Projects · SELENE CONSTRUCTION LTD
Centrum Park (Ph-Ii)
Selene Construction · Sector 103, Gurugram
Registered with RERA: Jan 2018
Is it legal?
- RERA registered, valid till Oct 2018 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit its quarterly progress report, so the Authority issued a show-cause notice (Jun 2022, open)
- Did not extend expired registration, file completion/part/occupation certificate, or requisite documents (Jun 2022, open)
- Did not complete Centrum Park (Phase II) within declared time; did not appear at most hearings (Jun 2022, open)
- 2 more cases: reply 4
Will it be delivered on time?
- Deadline Oct 2018, never extended (date has passed)
- 2 occupation certificates issued:
- Jan 2019: Group Housing Colony, Sector-103, Gurugram
- Jan 2019: Group housing colony, Sector-103 Gurugram
- Quarterly progress report shown as "not uploaded" by HRERA
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 13.6 km by road (19 min by car)
- Cyber City 56 min · Airport 36 min by car at 9:30 am
- Within 3 km: 3 hospitals, 0 schools, 0 malls
The builder: Selene Construction
- 2 projects registered in Gurugram
- 2 with an occupation certificate on record
- 32 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | CENTRUM PARK (PH-II) |
|---|---|
| Builder (promoter) | SELENE CONSTRUCTION LTD |
| Location | SECTOR-103, DAULTABAD, GURUGR AM |
| RERA project ID | RERA-GRG-533-2019 |
| Registration certificate number | 10 OF 2018 DATED 08.01.2018 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/10/2018 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 89282.758 acres |
| Licence | 252 of 2007 dated 2.11.2007 50 of 2011 dated 5.06.2011 63 of 2012 dated 19.06.2012 |
| Estimated cost of the project | ₹35,860 lakh (₹358.6 crore) |
| Total units (plots, apartments, shops) | 293 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 249 |
| Units unsold when registered | 249 |
| Layout plan approved on | 23-08-2013 |
| Building plans approved on | 23-08-2013 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-10-2018 |
|---|---|
| Revised completion date | 31-10-2018 |
| Infrastructure: projected completion | 31-10-2018 |
| Infrastructure: percentage complete when registered | 100% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against SELENE CONSTRUCTION LTD (all its projects) | 32 (Complaint: 26; Compensation: 3; Execution of an earlier order: 3) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in