Project nameBIRLA NAVYA (AVIK PHASE-2)
Builder (promoter)AVARNA PROJECTS LLP
LocationSECTOR-63A,VILLAGE- KADARPUR, MAIDAWAS, ULLAHWAS
RERA project IDRERA-GRG-1829-2024
Registration certificate numberGGM/909/641/2025/12 DATED 05.02.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/04/2030
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area10815.66 acres
LicenceThe Promoter is Third Party Right Holder of Plots through sale deed
Estimated cost of the project₹35,818.2 lakh (₹358.18 crore)
Total units (plots, apartments, shops)141
Unit sizes (carpet area, as declared)4 units of 1,161 sq ft carpet (1 tower); 4 units of 1,180 sq ft carpet (1 tower); 4 units of 1,341 sq ft carpet (1 tower); 4 units of 1,351 sq ft carpet (1 tower); 1 unit of 1,438 sq ft carpet (1 tower); 3 units of 1,468 sq ft carpet (1 tower); 4 units of 1,471 sq ft carpet (1 tower); 20 units of 1,481 sq ft carpet; 1 unit of 1,484 sq ft carpet (1 tower); 8 units of 1,491 sq ft carpet (2 towers); 4 units of 1,508 sq ft carpet (1 tower); 8 units of 1,523 sq ft carpet (2 towers); 1 unit of 1,595 sq ft carpet (1 tower); 2 units of 1,601 sq ft carpet (2 towers); 1 unit of 1,607 sq ft carpet (1 tower); 3 units of 1,624 sq ft carpet (1 tower); 6 units of 1,630 sq ft carpet (2 towers); 3 units of 1,654 sq ft carpet (1 tower); 2 units of 1,655 sq ft carpet; 1 unit of 1,662 sq ft carpet (1 tower); 4 units of 1,684 sq ft carpet; 1 unit of 1,685 sq ft carpet (1 tower); 1 unit of 1,686 sq ft carpet (1 tower); 3 units of 1,691 sq ft carpet (1 tower); 1 unit of 1,985 sq ft carpet (1 tower); 3 units of 2,009 sq ft carpet (1 tower); 1 unit of 2,020 sq ft carpet (1 tower); 3 units of 2,043 sq ft carpet (1 tower); 4 units of 2,057 sq ft carpet (1 tower); 1 unit of 2,169 sq ft carpet (1 tower); 2 units of 2,185 sq ft carpet; 1 unit of 2,200 sq ft carpet (1 tower); 1 unit of 2,203 sq ft carpet (1 tower); 2 units of 2,205 sq ft carpet (1 tower); 2 units of 2,207 sq ft carpet (2 towers); 2 units of 2,214 sq ft carpet (1 tower); 1 unit of 2,219 sq ft carpet (1 tower); 2 units of 2,220 sq ft carpet (1 tower); 1 unit of 2,221 sq ft carpet (1 tower); 1 unit of 2,234 sq ft carpet (1 tower); 2 units of 2,235 sq ft carpet (1 tower); 2 units of 2,241 sq ft carpet (2 towers); 4 units of 2,242 sq ft carpet (2 towers); 1 unit of 2,339 sq ft carpet (1 tower); 1 unit of 2,373 sq ft carpet (1 tower); 2 units of 2,374 sq ft carpet (1 tower); 1 unit of 2,423 sq ft carpet (1 tower); 1 unit of 2,446 sq ft carpet (1 tower); 3 units of 2,458 sq ft carpet; 1 unit of 2,480 sq ft carpet (1 tower); 2 units of 2,481 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on19-01-2023
Building plans approved on30-12-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-04-2025
Likely completion date30-04-2030

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal6

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹1,349 lakh (₹13.49 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹519 lakh (₹5.19 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹84 lakh (₹0.84 crore)
Project bank account (escrow): deposited in the quarter₹-435.79 lakh (₹-4.36 crore)
Project bank account (escrow): withdrawn in the quarter₹7.13 lakh (₹0.07 crore)
Project bank account (escrow): balance at quarter end₹118.52 lakh (₹1.19 crore)
Units in the project (apartments / plots)140 apartments
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Building Plans: Obtained Approval 29-10-2024

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 13 Oct 2026, for September 2026
By part
  • Tower A2 (P-7c, 9a, 9b, 18, 18a, 19, 20, 20a, 20b, 25, 25a, 26, 26a, 38-42, 42a, 42b, 45, 60-64, 67, 68, 68a, 68b, 69, 72, 73, 88, 89): Sub structure 31.23%, super structure 1.20%, mechanical 0.00%, electrical 2.08%, plumbing and firefighting 2.08%, internal finishing 0.00%, external finishing 1.71%. Excavation by mechanical means 60%, raft foundation 54.29%, basement level 1 23.33%, ground floor 5.71%, slabs laid 10.24% of total proposed slabs, external plaster 5.71%, internal plaster 4.17%.
Unclear in the certificate
  • Table B referred to in the certificate is not in the document, so no table B figures are given.
  • The certificate gives component percentages for the tower but no single overall percentage of completion.
  • Tower-wise figures are listed as one group (A2) and are not split by individual tower.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against AVARNA PROJECTS LLP (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in