Ashiana Anmol Phase III & Plaza Ph II

Ashiana Housing · Sector 33, Gurugram

Registered with RERA: Jun 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 33; the exact site was not found.

The builder: Ashiana Housing

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameASHIANA ANMOL PHASE III & PLAZA PH II
Builder (promoter)ASHIANA HOUSING LIMITED
LocationVILL. DHUNELA SEC 33 SOHNA
RERA project IDRERA-GRG-929-2021
Registration certificate numberGGM/579/311/2022/54 DATED 27.06.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2028
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area6.7879 acres
Licence20 0f 2014 dt 11.06.2014 valid upto 10.06.2026
Estimated cost of the project₹23,119.09 lakh (₹231.19 crore)
Total units (plots, apartments, shops)468
Unit sizes (carpet area, as declared)138 units of 174 sq ft carpet (1 tower); 90 units of 780 sq ft carpet (1 tower); 180 units of 996 sq ft carpet (1 tower); 30 units of 1,180 sq ft carpet (1 tower); 30 units of 1,262 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on05-03-2021
Building plans approved on05-03-2021

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-02-2023
Likely completion date31-12-2028

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal17

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹1,712.54 lakh (₹17.13 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹466.35 lakh (₹4.66 crore)
Spent on infrastructure in the quarter₹98.15 lakh (₹0.98 crore)
Other costs in the quarter (EDC, taxes, etc.)₹132.22 lakh (₹1.32 crore)
Project bank account (escrow): deposited in the quarter₹1,198.78 lakh (₹11.99 crore)
Project bank account (escrow): withdrawn in the quarter₹1,305.53 lakh (₹13.06 crore)
Project bank account (escrow): balance at quarter end₹24.34 lakh (₹0.24 crore)
Units in the project (apartments / plots)300 apartments
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 05-05-2021
  • Demarcation Plan: Obtained Approval 09-09-2013
  • Zoning Plan: Obtained Approval 08-09-2014
  • Service Plans: Obtained Approval 17-12-2021
  • Electricity Plans: Obtained Approval 13-01-2015
  • Site Plans: Obtained Approval 05-05-2021
  • Building Plans: Obtained Approval 05-05-2021
  • Fire NOC: Obtained Approval 22-12-2021

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 13 Oct 2026, for Sept-2026
By part
  • Towers T9, T10, T11, T12 & T13 (superstructure slabs): 75 out of 75 slabs laid by end of quarter
  • Excavation (sub-structure): 100%
  • Raft foundation: 100%
  • Basement level 1: 100%
  • Stilt / ground floor: 100%
  • Walls on floors: 100%
  • External wall finishing: 100%
  • Internal wall finishing: 100%
  • Waterproofing of terraces: 100%
  • Entrance lobby finishing: 100%
  • Compound wall: 100%
  • Lifts installation: 100%
  • Internal roads & pavements: 100%
  • Parking: 100%
  • Water supply: 100%
  • Sewerage (chamber, lines, septic tank, STP): 100%
  • Storm water drains: 100%
  • Landscaping & tree plantation: 100%
  • Parks and playgrounds: 100%
  • Children play equipment: 100%
  • Benches: 100%
  • Shopping area: 0%
  • Street lighting / electrification: 100%
  • Treatment and disposal of sewage / STP: 100%
  • Solid waste management & disposal: 100%
  • Water conservation and rain water harvesting: 100%
  • Energy management (solar): 100%
  • Fire protection and fire safety: 100%
  • Electrical meter room, sub-station, receiving station: 100%
Unclear in the certificate
  • Table A is not split by tower; the tower/building number field is blank, so tower-wise percentages are not given except for the slab count.
  • Table A total area on each floor is blank.
  • Table B-3 and B-4 community building and service rows are blank; schools and club rows have no entries.
  • Table B covered parking number is blank.
  • Table A rows for mechanical works are marked NA, and compliance to environment/CRZ NOC is marked Done without a percentage.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against ASHIANA HOUSING LIMITED (all its projects)1 (Complaint: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in