Projects · EMAAR MGF LAND LTD.

Colonnade

Emaar MGF Land · Sector 66, Gurugram

Registered with RERA: Aug 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 66; the exact site was not found.

The builder: Emaar MGF Land

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameCOLONNADE
Builder (promoter)EMAAR MGF LAND LTD.
LocationSECTOR-66, VILLAGE BADSHAHPUR , GURUGRAM
RERA project IDRERA-GRG-644-2020
Registration certificate number156 OF 2017 DATED 28.08.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2023
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area2.25 acres
Licence163 of 2008
Estimated cost of the project₹24,561 lakh (₹245.61 crore)
Total units (plots, apartments, shops)323
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered203
Units unsold when registered120
Layout plan approved on02-09-2020
Building plans approved on02-09-2020

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date30-06-2020
Revised completion date31-12-2021
Infrastructure: projected completion31-12-2021
Infrastructure: percentage complete when registered81.4%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/06/2026 (APR-JUN)
Latest report submitted on10-Jul-2026
Quarterly reports listed on the portal31

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2026 (APR-JUN))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹140 lakh (₹1.4 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹14,799 lakh (₹147.99 crore)
Other costs in the quarter (EDC, taxes, etc.)₹10,301 lakh (₹103.01 crore)
Project bank account (escrow): deposited in the quarter₹98.09 lakh (₹0.98 crore)
Project bank account (escrow): withdrawn in the quarter₹90 lakh (₹0.9 crore)
Project bank account (escrow): balance at quarter end₹10.02 lakh (₹0.1 crore)
Units in the project (apartments / plots)322 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹449.92 lakh (₹4.5 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 20-11-2018
  • Zoning Plan: Obtained Approval 20-11-2018
  • Service Plans: Obtained Approval 07-12-2021
  • Electricity Plans: Obtained Approval 20-10-2021
  • Site Plans: Obtained Approval 20-08-2021
  • Building Plans: Obtained Approval 20-08-2021
  • Fire NOC: Obtained Approval 31-12-2021

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 07 Jan 2024, for Dec-23
By part
  • Tower/building (Table A): 100%, All sub-structure and super-structure items are shown as completed. The building has 17 floors and all 17 slabs were laid by the end of the quarter. Basements (4) and waterproofing are completed.
  • Common areas and facilities (Table B): 100%, Items marked Yes, such as roads, water supply, sewerage, landscaping, street lighting, solar energy and fire safety, are shown at 100%. Children's play equipment, open parking, community buildings, schools, dispensary and club are marked No, meaning not proposed.
Unclear in the certificate
  • The certificate does not name separate towers. Table A is given for one tower/building.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project7
Cases
Decided cases against EMAAR MGF LAND LTD. (all its projects)1022 (Complaint: 321; Execution of an earlier order: 50; Compensation: 29); breakdown of the latest 400

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026