Central Avenue

Antriksh India Projects · Sector 33, Gurugram

Registered with RERA: Jul 2021

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Antriksh India Projects

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameCENTRAL AVENUE
Builder (promoter)ANTRIKSH INDIA PROJECTS PRIVATE LIMITED
LocationCENTRAL AVENUE, SUBASH CHOWK, SECTOR 33
RERA project IDRERA-GRG-791-2020
Registration certificate numberGGM/460/192/2021/28 DATED 06.07.2021
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/01/2028
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area8593.233 acres
Licence86 of 2019
Estimated cost of the project₹8,830.46 lakh (₹88.3 crore)
Total units (plots, apartments, shops)114
Unit sizes (carpet area, as declared)114 units averaging about 1,260 sq ft carpet (2 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on17-08-2020
Building plans approved on17-08-2020

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-02-2021
Likely completion date01-02-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal20

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹554.65 lakh (₹5.55 crore)
Borrowed from banks / financial institutions in the quarter₹50 lakh (₹0.5 crore)
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹351.71 lakh (₹3.52 crore)
Spent on infrastructure in the quarter₹18 lakh (₹0.18 crore)
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹554.65 lakh (₹5.55 crore)
Project bank account (escrow): withdrawn in the quarter₹565.02 lakh (₹5.65 crore)
Project bank account (escrow): balance at quarter end₹71.46 lakh (₹0.71 crore)
Units in the project (apartments / plots)114 apartments
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹74.1 lakh (₹0.74 crore) paid; ₹563.1 lakh (₹5.63 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 14-05-2014
  • Zoning Plan: Obtained Approval 01-08-2019
  • Service Plans: Obtained Approval 17-09-2025
  • Electricity Plans: Obtained Approval 19-09-2023
  • Site Plans: Obtained Approval 14-01-2020
  • Building Plans: Obtained Approval 29-01-2026
  • Fire NOC: Obtained Approval 15-01-2020

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatefor September 2026
By part
  • Tower A: Basement 1 and 2 completed. 20 floors total, 20th floor slab casted. Walls on floors 10%. Staircase 5%. Lift wells with waterproofing 100%. Doors and window frames 40%. External mechanical works 60%. Internal electrical 50%. External wall finish 15%. Lifts, overhead tanks and underground tank 100%. Compound wall 60%.
  • Tower B: Basement 1 and 2 completed. 19 floors total, 19th floor slab cast. Walls on floors (block work) 100%. Staircase 0%. Lift wells 0%. Doors and window frames 40%. External mechanical works 60%. Internal electrical 50%. Internal plumbing 70%.
Unclear in the certificate
  • Certificate date and site inspection date are blank.
  • Architect's Council of Architects registration number and validity date are blank.
  • Tower A shows 'Cumulative number of slabs' as 1 and Tower B as 3.5, which does not match the floor counts given.
  • Tower A shows 100% against 'Total floors in the tower', which is unclear.
  • Percent complete is given per activity, not as one figure per tower, so no tower-level percentage is stated.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registration
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusPending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against ANTRIKSH INDIA PROJECTS PRIVATE LIMITED (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in