RERA’d by NeevHQ

Projects · BRAHMA CITY PVT. LTD.

Brahma City M-Block

Brahma City · Sector 60, Gurugram

Registered with RERA: Oct 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Brahma City

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameBRAHMA CITY M-BLOCK
Builder (promoter)BRAHMA CITY PVT. LTD.
LocationSECTOR 60-61, VILLAGE ULLAWAS , TEHSIL WAZIRABAD
RERA project IDRERA-GRG-417-2019
Registration certificate number274 OF 2017 DATED 09.10.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/06/2030
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area34689 acres
LicenceLicence No. 64 of 2010
Estimated cost of the project₹8,600 lakh (₹86 crore)
Total units (plots, apartments, shops)74
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered74
Units unsold when registered0
Layout plan approved on02-11-2016
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion dateNot found in the records checked
Revised completion dateNot found in the records checked
Infrastructure: projected completion31-03-2022
Infrastructure: percentage complete when registered90%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal32

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹16.92 lakh (₹0.17 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)74 plots
Sold in the quarter0 plots
EDC (development charges): paid / due as on date₹1,640.7 lakh (₹16.41 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 19-12-2015
  • Demarcation Plan: Obtained Approval 19-12-2015
  • Zoning Plan: Obtained Approval 07-07-2017
  • Service Plans: Obtained Approval 25-10-2016
  • Electricity Plans: Obtained Approval 31-10-2020

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 15 Oct 2026, for Sep'26
By part
  • Block M: Sub-structure: excavation for water, sewer and cable laying 100%; raft RCC foundation 100%. Super-structure items marked NA. Fixing of door and window frames in units is in progress.
  • Common areas and services (Table B): Internal roads, water supply, sewerage, storm water drains, landscaping, parks and playgrounds, street lighting, sewage treatment, and water conservation are each certified at 100%. Parking, shopping area, community buildings and some other items are marked NA or No.
Unclear in the certificate
  • No overall percentage of construction completed is stated for the project or for Block M; Table A cumulative figures for super-structure and finishing are marked NA.
  • The percentage of work done during the quarter is not stated.
  • Table B item 23 and the B-4 services section are blank.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against BRAHMA CITY PVT. LTD. (all its projects)28 (Complaint: 24; Compensation: 4)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in