Projects · ATS REALWORTH PVT. LTD.
ATS Grandstand Phase 1
ATS Realworth · Sector 99A, Gurugram
Registered with RERA: Jan 2018
Is it legal?
- RERA registered, valid till Mar 2031
- HRERA has opened 3 cases of its own against the builder over this project (3 open):
- Did not submit quarterly progress report to the Authority (May 2022, open)
- 2 more cases: reply 4
- 4 complaints about this project decided by HRERA since Nov 2023 (1 delay interest ordered, 1 refund ordered, 1 other order, 1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Original deadline Nov 2028, extended to Mar 2031
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- In progress: Miscellaneous works 27%, Sub structure 7.9%, Super structure 0%
- Money: ₹13.5 crore spent of ₹184.7 crore; ₹171.2 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 209 units sold (builder's certificate, Sep 2026)
- Registration now covers 236
Location
- Nearest metro: Millennium City Centre Gurugram, 16.7 km by road (52 min by car)
- Cyber City 56 min · Airport 35 min by car at 9:30 am
- Within 3 km: 1 hospital, 0 schools, 1 mall
The builder: ATS Realworth
- 2 projects registered in Gurugram, 1 lapsed
- 0 with an occupation certificate on record
- 23 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ATS GRANDSTAND PHASE 1 |
|---|---|
| Builder (promoter) | ATS REALWORTH PVT. LTD. |
| Location | SECTOR-99A , VILLAG GOPALPUR, GURUGRAM, HARYANA |
| RERA project ID | RERA-GRG-379-2019 |
| Registration certificate number | 06 OF 2018 DATED 02.01.2018 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/03/2031 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 2.62 acres |
| Licence | 37 of 2013 (02-06-2024) |
| Estimated cost of the project | ₹19,002.28 lakh (₹190.02 crore) |
| Total units (plots, apartments, shops) | 236 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 210 |
| Units unsold when registered | 31 |
| Layout plan approved on | 26-05-2014 |
| Building plans approved on | 26-05-2014 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 28-05-2022 |
|---|---|
| Revised completion date | 27-11-2028 |
| Infrastructure: projected completion | 27-11-2028 |
| Infrastructure: percentage complete when registered | 2% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 21-Oct-2026 |
| Quarterly reports listed on the portal | 32 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹1,043.4 lakh (₹10.43 crore) |
| Spent on construction of apartments in the quarter | ₹742.09 lakh (₹7.42 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹190.14 lakh (₹1.9 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹1.21 lakh (₹0.01 crore) |
| Units in the project (apartments / plots) | 236 apartments |
| Sold in the quarter | Not found in the records checked |
| EDC (development charges): paid / due as on date | ₹146.98 lakh (₹1.47 crore) paid; ₹146.98 lakh (₹1.47 crore) due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| By part |
|
|---|---|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in