Projects · SPAZE TOWERS PVT. LTD.
Auto Max A Unit Of Omaxe Auto Ltd, (Boulevard I)
Spaze Towers · Sector 47, Gurugram
Registered with RERA: Jan 2018
Is it legal?
- RERA registered, valid till Sep 2021 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit quarterly progress report (May 2022, open)
- Did not apply to extend registration or file completion, part completion or occupation certificate (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 2 more cases: reply 4
Will it be delivered on time?
- Deadline Sep 2021, never extended (date has passed)
- 4 occupation certificates issued:
- Jul 2020: Commercial block, ground to 8th floor, plus basements (no flats listed)
- Jan 2023: Six towers, EWS tower, community building and ground-floor shops (276 flats)
- Jan 2023: Towers R1-R4, EWS Tower S1, community building, commercial (264 flats)
- Jan 2023: Towers R1-R4, EWS Tower S1, community building, commercial (264 flats)
- Construction, as certified by the architect (Oct–Dec 2023):
- Done: Boulevard-i: sub structure, Boulevard-i: super structure, Boulevard-i: mep, mechanical, Boulevard-i: mep, electrical, Boulevard-i: mep, plumbing & firefighting, Boulevard-i: finishing, external
- In progress: Boulevard-i: finishing, internal 92.06%
- Money: ₹117.8 crore spent of ₹117.3 crore (CA certificate, Dec 2023)
What's on offer?
- 300 units: 297 sold, 3 unsold (builder's certificate, Dec 2023)
Location
- Nearest metro: Millennium City Centre Gurugram, 7.7 km by road (37 min by car)
- Cyber City 46 min · Airport 51 min by car at 9:30 am
- Within 3 km: 15 hospitals, 14 schools, 6 malls
The builder: Spaze Towers
- 6 projects registered in Gurugram, 1 lapsed
- 5 with an occupation certificate on record
- 208 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | AUTO MAX A UNIT OF OMAXE AUTO LTD, (BOULEVARD I) |
|---|
| Builder (promoter) | SPAZE TOWERS PVT. LTD. |
|---|
| Location | SECTOR 47, VILLAGE TIKRI, GUR UGRAM, HARYANA |
|---|
| RERA project ID | RERA-GRG-527-2019 |
|---|
| Registration certificate number | 04 OF 2018 DATED 02.01.2018 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 10/09/2021 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 2.851 acres |
|---|
| Licence | 219 of 2007 dated 11.09.2007 |
|---|
| Estimated cost of the project | ₹11,735.16 lakh (₹117.35 crore) |
|---|
| Total units (plots, apartments, shops) | 299 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 297 |
|---|
| Units unsold when registered | 2 |
|---|
| Layout plan approved on | 07-09-2010 |
|---|
| Building plans approved on | 04-02-2020 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 10-09-2021 |
|---|
| Revised completion date | 10-09-2021 |
|---|
| Infrastructure: projected completion | 10-09-2021 |
|---|
| Infrastructure: percentage complete when registered | 98% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/12/2023 (OCT-DEC) |
|---|
| Latest report submitted on | 06-Feb-2024 |
|---|
| Quarterly reports listed on the portal | 21 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2023 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0.2 lakh (₹0 crore) |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0.78 lakh (₹0.01 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0.8 lakh (₹0.01 crore) |
|---|
| Units in the project (apartments / plots) | 300 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹11.12 lakh (₹0.11 crore) paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 09-09-2010
- Demarcation Plan: Obtained Approval 23-03-2008
- Zoning Plan: Obtained Approval 16-04-2008
- Service Plans: Obtained Approval 08-05-2020
- Electricity Plans: Obtained Approval 08-05-2020
- Site Plans: Obtained Approval 07-09-2010
- Building Plans: Obtained Approval 07-01-2010
- Fire NOC: Obtained Approval 26-06-2020
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 31 Dec 2023, for 31 Dec 2023 |
|---|
| By part | - Boulevard-I (Single Tower): Sub structure: 100%
- Boulevard-I (Single Tower): Super structure: 100%
- Boulevard-I (Single Tower): MEP, Mechanical (lifts, ventilation, etc.): 100%
- Boulevard-I (Single Tower): MEP, Electrical (conduiting, wiring, fixtures, etc.): 100%
- Boulevard-I (Single Tower): MEP, Plumbing & Firefighting: 100%
- Boulevard-I (Single Tower): Finishing, Internal (plaster, tiling, flooring, painting, etc.): 92.06%
- Boulevard-I (Single Tower): Finishing, External (plaster, painting, facade, etc.): 100%
|
|---|
| Unclear in the certificate | - Table B is referred to in the certificate but is not included in the document.
- Number of floors, total area per floor and stilt/ground floor fields in the status table are blank.
- Work done value during the quarter for internal finishing is shown as 0.20 with no unit stated.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Occupation Certificate (Form BR-VII) dated 27 Jul 2020: covers Commercial Block (Tower/Block No. not stated), ground floor to 8th floor, basements 1 to 3, terrace floor (mumty/machine room), VCB room and guard room, in the Commercial Colony under Licence No. 219 of 2007 dated 11 Sep 2007 at Village Tikri, Sector-47, Gurugram. Memo No. ZP-318/JD(AS)/2020/13123.. Addressed to Spaze Tower Pvt. Ltd.. Composition fees for variations from approved plans: ₹18,03,243. Unclear in the document: The memo number (13123) and the issue date (27-07-2020) are handwritten and hard to read with certainty.; The last page is mostly illegible, with mirrored and faded text, so its content could not be read.; The Tower/Block number is not clearly stated in the table; it reads only 'Commercial Block'.
- Occupation Certificate (Form BR-VII) dated 04 Jan 2023: covers Towers Q1 (Platinum-A), Q2 (Platinum-F), R1 (Platinum-B), R2 (Platinum-C), R3 (Platinum-D) and R4 (Platinum-E), each with 46 or 80 dwelling units, in Group Housing Colony at Sector 28, Gurugram. Also covers the Community Building in Towers Q1 and Q2, the commercial component on the ground floor only of Towers R2, R3 and S1, and EWS Tower S1 with 12 EWS units. Total is 264 main dwelling units and 12 EWS units.. Addressed to Indian Airlines Pilot Co-operative House Building Society Ltd and others, c/o Essel Housing Projects Pvt Ltd. Composition fees for variations from approved plans: ₹2,12,778. Unclear in the document: Scan quality is low; some stamp and signature text is hard to read.
- Occupation Certificate: covers Permission to occupy Tower R1 (Platinum-B), Tower R2 (Platinum-C), Tower R3 (Platinum-D), Tower R4 (Platinum-E), Tower S1 (EWS), the community building, and commercial components in Towers R2, R3 and S1 (ground floor), plus the lower and upper basements, in a group housing colony measuring 36.51875 acres in Sector-28, Gurugram. The subject line also names Towers Q1 (Platinum-A) and Q2 (Platinum-F), but they are not in the grant table.. Addressed to Indian Airlines Pilot Co-operative House Building Society Ltd and others, care of Essel Housing Projects Pvt. Ltd. Composition fees for variations from approved plans: ₹2,12,778. Unclear in the document: The memo date is garbled in the scan, so the issue date could not be read.; The subject line names Towers Q1 and Q2, but the grant table does not list them. Their status is not clear.; The FAR and floor-area figures in the table are garbled and could not be read reliably.; The composition fee is partly garbled and read as 2,12,778 rupees.; The document states 264 main dwelling units and 12 EWS units. The 264 figure is given here; the EWS units are not added in.
- Occupation Certificate: covers Towers Q1 (Platinum-A), Q2 (Platinum-F), R1 (Platinum-B), R2 (Platinum-C), R3 (Platinum-D), R4 (Platinum-E), EWS Tower S1, community building in Towers Q1 and Q2, and commercial component, in a group housing colony of 36.51875 acres in Sector-28, Gurugram. The occupation certificate is granted for the buildings described in the table of the order, including the basements.. Addressed to Indian Airlines Pilot Co-operative House Building Society Ltd and others, c/o Essel Housing Projects Pvt. Ltd. Composition fees for variations from approved plans: ₹2,12,778. Unclear in the document: Issue date of the order is garbled in the scan; the memo date could not be read reliably.; The document states 264 main dwelling units and 12 EWS units; the per-tower unit counts in the table do not clearly add up to these totals.; Subject line lists Towers Q1 and Q2, but the table of buildings does not show separate rows for them.; Floor area (FAR) figures in the table are partly garbled and were not filled in.; Composition fee amount is printed as 2,12,778 in a garbled form; read as Rs 212778.
|
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 5 |
|---|
| By status | First Hearing: 5 |
|---|
| Proceedings | - RERA-GRG-3159-2022: Authority-initiated proceeding against Spaze Towers Pvt. Ltd. (promoter), case RERA-GRG-3159-2022, listed as HARERA Gurugram through a named officer versus the promoter. The page does not state the specific reason for the case. Status: First hearing listed for 30 Jun 2022. The listing shows the status as FIRST HEARING, with no proceedings or order recorded. Latest: 30 Jun 2022, First hearing listed. Documents were submitted on this date, under the remark 'NEW COMPLAINT'. No proceedings of the day, bench order, or order uploaded are recorded.
- RERA-GRG-3521-2022: The Authority issued a show cause notice to the promoter, Spaze Towers Pvt. Ltd., for not submitting its quarterly progress report. Status: First hearing listed for 27 Jun 2022. The page shows no hearing outcome or order yet. Latest: 27 Jun 2022, First hearing was listed. The status shows 'FIRST HEARING', with no proceedings, bench order or order upload recorded.
- RERA-GRG-3874-2022: The Authority issued a show cause notice to the promoter, Spaze Towers Pvt. Ltd., for not applying to extend its registration and for not submitting a completion certificate, part completion certificate or occupation certificate, as the case may be, and for not submitting the required documents. The case page shows the registration certificate status as RC EXPIRED. Status: First hearing listed for 28 Jun 2022. The page shows no proceedings or order for that hearing yet. Latest: 28 Jun 2022, First hearing was listed. The proceedings, bench and order fields are shown as blank ('---').
- RERA-GRG-3876-2022: The Authority issued a show-cause notice to the promoter, Spaze Towers Pvt. Ltd., for not adhering to the time period it declared for completing the project, under section 4(2)(l)(C). Status: The case is listed for first hearing on 30 Jun 2022. The case listing shows status 'First Hearing' with no proceedings of the day, bench order or order recorded. Latest: 30 Jun 2022, First hearing listed. No proceedings or order are recorded in the document.
- RERA-GRG-5215-2019: The Authority's own proceeding against the promoter, SPAZE TOWERS PVT. LTD., for compliance with a section of the RERA Act (recorded as 'Sec 42 1D A-H') and the quarterly progress report (QPR). The case was registered as a new complaint in Gurugram. Status: Listed at the first hearing stage. The case page shows the status as FIRST HEARING with a hearing date of 06 Jan 2020. No proceedings or order are recorded for that date. Latest: 24 Aug 2020, Second notice issued to the promoter for compliance with section 42 (1D) and the QPR, dispatched (Dispatch ID EH639075845IN).
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|
| Decided cases against SPAZE TOWERS PVT. LTD. (all its projects) | 208 (Complaint: 184; Execution of an earlier order: 14; Compensation: 10) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in