Aster Court Premier

Orris Infrastructure · Sector 85, Gurugram

Registered with RERA: Oct 2018

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Orris Infrastructure

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameASTER COURT PREMIER
Builder (promoter)ORRIS INFRASTRUCTURE PVT LTD
LocationSECTOR-85, BADHA, MANESAR
RERA project IDRERA-GRG-415-2019
Registration certificate numberGGM/287/2018/19 DATED 13.10.2018
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to31/12/2025
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area5.90625 acres
Licence39 OF 2009 (24.07.2009), 99 OF 2011 (17.11.2011)
Estimated cost of the project₹30,515.76 lakh (₹305.16 crore)
Total units (plots, apartments, shops)262
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder3 BHK: 1,240 sq ft carpet, 126 units; 4 BHK: 1,513 sq ft carpet, 136 units (source: the builder's registration form (Form A-H))
Units booked when registered128
Units unsold when registered134
Layout plan approved on10-04-2012
Building plans approved on10-04-2012

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date30-06-2020
Revised completion date30-06-2020
Infrastructure: projected completion30-06-2020
Infrastructure: percentage complete when registered17.09%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2025 (JUL-SEP)
Latest report submitted on30-Jun-2026
Quarterly reports listed on the portal27

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2025 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹1.27 lakh (₹0.01 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹1.07 lakh (₹0.01 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)262 apartments
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹1,818.98 lakh (₹18.19 crore) paid; ₹0 due
Approvals listedNot found in the records checked

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 11 Oct 2025, for 30 Sep 2025
By part
  • Tower 3O: 100%, Sub-structure, super-structure, MEP, finishing and installation all shown as completed; S+11 floors with 12 slabs laid
  • Tower 3L: 100%, Sub-structure, super-structure, MEP, finishing and installation all shown as completed; S+11 floors with 12 slabs laid
  • Tower 3M: 100%, Sub-structure, super-structure, MEP, finishing and installation all shown as completed; S+11 floors with 12 slabs laid
Unclear in the certificate
  • Para 5 refers to Table B, but no Table B appears in the document.
  • Tower 3O, item 17(iv) electrical fittings/lighting is marked 'Completed' but the percentage column shows 0%.
  • Modular kitchen status is marked 'As per Possession' in all towers instead of a percentage.
  • Tower 3L and 3M have some typed amounts without commas and a few value entries differ between tables; amounts are as typed.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusFirst Hearing: 5; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project3
Cases
Decided cases against ORRIS INFRASTRUCTURE PVT LTD (all its projects)125 (Complaint: 100; Execution of an earlier order: 12; Compensation: 13)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026