RERA’d by NeevHQ

Projects · ADVANCE INDIA PROJECTS LTD.

AIPL Joy Square

Advance India Projects · Sector 63A, Gurugram

Registered with RERA: Oct 2017

Is it legal?

Will it be delivered on time?

Location

Location shown for Sector 63A; the exact site was not found.

The builder: Advance India Projects

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameAIPL JOY SQUARE
Builder (promoter)ADVANCE INDIA PROJECTS LTD.
LocationSECTOR-63A, VILLAGE KADARPUR, TEHSIL AND DIST. GURUGRAM
RERA project IDRERA-GRG-591-2020
Registration certificate number259 OF 2017 DATED 03.10.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2022
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area2.838 acres
Licence119 of 2011 (28-12-2011) and 71 of 2014 (29-07-2014)
Estimated cost of the project₹25,822.38 lakh (₹258.22 crore)
Total units (plots, apartments, shops)577
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered406
Units unsold when registered171
Layout plan approved on18-09-2019
Building plans approved on18-09-2019

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-12-2022
Revised completion date31-12-2022
Infrastructure: projected completion31-12-2022
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2024 (APR-JUN)
Latest report submitted on24-Jul-2024
Quarterly reports listed on the portal23

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2024 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹1,303.05 lakh (₹13.03 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹575.49 lakh (₹5.75 crore)
Spent on infrastructure in the quarter₹159.49 lakh (₹1.59 crore)
Other costs in the quarter (EDC, taxes, etc.)₹383.21 lakh (₹3.83 crore)
Project bank account (escrow): deposited in the quarter₹912.14 lakh (₹9.12 crore)
Project bank account (escrow): withdrawn in the quarter₹963 lakh (₹9.63 crore)
Project bank account (escrow): balance at quarter end₹27.3 lakh (₹0.27 crore)
Units in the project (apartments / plots)576 apartments
Sold in the quarter3 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 06-11-2015
  • Zoning Plan: Obtained Approval 05-08-2015
  • Service Plans: Obtained Approval 10-12-2012
  • Electricity Plans: Obtained Approval 30-09-2019
  • Site Plans: Obtained Approval 06-11-2015
  • Building Plans: Obtained Approval 18-09-2019
  • Fire NOC: Obtained Approval 06-12-2019

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 03 Jul 2024, for 30 Jun 2024
By part
  • Sub structure: 100%
  • Super structure: 100%
  • Mechanical (MEP): 100%
  • Electrical (MEP): 100%
  • Plumbing and firefighting (MEP): 100%
  • Internal finishing: 98%, Lift lobbies and common areas work in progress
  • External finishing: 99%
Unclear in the certificate
  • Table A is headed for a building/tower but the tower number is left blank, so the figures are read as project-wide cumulative figures.
  • The note on billing (about Rs. 93.47 crores billed against a budget of Rs. 124.00 crores) is partly garbled and is not used here.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed4
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project9
Cases
Decided cases against ADVANCE INDIA PROJECTS LTD. (all its projects)94 (Complaint: 85; Compensation: 7; Execution of an earlier order: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in