Projects · AVL INFRASTRUCTURE PVT.LTD.
Avl 36 Gurgaon
Avl Infrastructure · Sector 36, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Dec 2019 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit a quarterly progress report, prompting a show-cause notice (open)
- Did not apply to extend registration; did not submit completion or occupation certificate and documents (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 3 more cases: reply 4
Will it be delivered on time?
- Deadline Dec 2019, never extended (date has passed)
- Occupation certificate (Dec 2019) covers: Towers 1 to 19 and commercial building
- Construction, as certified by the architect (Jul–Sep 2022):
- Done: 18 parts
- Money: ₹273.4 crore spent of ₹273.4 crore (CA certificate, Sep 2022)
What's on offer?
- 1,480 units: 1,480 sold, 0 unsold (builder's certificate, Sep 2022)
- Flats: 1480 of 1480 sold
- Commercial Shops: 63 of 63 sold
Location
- Nearest metro: Millennium City Centre Gurugram, 15.6 km by road (47 min by car)
- Cyber City 53 min · Airport 43 min by car at 9:30 am
- Within 3 km: 3 hospitals, 1 school, 1 mall
The builder: Avl Infrastructure
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 5 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | AVL 36 GURGAON |
|---|---|
| Builder (promoter) | AVL INFRASTRUCTURE PVT.LTD. |
| Location | SECTOR-36-A,GURUGRAM |
| RERA project ID | RERA-GRG-461-2019 |
| Registration certificate number | 106 OF 2017 DATED 24.08.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2019 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 9.06875 acres |
| Licence | 18 of 2014 (10-06-2014), 74 of 2014 (01-08-2014) |
| Estimated cost of the project | ₹26,000 lakh (₹260 crore) |
| Total units (plots, apartments, shops) | 1480 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 1250 |
| Units unsold when registered | 240 |
| Layout plan approved on | 17-12-2019 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-12-2019 |
|---|---|
| Revised completion date | 17-12-2019 |
| Infrastructure: projected completion | 17-12-2019 |
| Infrastructure: percentage complete when registered | 100% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2022 (JUL-SEP) |
| Latest report submitted on | 20-Nov-2022 |
| Quarterly reports listed on the portal | 16 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2022 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹50 lakh (₹0.5 crore) |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹186.8 lakh (₹1.87 crore) |
| Project bank account (escrow): deposited in the quarter | ₹18 lakh (₹0.18 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹18 lakh (₹0.18 crore) |
| Project bank account (escrow): balance at quarter end | ₹0.17 lakh (₹0 crore) |
| Units in the project (apartments / plots) | 1480 apartments |
| Sold in the quarter | 2022 apartments |
| EDC (development charges): paid / due as on date | ₹1,207.61 lakh (₹12.08 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 10 Oct 2022, for 30 Sep 2022 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against AVL INFRASTRUCTURE PVT.LTD. (all its projects) | 5 (Complaint: 4; Compensation: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in