Projects · RAHEJA DEVELOPERS LTD.
Amaltaas Tower (Tower-B)
Raheja Developers · Sector 99, Gurugram
Registered with RERA: Jul 2017
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Jul 2022)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit quarterly progress report (May 2022, open)
- Did not upload required project updates (REP-I Part A-H) on webpage (Nov 2019, open). At stake: Authority decided ₹25,000 a day penalty while default continues; up to 5% of project cost
- Changed project bank accounts without approval; did not file quarterly progress reports, audit reports or reconciliation (Jun 2022, open). At stake: show-cause on penalty under section 60 of the Act; no amount stated
- 3 more cases: reply 4
Will it be delivered on time?
- Deadline Dec 2022, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Apr–Jun 2025):
- In progress: Common areas and amenities 0%
- Money: ₹51.7 crore spent of ₹109 crore; ₹57.3 crore still to spend (CA certificate, Jun 2025)
What's on offer?
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 2 BHK: 807–975 sq ft carpet, 116 units
- 3 BHK: 1,083–1,251 sq ft carpet, 12 units
Location
- Nearest metro: IFFCO Chowk, 15.4 km by road (47 min by car)
- Cyber City 55 min · Airport 34 min by car at 9:30 am
- Within 3 km: 1 hospital, 0 schools, 1 mall
Location shown for Sector 99; the exact site was not found.
The builder: Raheja Developers
- 10 projects registered in Gurugram, 10 lapsed
- 0 with an occupation certificate on record
- 320 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | AMALTAAS TOWER (TOWER-B) |
|---|---|
| Builder (promoter) | RAHEJA DEVELOPERS LTD. |
| Location | RAHEJA VANYA SECTOR-99-A, GUR UGRAM |
| RERA project ID | RERA-GRG-549-2020 |
| Registration certificate number | 18 OF 2017 DATED 06.07.2017 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 05/07/2022 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 2.21 acres |
| Licence | 64 of 2013 and 72 of 2014 |
| Estimated cost of the project | ₹9,829 lakh (₹98.29 crore) |
| Total units (plots, apartments, shops) | 139 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 2 BHK: 807–975 sq ft carpet, 116 units; 3 BHK: 1,083–1,251 sq ft carpet, 12 units (source: the builder's registration form (Form A-H)) |
| Units booked when registered | 23 |
| Units unsold when registered | 116 |
| Layout plan approved on | 02-01-2017 |
| Building plans approved on | 02-01-2017 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 01-12-2022 |
|---|---|
| Revised completion date | 31-12-2022 |
| Infrastructure: projected completion | 31-12-2022 |
| Infrastructure: percentage complete when registered | 0% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/06/2025 (APR-JUN) |
| Latest report submitted on | 28-Aug-2025 |
| Quarterly reports listed on the portal | 27 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2025 (APR-JUN))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹1,694.96 lakh (₹16.95 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹2,607.03 lakh (₹26.07 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 139 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹467.51 lakh (₹4.68 crore) paid; ₹1,150.77 lakh (₹11.51 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 16 Jul 2025, for 30 Jun 2025 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against RAHEJA DEVELOPERS LTD. (all its projects) | 320 (Complaint: 252; Compensation: 32; Execution of an earlier order: 36) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in