RERA’d by NeevHQ

Projects · ATS COMMERCIAL REAL ESTATE PRIVATE LIMITED

Bonheur Avenue Phase 2

ATS Commercial Real Estate · Sector 35, Gurugram

Registered with RERA: May 2023

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: ATS Commercial Real Estate

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameBONHEUR AVENUE PHASE 2
Builder (promoter)ATS COMMERCIAL REAL ESTATE PRIVATE LIMITED
LocationSECTOR 35, VILLAGE DHUNELA
RERA project IDRERA-GRG-1323-2023
Registration certificate numberGGM/712/444/2023/56 DATED 08.05.2023
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/04/2025
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area5.05 acres
Licence209 of 2022 (16/12/2022)
Estimated cost of the project₹8,490 lakh (₹84.9 crore)
Total units (plots, apartments, shops)87
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on06-02-2023
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-05-2023
Likely completion date30-04-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2025 (JAN-MAR)
Latest report submitted on17-Apr-2025
Quarterly reports listed on the portal7

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2025 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹44.19 lakh (₹0.44 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹-12.75 lakh (₹-0.13 crore)
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹9.93 lakh (₹0.1 crore)
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹30.94 lakh (₹0.31 crore)
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹286.23 lakh (₹2.86 crore)
Units in the project (apartments / plots)87 plots
Sold in the quarter0 plots
EDC (development charges): paid / due as on date₹278.1 lakh (₹2.78 crore) paid; ₹251 lakh (₹2.51 crore) due
Approvals listed
  • Layout Plan: Obtained Approval 16-12-2022
  • Demarcation Plan: Obtained Approval 13-01-2023
  • Zoning Plan: Obtained Approval 06-02-2023
  • Service Plans: Obtained Approval 28-07-2023
  • Electricity Plans: Obtained Approval 20-07-2023

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 31 Mar 2025, for March-25
By part
  • Sub Structure: not stated
  • Super Structure: not stated
  • Mechanical (lifts, ventilation): not stated
  • Electrical (conduiting, wiring, fixtures): 100%, Work value 500.00 done during the quarter and 500.00 cumulative
  • Plumbing & Fire Fighting (pipings, pumps, pump room, fixtures): 100%, Work value 266.00 done during the quarter and 266.00 cumulative
  • Internal finishing: not stated
  • External finishing: not stated
  • Internal roads and pavements: 100%
  • Water supply: 100%
  • Sewerage (chamber, lines, septic tank, STP): 100%
  • Storm water drains: 100%
  • Landscaping and tree plantation: 100%
  • Parks and playgrounds: 100%
  • Children play equipment: 100%
  • Benches: 100%
  • Shopping area: 0%
  • Street lighting and electrification: 100%
  • Treatment and disposal of sewage and sullage water/STP: 95%
  • Solid waste management and disposal: 95%
  • Water conservation, rain water harvesting, percolating well/pit: 100%
  • Energy management (solar): 0%
  • Fire protection and fire safety requirements: 100%
  • Electrical meter room, sub-station, receiving station: 100%
  • 10% land transferred to competent authority: 100%, Transferred to DTCP on 10 Jun 2022
Unclear in the certificate
  • Signing date of the certificate is garbled as '145-04-2025'; the certificate date above is the site inspection and certification date 31-03-2025 instead.
  • Units of the rupee-style values in Table A (500.00 and 266.00) are not stated.
  • Several items are marked NA and are shown as null.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusPending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against ATS COMMERCIAL REAL ESTATE PRIVATE LIMITED (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in