Projects · SWETA ESTATES PVT. LTD.

Bella Vista – Central Park Resorts

Sweta Estates · Sector 48, Gurugram

Registered with RERA: Dec 2019

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Sweta Estates

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameBELLA VISTA - CENTRAL PARK RESORTS
Builder (promoter)SWETA ESTATES PVT. LTD.
LocationSECTOR 48, SOHNA ROAD, NEAR S UBHASH CHOWK, GURGAON
RERA project IDRERA-GRG-330-2019
Registration certificate numberGGM/379/111/2019/73 DATED 23.12.2019
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to28/02/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area13.20 acres
Licence02 of 1995 dt. 10.03.1995 35-37 of 1996 dt. 17.04.1996 117-119 of 2004 dt. 16.08.2004
Estimated cost of the project₹3,88,664 lakh (₹3,886.64 crore)
Total units (plots, apartments, shops)511
Unit sizes (carpet area, as declared)511 units averaging about 850 sq ft carpet (2 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on24-10-2019
Building plans approved on24-10-2019

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-07-2019
Likely completion date31-08-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2026 (JAN-MAR)
Latest report submitted on14-Apr-2026
Quarterly reports listed on the portal25

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2026 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹4,959.59 lakh (₹49.6 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹-5,375.88 lakh (₹-53.76 crore)
Spent on construction of apartments in the quarter₹4,585 lakh (₹45.85 crore)
Spent on infrastructure in the quarter₹1,434.54 lakh (₹14.35 crore)
Other costs in the quarter (EDC, taxes, etc.)₹1,202.58 lakh (₹12.03 crore)
Project bank account (escrow): deposited in the quarter₹3,471.72 lakh (₹34.72 crore)
Project bank account (escrow): withdrawn in the quarter₹3,888 lakh (₹38.88 crore)
Project bank account (escrow): balance at quarter end₹0.41 lakh (₹0 crore)
Units in the project (apartments / plots)499 apartments
Sold in the quarter14 apartments
EDC (development charges): paid / due as on date₹920.61 lakh (₹9.21 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 01-05-2015
  • Zoning Plan: Obtained Approval 01-05-2015
  • Service Plans: Obtained Approval 27-08-2014
  • Electricity Plans: Obtained Approval 29-04-2014
  • Fire NOC: Obtained Approval 14-01-2023

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 01 Apr 2026, for March 2026
By part
  • Tower BELAPERLA (Belaperla, earlier Bella Vista, Central Park Resorts): Sub structure 99.5%. Super structure 99.5%. Mechanical, electrical, plumbing and firefighting, and HVAC each 99%. Internal finishing 98%. External finishing 98%. Two basements, G+31 floors. Excavation, foundation, basements and waterproofing are completed. Walls, staircases, lift wells and lift lobbies are shown as built on all floors. Compound wall and entrance lobby finishing are completed.
  • Tower BELANOVA (Belaperla, earlier Bella Vista, Central Park Resorts): Sub structure 99.5%. Super structure 99.5%. Mechanical 85%. Electrical 85%. Plumbing and firefighting 80%. HVAC 25%. Internal finishing 85%. External finishing 90%.
Unclear in the certificate
  • Table B, which the certificate refers to, is not in the document.
  • The sub-structure and super-structure status pages do not name the tower they cover.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusScrutinized: 1; First Hearing: 4
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project1
Cases
Decided cases against SWETA ESTATES PVT. LTD. (all its projects)10 (Complaint: 9; Compensation: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026