Projects · ADVANCE INDIA PROJECTS LTD.
AIPL Joy Street
Advance India Projects · Sector 66, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Dec 2020 (date has passed)
- HRERA has opened 7 cases of its own against the builder over this project (7 open):
- Did not submit quarterly progress report (May 2022, open)
- Did not apply to extend registration; did not submit completion or occupation certificate, or required documents (Jun 2022, open)
- Did not complete the project within the time it declared (Jun 2022, open)
- 4 more cases: reply 4
- 16 complaints about this project decided by HRERA since Nov 2023 (1 delay interest ordered, 5 refund ordered, 3 assured return ordered, 1 compensation ordered, 6 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Jun 2021, never extended (date has passed)
- Occupation certificate (Sep 2020) covers: Commercial building, ground to 15th floor, and basements (no flats listed)
- Construction, as certified by the architect (Oct–Dec 2023):
- Money: ₹414.2 crore spent of ₹434.8 crore; ₹20.6 crore still to spend (CA certificate, Dec 2023)
Location
- Nearest metro: Sector 55–56, 7 km by road (23 min by car)
- Cyber City 47 min · Airport 58 min by car at 9:30 am
- Within 3 km: 9 hospitals, 12 schools, 6 malls
The builder: Advance India Projects
- 7 projects registered in Gurugram
- 5 with an occupation certificate on record
- 94 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | AIPL JOY STREET |
|---|
| Builder (promoter) | ADVANCE INDIA PROJECTS LTD. |
|---|
| Location | SECTOR-66, VILLAGE MEDAWAS & BADSHAHPUR, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-599-2020 |
|---|
| Registration certificate number | 157 OF 2017 DATED 28.08.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 31/12/2020 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 3.95 acres |
|---|
| Licence | . 07 of 2008 (21-01-2008) and License no. 152 of 2008 (30-07-2008) |
|---|
| Estimated cost of the project | ₹43,483.9 lakh (₹434.84 crore) |
|---|
| Total units (plots, apartments, shops) | 634 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 602 |
|---|
| Units unsold when registered | 32 |
|---|
| Layout plan approved on | 31-01-2020 |
|---|
| Building plans approved on | 31-01-2020 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-12-2020 |
|---|
| Revised completion date | 30-06-2021 |
|---|
| Infrastructure: projected completion | 30-06-2021 |
|---|
| Infrastructure: percentage complete when registered | 70% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/12/2023 (OCT-DEC) |
|---|
| Latest report submitted on | 16-Feb-2024 |
|---|
| Quarterly reports listed on the portal | 21 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2023 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹64.7 lakh (₹0.65 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹45.29 lakh (₹0.45 crore) |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹44.84 lakh (₹0.45 crore) |
|---|
| Project bank account (escrow): balance at quarter end | ₹0.45 lakh (₹0 crore) |
|---|
| Units in the project (apartments / plots) | 634 apartments |
|---|
| Sold in the quarter | 2 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹1,508.53 lakh (₹15.09 crore) paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 14-07-2016
- Zoning Plan: Obtained Approval 16-06-2010
- Service Plans: Obtained Approval 22-06-2020
- Electricity Plans: Obtained Approval 16-12-2020
- Site Plans: Obtained Approval 30-05-2019
- Building Plans: Obtained Approval 19-07-2017
- Fire NOC: Obtained Approval 15-07-2020
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 09 Jan 2024, for 31st December 2023 |
|---|
| By part | - Tower 1: 100%, Table A shows 100% for sub structure, super structure, MEP and finishing. Building is G+15 with three basements. No work value is recorded as done during the quarter.
- Internal roads & pavements: 100%
- Parking: 100%, Covered parking 509, open parking 90
- Water supply: 100%
- Sewerage (chamber, lines, septic tanks, STP): 100%
- Storm water drains: 100%
- Landscaping & tree plantation: Not proposed
- Parks and playgrounds: Not proposed
- Shopping area: Not proposed
- Street lighting/electrification: 100%
- Treatment and disposal of sewage and sullage water/STP: 100%
- Water conservation, rain water harvesting, percolating well/pit: 100%
- Fire protection and fire safety requirements: 100%
- Electrical meter room, sub-station, receiving station: 100%
- Rain Water Harvesting: 100%
- Underground Tank: 100%
|
|---|
| Unclear in the certificate | - Table A row for fixing of door and window frames in flats says 'WIP' but shows 100%.
- Table A rows for sanitary fixtures, modular kitchen and gas piping within flats are blank.
- The electrical figure in Table A (section 3.2) appears struck through or smudged in the scan.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Occupation Certificate (Form BR-VII) dated 28 Sep 2020: covers Commercial Building (Tower/Block: Commercial Building), Ground Floor to 15th Floor, in the Commercial Colony measuring 3.9562 acres at Sector-66, Gurugram Manesar Urban Complex. Non-FAR areas also covered: Basement-1, Basement-2, Basement-3, Service Floor at 4th Floor, Guard Room (4 nos.), Metre Room, Transformer Room and HT Room, and Mumty and Machine Room.. Addressed to Landmark Apartments Pvt. Ltd.. Composition fees for variations from approved plans: ₹6,70,476. Unclear in the document: The memo number handwritten after 'ZP-483/SD(DK)/2020/' is hard to read in the scan.; The endorsement number and date after 'Endst. No. ZP-483/SD(DK)/2020/' are blank.
|
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 7 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 6 |
|---|
| Proceedings | - RERA-GRG-2766-2022: Case listed as HARERA Gurugram versus Advance India Projects Ltd (promoter). The page does not describe the matter being dealt with. Status: The page says the online complaint has not yet been received at the office. Complaint dispatch shows 'Not Yet'. No hearing date is listed and no hearings or orders are shown.
- RERA-GRG-3082-2022: The Authority issued a show cause notice to the promoter, Advance India Projects Ltd, for not submitting its quarterly progress report. The promoter was asked to appear before the Authority at a first hearing or send a written reply. Status: First hearing was listed for 27 Jun 2022. The page shows the status as First Hearing, with no proceedings or order recorded. Latest: 27 Jun 2022, First hearing was listed. The page shows the status as First Hearing, with no proceedings or order recorded and no order uploaded.
- RERA-GRG-3122-2022: Show cause notice to the promoter for not applying to extend the project registration, and for not submitting a completion certificate, part completion certificate or occupation certificate, and the required documents. The Authority started this case itself. The promoter is Advance India Projects Ltd. Status: First hearing listed for 28 Jun 2022. The page shows no proceedings, bench order or outcome for that hearing. Latest: 28 Jun 2022, First hearing listed. The status shows First Hearing, with no proceedings or order recorded.
- RERA-GRG-3123-2022: Show-cause notice to the promoter Advance India Projects Ltd for not completing the project within the time it declared, under section 4(2)(l)(C) of the RERA Act Status: First hearing listed for 30 Jun 2022. The page shows no proceedings, bench order or order for that hearing. Latest: 30 Jun 2022, First hearing listed. Proceedings of the day, bench and order fields are blank on the page.
- RERA-GRG-3124-2022: Show cause notice issued to the promoter Advance India Projects Ltd. for not applying to extend its registration, and for not submitting a completion certificate, part completion certificate or occupation certificate, along with the requisite documents. The page records the registration certificate as expired. Status: First hearing was listed for 28 Jun 2022. The page shows the status as First Hearing, with no proceedings or order recorded for that day. Latest: 28 Jun 2022, First hearing was listed. No proceedings, bench order or order upload is shown on the page.
- RERA-GRG-4999-2022: A complaint filed with the Authority against the promoter Advance India Projects Ltd. The page shows the party as HARERA Gurugram through a named representative, and the complaint is recorded as 'Self'. The page does not clearly show that the Authority itself started the case, as the user's note says. Status: The case is at the first hearing stage. The page lists the first hearing for 30 Jun 2022 but records no proceedings of the day and no order. Latest: 16 Jul 2022, Document submitted under Dak ID 38073, recorded with the remark 'New Complaint'.
- RERA-GRG-5343-2019: Promoter Advance India Projects Ltd. has not filed project updates (REP-I Part A-H, quarterly progress reports) on the Authority's web portal for the AIPL Joy Street project in Sector 66, Gurugram. The Authority started the proceeding itself and has issued notices and directions. Status: Listed at the First Hearing stage. The next hearing was fixed for 24 Feb 2020 and its status shows PENDING. The latest dated item on the page is the sixth notice dated 03 Sep 2020. No final order is shown. Latest: 03 Sep 2020, Sixth notice dispatched asking for compliance with section 42 of the Act. Penalty: Rs 25,000 per day from 31 Dec 2019 while the default continues. The penalty may cumulatively extend up to five percent of the estimated cost of the real estate project, as determined by the Authority. The Authority also said that if the promoter does not comply within one month of receiving the show cause notice, it may show cause why its registration should not be revoked.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 16 |
|---|
| Cases | - RERA-GRG-5821-2025 (complaint, decided 17-Jul-2026): Buyer sought delay interest and other relief; builder ordered to pay 10.80% interest for delay and execute conveyance deed.
- RERA-GRG-4529-2024 (compensation, decided 25-Mar-2026): Buyer sought compensation over an unleased commercial unit and possession; HRERA dismissed the complaint.
- RERA-GRG-1160-2024 (complaint, decided 20-Jan-2026): Food court buyer sought physical possession of leased unit; HRERA dismissed the complaint, as the unit was meant for leasing.
- RERA-GRG-4561-2024 (complaint, decided 20-Jan-2026): Buyers complained of commercial unit leased to a gym without consent at low rent; HRERA dismissed the complaint.
- RERA-GRG-1201-2023 (compensation, decided 07-Jan-2026): Buyer sought rent compensation after promised leasing failed; builder ordered to pay Rs 25,807 monthly with 10.85% interest.
- RERA-GRG-712-2024 (complaint, decided 20-Nov-2025): Buyer's unit cancelled for non-payment; builder ordered to refund paid amount minus 10% earnest money, with 10.85% interest.
- RERA-GRG-5216-2023 (complaint, decided 13-Nov-2025): Buyer sought refund of a commercial unit after leasing promise failed; builder ordered to refund with 10.85% interest.
- RERA-GRG-3785-2024 (complaint, decided 04-Sep-2025): Buyer sought refund after builder terminated allotment; builder ordered to refund paid amount minus 10% earnest money, with 10.85% interest.
- RERA-GRG-5865-2024 (complaint, decided 12-Aug-2025): Buyer sought possession, delay compensation and refunds after a delayed unit; HRERA dismissed the complaint as possession was offered before the due date.
- RERA-GRG-2966-2024 (complaint, decided 04-Jul-2025): Buyers sought lease rental, delay charges and refunds; HRERA ordered builder to pay Rs 50,100 monthly lease rental for three years.
- RERA-GRG-2185-2021 (complaint, decided 27-May-2025): Retail unit buyer sought delay compensation; HRERA ordered 11.10% delay possession charges from June 2020 to December 2020, less assured return already paid.
- RERA-GRG-7161-2022 (complaint, decided 10-Dec-2024): Buyer sought delay compensation and assured return; HRERA ordered assured return till offer date, quashed labour cess and sinking fund, and barred holding charges.
- RERA-GRG-7164-2022 (complaint, decided 10-Dec-2024): Buyer sought delay compensation and assured return; HRERA ordered assured return till offer date, quashed labour cess and sinking fund, and barred holding charges.
- RERA-GRG-963-2021 (complaint, decided 29-Mar-2024): Buyers sought refund after possession delay; HRERA ordered builder to refund Rs 90.77 lakh with 10.85% interest.
- RERA-GRG-3258-2021 (complaint, decided 05-Mar-2024): Buyer sought possession, delay charges and assured returns for a shop; dismissed as the same matter is pending in civil court.
- RERA-GRG-3256-2021 (complaint, decided 05-Mar-2024): Buyer sought possession, delay charges and assured returns for a shop; dismissed as the same matter is pending in civil court.
|
|---|
| Decided cases against ADVANCE INDIA PROJECTS LTD. (all its projects) | 94 (Complaint: 85; Compensation: 7; Execution of an earlier order: 2) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in