Projects · ORRIS INFRASTRUCTURE PVT LTD
Aster Court Premier
Orris Infrastructure · Sector 85, Gurugram
Registered with RERA: Oct 2018
Is it legal?
- RERA registration marked "Lapsed" by HRERA (was valid till Dec 2025)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit quarterly progress report; show-cause notice issued 31 May 2022 (May 2022, open)
- Failed to apply for registration extension, submit completion or occupation certificate, or requisite documents (Jun 2022, open)
- Did not complete the project within the time it declared (Jun 2022, open)
- 3 more cases: reply 4
- 3 complaints about this project decided by HRERA since Nov 2023 (1 delay interest ordered, 1 refund ordered, 1 compensation ordered)
Will it be delivered on time?
- Original deadline Jun 2020, extended to Dec 2025
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2025):
- Done: Tower 3o, Tower 3l, Tower 3m
- Money: ₹328.4 crore spent of ₹305.2 crore (CA certificate, Sep 2025)
What's on offer?
- Registration now covers 262
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 3 BHK: 1,240 sq ft carpet, 126 units
- 4 BHK: 1,513 sq ft carpet, 136 units
Location
- Nearest metro: Millennium City Centre Gurugram, 19 km by road (52 min by car)
- Cyber City 58 min · Airport 43 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
The builder: Orris Infrastructure
- 4 projects registered in Gurugram, 3 lapsed
- 0 with an occupation certificate on record
- 125 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ASTER COURT PREMIER |
|---|---|
| Builder (promoter) | ORRIS INFRASTRUCTURE PVT LTD |
| Location | SECTOR-85, BADHA, MANESAR |
| RERA project ID | RERA-GRG-415-2019 |
| Registration certificate number | GGM/287/2018/19 DATED 13.10.2018 |
| Registration status | Marked "Lapsed Project" on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2025 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 5.90625 acres |
| Licence | 39 OF 2009 (24.07.2009), 99 OF 2011 (17.11.2011) |
| Estimated cost of the project | ₹30,515.76 lakh (₹305.16 crore) |
| Total units (plots, apartments, shops) | 262 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | 3 BHK: 1,240 sq ft carpet, 126 units; 4 BHK: 1,513 sq ft carpet, 136 units (source: the builder's registration form (Form A-H)) |
| Units booked when registered | 128 |
| Units unsold when registered | 134 |
| Layout plan approved on | 10-04-2012 |
| Building plans approved on | 10-04-2012 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-06-2020 |
|---|---|
| Revised completion date | 30-06-2020 |
| Infrastructure: projected completion | 30-06-2020 |
| Infrastructure: percentage complete when registered | 17.09% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2025 (JUL-SEP) |
| Latest report submitted on | 30-Jun-2026 |
| Quarterly reports listed on the portal | 27 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2025 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹1.27 lakh (₹0.01 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹1.07 lakh (₹0.01 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 262 apartments |
| Sold in the quarter | Not found in the records checked |
| EDC (development charges): paid / due as on date | ₹1,818.98 lakh (₹18.19 crore) paid; ₹0 due |
| Approvals listed | Not found in the records checked |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 11 Oct 2025, for 30 Sep 2025 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 3 |
|---|---|
| Cases |
|
| Decided cases against ORRIS INFRASTRUCTURE PVT LTD (all its projects) | 125 (Complaint: 100; Execution of an earlier order: 12; Compensation: 13) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in