Avenue 81 PHASE-2

GLS Infracon · Sector 81, Gurugram

Registered with RERA: May 2023

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: M/S GLS Infracon

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameAVENUE 81 PHASE-2
Builder (promoter)GLS INFRACON PVT. LTD.
LocationSECTOR 81, GURUGRAM, SITUATED IN THE REVENUE ESTATE OF VILLAGE NAWADA FATEHPUR, DISTRICT GURUGRAM, HARYANA
RERA project IDRERA-GRG-1257-2023
Registration certificate numberGGM/724/456/2023/68 DATED 29.05.2023
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to03/10/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area1.875 acres
Licence160 of 2022 dated 04.10.2022 (03.10.2027)
Estimated cost of the project₹6,764.22 lakh (₹67.64 crore)
Total units (plots, apartments, shops)220
Unit sizes (carpet area, as declared)4 units of 336 sq ft carpet (2 towers); 8 units of 345 sq ft carpet (2 towers); 104 units of 643 sq ft carpet (2 towers); 104 units of 645 sq ft carpet (2 towers)
Flat types (BHK), as stated by the builder1 BHK: 336–345 sq ft carpet; 2 BHK + study: 643 sq ft carpet; 2 BHK + store: 645 sq ft carpet (source: the builder's floor plans uploaded to HRERA)
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on04-05-2023
Building plans approved on04-05-2023

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-07-2023
Likely completion date03-10-2027

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2026 (APR-JUN)
Latest report submitted on14-Aug-2026
Quarterly reports listed on the portal12

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹250.52 lakh (₹2.51 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹26.98 lakh (₹0.27 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹227.05 lakh (₹2.27 crore)
Project bank account (escrow): deposited in the quarter₹361.37 lakh (₹3.61 crore)
Project bank account (escrow): withdrawn in the quarter₹357.14 lakh (₹3.57 crore)
Project bank account (escrow): balance at quarter end₹4.23 lakh (₹0.04 crore)
Units in the project (apartments / plots)220 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹147.68 lakh (₹1.48 crore) paid; ₹85.46 lakh (₹0.85 crore) due
Approvals listedNot found in the records checked

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 06 Jul 2026, for June 2026
By part
  • Tower F: Sub structure 10% and super structure 45% complete cumulatively to end of quarter, with no work done during the quarter. Slabs 75% laid, walls, staircase, lift wells and lift lobbies 50% under progress. MEP and finishing works not started.
Unclear in the certificate
  • Certificate refers to Table B for other buildings or towers, but Table B is not included in the pages provided, so only Tower F is reported.
  • No single overall percentage is stated for Tower F, so the tower-level percent is left blank.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusDisposed: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against GLS INFRACON PVT. LTD. (all its projects)3 (Complaint: 3)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026