May 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2023, open)
- Did not file REP-I project details online or in hard copy; quarterly progress reports not filed (Nov 2019, open). At stake: Rs 25,000 per day from 31 Dec 2019, up to 5% of project cost
- 2 more cases: reply 4
Will it be delivered on time?
- Deadline Jun 2022, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2 BHK
- 3 BHK
Location
- Nearest metro: Sector 54 Chowk, 4.3 km by road (11 min by car)
- Cyber City 18 min · Airport 35 min by car at 9:30 am
- Within 3 km: 9 hospitals, 12 schools, 5 malls
The builder: Vipul
- 3 projects registered in Gurugram, 3 lapsed
- 0 with an occupation certificate on record
- 97 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | AAROHAN PHASE I |
|---|---|
| Builder (promoter) | VIPUL LTD. |
| Location | SECTOR -53, GURUGRAM |
| RERA project ID | RERA-GRG-452-2019 |
| Registration certificate number | 131 OF 2017 DATED 28.08.2017 (SUPERSEDED BY GGM/554/286/2022/29 DATED 25.04.2022) |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/06/2022 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 19.244 acres |
| Licence | 168-172 of 2004 dated 16.12.2004, 545-546 of 2006 dated 13.03.2006 |
| Estimated cost of the project | ₹84,387 lakh (₹843.87 crore) |
| Total units (plots, apartments, shops) | 382 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 2 BHK; 3 BHK (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | 115 |
| Units unsold when registered | 267 |
| Layout plan approved on | 30-11-2016 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-06-2022 |
|---|---|
| Revised completion date | 30-06-2022 |
| Infrastructure: projected completion | 30-06-2022 |
| Infrastructure: percentage complete when registered | 0% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against VIPUL LTD. (all its projects) | 97 (Complaint: 81; Execution of an earlier order: 14; Compensation: 2) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026