RERA’d by NeevHQ

Projects · UDAY BUILDLWELL PRIVATE LIMITED

Arden 45

Uday Buildlwell · Sector 45, Gurugram

Registered with RERA: Apr 2024

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Uday Buildlwell

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameARDEN 45
Builder (promoter)UDAY BUILDLWELL PRIVATE LIMITED
LocationVILLAGE KANHAI, SECTOR-45
RERA project IDRERA-GRG-1517-2023
Registration certificate numberGGM/817/549/2024/44 DATED 22.04.2024
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to31/10/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area1.025 acres
Licence204 OF 2022 for 0.65 Acres and 189 of 2023 for 0.375 Acres
Estimated cost of the project₹22,666.08 lakh (₹226.66 crore)
Total units (plots, apartments, shops)279
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered4
Units unsold when registered275
Layout plan approved on12-01-2024
Building plans approved on12-01-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-10-2026
Revised completion date31-10-2026
Infrastructure: projected completion30-04-2026
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on13-Nov-2026
Quarterly reports listed on the portal9

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹-66 lakh (₹-0.66 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹219.13 lakh (₹2.19 crore)
Spent on construction of apartments in the quarter₹153.13 lakh (₹1.53 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹25.75 lakh (₹0.26 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)279 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹553.42 lakh (₹5.53 crore) paid; ₹553.42 lakh (₹5.53 crore) due
Approvals listedNot found in the records checked

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026
Overall work complete53%
By part
  • Tower A: 80%, Sub-structure 90% and super-structure 85% cumulative; 5 slabs laid; MEP and finishing partly done
  • Tower B: 33%, Sub-structure 95% and super-structure 20% cumulative; MEP and finishing at 0%
Unclear in the certificate
  • The certificate does not name the quarter it reports on.
  • Annexure A gives overall progress of 53% as of 30.06.2026 and the project status as on 30.09.2026; the two dates are not explained.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against UDAY BUILDLWELL PRIVATE LIMITED (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026