Projects · 4S DEVELOPERS PVT. LTD.
Aradhya Homes
4S Developers · Sector 67, Gurugram
Registered with RERA: Jun 2020
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Sep 2021)
- HRERA has opened 4 cases of its own against the builder over this project (4 open):
- Did not submit quarterly progress report, per Authority's show-cause notice (May 2022, open)
- Did not apply to extend registration, submit completion or occupation certificate, or required documents (Jun 2022, open)
- Did not complete the project within the time period it declared (Jun 2022, open)
- 1 more case: reply 4
- 5 complaints about this project decided by HRERA since Nov 2023 (4 refund ordered, 1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Sep 2021, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Quarterly progress report shown as "not uploaded" by HRERA
What's on offer?
- 172 units in 2 sizes, as declared to HRERA:
- 52 units of 1,615 sq ft carpet (1 tower)
- 120 units of 1,776 sq ft carpet (1 tower)
- HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
- 43 plots, 274–299 sq yd
Location
- Nearest metro: Sector 55–56, 9.9 km by road (35 min by car)
- Cyber City 58 min · Airport 66 min by car at 9:30 am
- Within 3 km: 12 hospitals, 22 schools, 2 malls
The builder: 4S Developers
- 4 projects registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 5 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ARADHYA HOMES |
|---|---|
| Builder (promoter) | 4S DEVELOPERS PVT. LTD. |
| Location | SECTOR 67-A, GURUGRAM, HARYAN A |
| RERA project ID | RERA-GRG-652-2020 |
| Registration certificate number | GGM/411/143/2020/27 DATED 22.06.2020 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/09/2021 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 10464 acres |
| Licence | Land Owner |
| Estimated cost of the project | ₹9,927.98 lakh (₹99.28 crore) |
| Total units (plots, apartments, shops) | 215 |
| Unit sizes (carpet area, as declared) | 52 units of 1,615 sq ft carpet (1 tower); 120 units of 1,776 sq ft carpet (1 tower) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 15-04-2020 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 15-04-2020 |
|---|---|
| Likely completion date | 30-09-2021 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in