Central Park Flower Valley Floors And Villas

Central Park Flower Valley · Sector 29, Gurugram

Registered with RERA: Oct 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Central Park Flower Valley

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameCENTRAL PARK FLOWER VALLEY FLOORS AND VILLAS
Builder (promoter)CENTRAL PARK FLOWER VALLEY
LocationVILLAGE DHUNELA & BERKA, SECT OR-29,30,32 AND 33, SOHNA
RERA project IDRERA-GRG-1084-2022
Registration certificate numberGGM/624/356/2022/99 DATED 27.10.2022
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to31/12/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area14.4938 acres
Licence54 of 2014, 28 of 2016 and 07 of 2020
Estimated cost of the project₹74,524.13 lakh (₹745.24 crore)
Total units (plots, apartments, shops)948
Unit sizes (carpet area, as declared)883 units averaging about 700 sq ft carpet (269 towers); 65 units averaging about 2,380 sq ft carpet (65 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on13-12-2021
Building plans approved on26-10-2017

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction28-08-2017
Likely completion date31-12-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2024 (OCT-DEC)
Latest report submitted on13-Jan-2025
Quarterly reports listed on the portal8

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2024 (OCT-DEC))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹1,807.26 lakh (₹18.07 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹-684.38 lakh (₹-6.84 crore)
Spent on construction of apartments in the quarter₹679.52 lakh (₹6.8 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹435.64 lakh (₹4.36 crore)
Project bank account (escrow): deposited in the quarter₹1,265.08 lakh (₹12.65 crore)
Project bank account (escrow): withdrawn in the quarter₹1,257.37 lakh (₹12.57 crore)
Project bank account (escrow): balance at quarter end₹7.71 lakh (₹0.08 crore)
Units in the project (apartments / plots)884 apartments
Sold in the quarter6 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 13-12-2021
  • Demarcation Plan: Obtained Approval 10-08-2022
  • Zoning Plan: Obtained Approval 10-08-2022
  • Service Plans: Obtained Approval 16-05-2022
  • Electricity Plans: Obtained Approval 19-03-2021

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 01 Jan 25, for Dec 2024
By part
  • Flamingo Floors: 100%, G+2 floors; all slabs completed; walls, staircase, lift wells and door and window frames completed; sub and super structure show no work done in the quarter; 'Other items' show 117.92% of total proposed work
  • Cerise Floors: 100%, Sub structure, super structure, MEP and finishing items each show 100% of total proposed work; 'Other items' show 253% of total proposed work
Unclear in the certificate
  • Table A for Flamingo Floors shows 'Other items' at 117.92%, which is above 100%; the certificate does not explain this.
  • Table A for Cerise Floors shows 'Other items' at 253%, which is above 100%; the certificate does not explain this.
  • The certificate does not give one overall percentage of construction completed for the whole project.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusPending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against CENTRAL PARK FLOWER VALLEY (all its projects)8 (Compensation: 8)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in