RERA’d by NeevHQ

Projects · INTERNATIONAL LAND DEVELOPERS PVT. LTD.

Arete, Phase I

International Land Developers · Sector 33, Gurugram

Registered with RERA: Feb 2019

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: International Land Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameARETE, PHASE I
Builder (promoter)INTERNATIONAL LAND DEVELOPERS PVT. LTD.
LocationSECTOR- 33, SOHNA, GURUGRAM
RERA project IDRERA-GRG-151-2019
Registration certificate numberGGM/312/44/2019/06 DATED 08.02.2019
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to02/07/2022
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area11.6125 acres
Licence44 OF 2013
Estimated cost of the project₹35,479 lakh (₹354.79 crore)
Total units (plots, apartments, shops)556
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder2 BHK: 667–699 sq ft carpet, 344 units; 3 BHK: 1,041–1,222 sq ft carpet, 194 units (source: the builder's registration form (Form A-H))
Units booked when registered274
Units unsold when registered280
Layout plan approved on14-05-2014
Building plans approved on25-05-2015

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-03-2021
Revised completion date31-03-2023
Infrastructure: projected completion31-03-2023
Infrastructure: percentage complete when registered14%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2026 (APR-JUN)
Latest report submitted on09-Jul-2026
Quarterly reports listed on the portal29

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)553 apartments, 553 plots
Sold in the quarter273 apartments, 273 plots
EDC (development charges): paid / due as on date₹451 lakh (₹4.51 crore) paid; ₹10,189 lakh (₹101.89 crore) due
Approvals listed
  • Layout Plan: Obtained Approval 01-05-2015
  • Demarcation Plan: Obtained Approval 01-05-2012
  • Zoning Plan: Obtained Approval 10-06-2014
  • Service Plans: Obtained Approval 29-11-2014
  • Electricity Plans: Obtained Approval 06-02-2014
  • Site Plans: Obtained Approval 10-06-2014
  • Building Plans: Obtained Approval 25-05-2015
  • Fire NOC: Obtained Approval 21-07-2016

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 08 Jul 2026, for 30 Jun 2026
By part
  • Tower 1: Sub-structure 100% complete. Super-structure 77.7%. Mechanical 0%, electrical 6%, plumbing and firefighting 18%, internal finishing 6%, external finishing 0%. Cumulative slabs laid by end of quarter: 17.5.
  • Tower 2: Sub-structure 100% complete. Super-structure 80%. Mechanical 0%, electrical 6%, plumbing and firefighting 18%, internal finishing 6%, external finishing 0%.
Unclear in the certificate
  • Table A for Tower 1 has a slab row that refers to 'tower 1B'; the tower name there is unclear.
  • Table A is provided only for Towers 1 and 2. Towers 3 to 6 and Table B are not in the copy provided.
  • Tower 1 Table A shows 77.7% for slabs and 0% for floor-wise slab status; the 0% entry is not explained.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusScrutinized: 1; Pending: 3; First Hearing: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project6
Cases
Decided cases against INTERNATIONAL LAND DEVELOPERS PVT. LTD. (all its projects)64 (Complaint: 42; Execution of an earlier order: 6; Compensation: 16)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in