Projects · BRAHMA CITY PVT. LTD.
Brahma City K-Block
Brahma City · Sector 63, Gurugram
Registered with RERA: Oct 2017
Is it legal?
- RERA registered, valid till Jun 2030
- HRERA has opened 7 cases of its own against the builder over this project (7 open):
- Did not submit its quarterly progress report (May 2022, open)
- Did not apply to extend registration, submit completion or occupation certificate, or required documents (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 4 more cases: reply 4
Will it be delivered on time?
- Original deadline not found, extended 2 times to Jun 2030
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- In progress: Internal roads and pavements 95%, Water supply 90%, Sewerage 90%, Storm water drains 90%, Street lighting and electrification 90%, Treatment and disposal of sewage and sullage water 90%, and 3 more
- Money: ₹62.7 crore spent of ₹84 crore; ₹21.3 crore still to spend (CA certificate, Sep 2026)
Location
- Nearest metro: Sector 55–56, 3.2 km by road (11 min by car)
- Cyber City 34 min · Airport 50 min by car at 9:30 am
- Within 3 km: 18 hospitals, 37 schools, 11 malls
The builder: Brahma City
- 5 projects registered in Gurugram, 2 lapsed
- 0 with an occupation certificate on record
- 28 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | BRAHMA CITY K-BLOCK |
|---|
| Builder (promoter) | BRAHMA CITY PVT. LTD. |
|---|
| Location | SECTOR-63, TEHSIL WAZIRABAD, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-519-2019 |
|---|
| Registration certificate number | 268 OF 2017 DATED 09.10.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 30/06/2030 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 34689 acres |
|---|
| Licence | 64 of 2010 |
|---|
| Estimated cost of the project | ₹8,643.72 lakh (₹86.44 crore) |
|---|
| Total units (plots, apartments, shops) | 77 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 76 |
|---|
| Units unsold when registered | 1 |
|---|
| Layout plan approved on | 08-05-2014 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | Not found in the records checked |
|---|
| Revised completion date | Not found in the records checked |
|---|
| Infrastructure: projected completion | 31-12-2022 |
|---|
| Infrastructure: percentage complete when registered | 0% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 15-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 32 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹193.51 lakh (₹1.94 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹1.35 lakh (₹0.01 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 77 plots |
|---|
| Sold in the quarter | 2 plots |
|---|
| EDC (development charges): paid / due as on date | ₹1,414.95 lakh (₹14.15 crore) paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 19-12-2015
- Demarcation Plan: Obtained Approval 19-12-2015
- Zoning Plan: Obtained Approval 07-07-2017
- Service Plans: Obtained Approval 25-10-2016
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 15 Oct 2026, for Q3 Sep 2026 |
|---|
| By part | - Block K: Excavation for water, sewer and cable laying 95% done. Foundation, super-structure and MEP entries marked NA. Door and window frame fixing in progress.
- Internal roads and pavements: 95%
- Water supply: 90%
- Sewerage (chamber, lines, septic tanks, STP): 90%
- Storm water drains: 90%
- Landscaping and tree plantation: 50%
- Street lighting and electrification: 90%
- Treatment and disposal of sewage and sullage water (common STP): 90%
- Water conservation, rain water harvesting, percolating well/pit: 90%
- Electrical meter room, sub-station, receiving station (common): 90%
|
|---|
| Unclear in the certificate | - Table A cumulative percentage of work done for Block K is not filled in (marked NA), so no overall figure is stated.
- Work done during the quarter is not stated as a percentage.
- Quarter is written as 'Q3 Sep 2026', which is not a standard quarter label; reported as written.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | - Extension 268 of 2017 dated 06 Mar 2023: registration extended from 30 Jun 2019 to 30 Jun 2025. Conditions include: Penalty of Rs. 10 lakhs imposed for violation of sections 3 and 4 of the Act; the promoter must deposit it before the certificate is issued.; Continuation is subject to the outcome of a pending case before the Punjab and Haryana High Court (CWP No. 2926 of 2022).; The promoter must pay delay possession charges under section 18(1) of the Act from the promoter's own funds and project cash inflow, not from the allottees' money.; The registration is without prejudice to allottees' rights under section 18(1) regarding delay possession charges, including withdrawal from the project.; The promoter must not sell units on a subvention or assured return scheme without the Authority's prior approval.; The promoter must not create further encumbrance on future receivables or separate RERA accounts, except the existing lender's charge.; The promoter must submit quarterly progress reports and a monthly PERT chart comparison of proposed and actual work.; The promoter must enable formation of an association of allottees within three months of a majority of allottees booking.; Sales are on a carpet area basis only, and the total price includes all charges; no separate EDC/IDC is payable except the total sale consideration.; The promoter must complete community sites within the declared completion period.
- Extension 06 of 2023 dated 17 Oct 2025: registration extended from 30 Jun 2025 to 30 Jun 2030. Conditions include: Registration remains in force under section 7(3) of the Act, subject to the conditions listed in the certificate, binding on the promoter.; Promoter must submit the revalidated environment clearance within 4 months from the issue of this continuation certificate.; Authority imposed a penalty of Rs. 25 lakhs for violation of section 4(2)(l)(c) of the Act; the promoter has deposited it vide DD dated 22 Sep 2025.; Promoter must give allottees delay possession charges under section 18(1) from the promoter's own funds; project cash inflow must not be used for this.; Sale only on carpet area basis; total sale consideration must be inclusive of all charges, with no separate EDC/IDC payable by allottees.; Promoter must enable formation of an allottees' association within three months of majority of allottees booking, and allotment letters must require membership.; Promoter must not create further encumbrance on future receivables or separate RERA accounts, except the existing lender charge.; Promoter must submit monthly comparison of proposed and actual work on the 7th of each month and quarterly progress reports.; Authority may revoke registration or penalise the promoter for non-compliance, including failure to obtain renewals of approvals on time.; Project completion period declared as 30 Jun 2030; licence no. 64 of 2011 valid up to 20 Aug 2030.
|
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 7 |
|---|
| By status | Online Complaint Not Yet Received At Office: 2; First Hearing: 4; Pending: 1 |
|---|
| Proceedings | - RERA-GRG-2951-2022: A complaint numbered RERA-GRG-2951-2022, listed on the HRERA Gurugram page as 'HARERA GURUGRAM THROUGH ASHA V/S BRAHMA CITY PVT. LTD.', against the promoter Brahma City Pvt. Ltd. The page does not state the grievance itself. Status: The page shows the complaint as 'Online complaint not yet received at office'. Complaint dispatched status is 'Not Yet'. Next date of hearing is 'NA'. No hearings, proceedings or orders are listed.
- RERA-GRG-3460-2022: Show cause notice issued to the promoter, Brahma City Pvt. Ltd., for not submitting a quarterly progress report Status: First hearing listed for 27 Jun 2022 at 11.00 am. The case page shows no order or outcome from that hearing yet. Latest: 27 Jun 2022, First hearing was fixed. The promoter was asked to appear before the Authority at 11.00 am in the HARERA office in Gurugram, with any written reply. The case page status shows First Hearing, with no proceedings or order recorded.
- RERA-GRG-3463-2022: Complaint RERA-GRG-3463-2022 listed by HARERA Gurugram against Brahma City Pvt. Ltd. The document does not state what the complaint is about. Status: The page says the online complaint has not yet been received at the office. No next hearing date is set (NA), and the complaint has not been dispatched.
- RERA-GRG-3703-2022: A show cause notice issued by the Authority to the promoter, Brahma City Pvt. Ltd., for not applying to extend its registration, for not submitting a completion, part completion or occupation certificate, and for not submitting the required documents. Status: First hearing listed for 28 Jun 2022. The page shows no proceedings, bench order or order uploaded yet. Latest: 28 Jun 2022, First hearing was listed. The status on the page is 'First Hearing' and no proceedings or order are recorded.
- RERA-GRG-3704-2022: The Authority started this case on its own (suo motu) against the promoter, Brahma City Pvt. Ltd., for not adhering to the time period it declared for completing the project, as required under section 4(2)(l)(C). A show-cause notice was issued. Status: The case is listed at the first hearing, which was fixed for 30 Jun 2022. The proceedings, bench and order fields are blank. An advocate's reply to the suo motu notice was received on 24 Aug 2022. Latest: 24 Aug 2022, A reply from the promoter's advocate to the suo motu notice (Dak ID 39962) was received.
- RERA-GRG-5206-2022: A complaint about Brahma City Pvt. Ltd. (the promoter), listed before the Authority at Gurugram. The document does not state the grievance itself. Status: First hearing listed for 30 Jun 2022. No order or proceedings of the day are recorded. Latest: 16 Jul 2022, A document was received from the complainant under Dak ID 37884, recorded as a new complaint.
- RERA-GRG-5431-2019: The Authority started this proceeding against Brahma City Pvt. Ltd. about filing the REP-I Part (A-H) form on the HARERA website for the registered project Brahma City-K Block in Sector 63, Gurugram. The Authority issued notices asking for compliance with section 42(1D) and a QPR. Status: Pending. The page shows the next hearing on 24 Feb 2020. No order after 22 Jan 2020 is shown, and the last notice was dispatched on 09 Sep 2020. Latest: 09 Sep 2020, Fourth notice dispatched for compliance of section 42(1D). The complaint was also dispatched on this date.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|
| Decided cases against BRAHMA CITY PVT. LTD. (all its projects) | 28 (Complaint: 24; Compensation: 4) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in