Registration

Project nameCAPITAL GATEWAY(PHASE-1)
Builder (promoter)KNS INFRACON PVT.LTD
LocationSECTOR-110A/111, VILLAGE CHAU MA, GURUGRAM
RERA project IDRERA-GRG-577-2020
Registration certificate number12 OF 2018 DATED 10.01.2018
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/06/2027
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area10.461 acres
Licence34 of 2011 Dated 16.04.2011
Estimated cost of the project₹48,468.95 lakh (₹484.69 crore)
Total units (plots, apartments, shops)538
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder2 BHK: 775 sq ft carpet, 67 units; 3 BHK: 850–1,087 sq ft carpet, 369 units; 4 BHK: 1,464 sq ft carpet, 51 units; 5 BHK: 1,744 sq ft carpet, 51 units (source: the builder's registration form (Form A-H))
Units booked when registered481
Units unsold when registered57
Layout plan approved on09-12-2016
Building plans approved on09-12-2016

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date23-07-2016
Revised completion date31-12-2021
Infrastructure: projected completion31-12-2021
Infrastructure: percentage complete when registered59.8%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2025 (JAN-MAR)
Latest report submitted on09-Dec-2025
Quarterly reports listed on the portal26

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2025 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹1,064.29 lakh (₹10.64 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹326 lakh (₹3.26 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹1,743 lakh (₹17.43 crore)
Project bank account (escrow): deposited in the quarter₹745 lakh (₹7.45 crore)
Project bank account (escrow): withdrawn in the quarter₹907 lakh (₹9.07 crore)
Project bank account (escrow): balance at quarter end₹21 lakh (₹0.21 crore)
Units in the project (apartments / plots)538 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹5,597 lakh (₹55.97 crore) paid; ₹1,336 lakh (₹13.36 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 02-04-2015
  • Zoning Plan: Obtained Approval 11-04-2011
  • Service Plans: Obtained Approval 25-03-2019
  • Electricity Plans: Obtained Approval 18-01-2023
  • Site Plans: Obtained Approval 12-09-2016
  • Building Plans: Obtained Approval 12-04-2016
  • Fire NOC: Obtained Approval 03-07-2019

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 07 Apr 2025, for 01 Jan 2025 to 31 Mar 2025
By part
  • Internal roads & pavements (Phase-1): 100%
  • Internal roads & pavements (Phase-2): 15%
  • Parking (Phase-1): 100%
  • Parking (Phase-2): 15%
  • Covered parking, 747 nos (Phase-1): 98%
  • Covered parking, 747 nos (Phase-2): 0%
  • Open parking, 211 nos (Phase-1): 98%
  • Open parking, 211 nos (Phase-2): 0%
  • Water supply (Phase-1): 99%
  • Water supply (Phase-2): 5%
  • Sewerage (Phase-1): 98%
  • Sewerage (Phase-2): 2%
  • Storm water drains (Phase-1): 97%
  • Storm water drains (Phase-2): 0%
  • Landscaping & tree plantation (Phase-1): 85%
  • Landscaping & tree plantation (Phase-2): 10%
  • Parks and playgrounds (Phase-1): 95%
  • Parks and playgrounds (Phase-2): 0%
  • Fixing of children play equipment (Phase-1): 98%
  • Fixing of children play equipment (Phase-2): 0%
  • Benches (Phase-1): 87%
  • Benches (Phase-2): 0%
  • Shopping area (Phase-1): 95%
  • Shopping area (Phase-2): 0%
  • Street lighting/electrification (Phase-1): 98%
  • Street lighting/electrification (Phase-2): 0%
  • Treatment and disposal of sewage and sullage water/STP (Phase-1): 91%
  • Treatment and disposal of sewage and sullage water/STP (Phase-2): 0%
  • Solid waste management & disposal (Phase-1): 0%
  • Solid waste management & disposal (Phase-2): 0%
  • Water conservation, rain water harvesting, percolating well/pit (Phase-1): 96%
  • Water conservation, rain water harvesting, percolating well/pit (Phase-2): 0%
  • Energy management (solar) (Phase-1): 85%
  • Energy management (solar) (Phase-2): 0%
  • Fire protection and fire safety requirements (Phase-1): 94%
  • Fire protection and fire safety requirements (Phase-2): 0%
  • Electrical meter room, sub-station, receiving station (Phase-1): 90%
  • Electrical meter room, sub-station, receiving station (Phase-2): 0%
  • Community centre (Phase-2; not proposed in Phase-1): 0%
  • Schools (Phase-2): 2%
  • Club (Phase-2): 1%
Unclear in the certificate
  • Table A gives percentages per activity for each tower (Towers A to J, EWS-1, EWS-2, Commercial-1, Commercial-2, School & Community) but no single overall figure per tower. The table is printed sideways and partly hard to read, so tower-wise totals are not given here.
  • Overall percentage of construction completed and percentage done in the quarter are not stated as single figures in the certificate.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusFirst Hearing: 4; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project67
Cases
Decided cases against KNS INFRACON PVT.LTD (all its projects)109 (Complaint: 97; Execution of an earlier order: 10; Compensation: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026