Projects · PIVOTAL INFRASTRUCTURE PVT LTD
Affordable Group Housing Colony
Pivotal Infrastructure · Sector 62, Gurugram
Registered with RERA: Sep 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till May 2021)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Failed to apply to extend registration; no completion, part-completion or occupation certificate submitted (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- Did not submit quarterly progress report (Jun 2022, open)
- 3 more cases: reply 4
- 1 complaint about this project decided by HRERA since Nov 2023 (1 delay interest ordered)
Will it be delivered on time?
- Deadline Jul 2021, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
What's on offer?
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 1 BHK: 306 sq ft carpet, 180 units
- 2 BHK: 574–645 sq ft carpet, 560 units
Location
- Nearest metro: Sector 55–56, 2.4 km by road (11 min by car)
- Cyber City 34 min · Airport 51 min by car at 9:30 am
- Within 3 km: 10 hospitals, 24 schools, 5 malls
Location shown for Sector 62; the exact site was not found.
The builder: Pivotal Infrastructure
- 3 projects registered in Gurugram, 3 lapsed
- 0 with an occupation certificate on record
- 128 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | AFFORDABLE GROUP HOUSING COLONY |
|---|---|
| Builder (promoter) | PIVOTAL INFRASTRUCTURE PVT LTD |
| Location | SECTOR 62, ULLAHAWAS, GURUGRA M |
| RERA project ID | RERA-GRG-420-2019 |
| Registration certificate number | 178 OF 2017 DATED 01.09.2017 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 29/05/2021 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 5.06875 acres |
| Licence | 5 of 2016 (30.05.2016) |
| Estimated cost of the project | ₹15,947 lakh (₹159.47 crore) |
| Total units (plots, apartments, shops) | 740 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 1 BHK: 306 sq ft carpet, 180 units; 2 BHK: 574–645 sq ft carpet, 560 units (source: the builder's registration form (Form A-H)) |
| Units booked when registered | 740 |
| Units unsold when registered | 0 |
| Layout plan approved on | 25-07-2016 |
| Building plans approved on | 25-07-2016 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 27-07-2021 |
|---|---|
| Revised completion date | 27-07-2021 |
| Infrastructure: projected completion | 27-07-2021 |
| Infrastructure: percentage complete when registered | 45% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/12/2024 (OCT-DEC) |
| Latest report submitted on | 13-Sep-2025 |
| Quarterly reports listed on the portal | 25 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2024 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹178.71 lakh (₹1.79 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹86.05 lakh (₹0.86 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹5.99 lakh (₹0.06 crore) |
| Project bank account (escrow): deposited in the quarter | ₹178.71 lakh (₹1.79 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹178.71 lakh (₹1.79 crore) |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 740 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹920.5 lakh (₹9.21 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|---|
| Cases | |
| Decided cases against PIVOTAL INFRASTRUCTURE PVT LTD (all its projects) | 128 (Complaint: 106; Execution of an earlier order: 20; Compensation: 2) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in