Projects · EXPERION DEVELOPERS PVT. LTD. & OTHERS
Commercial Colony
Experion Developers Pvt. Ltd. & Others · Sector 15, Gurugram
Registered with RERA: Oct 2017
Is it legal?
- RERA registered, valid till Oct 2018 (date has passed)
- HRERA has opened 7 cases of its own against the builder over this project (7 open):
- Failed to file REP-I (Part A-H) on Authority's web portal for offline registered project (Jun 2022, open)
- Did not submit several quarterly progress reports (QPRs), including those for 2018 to 2019 (May 2022, open)
- Did not apply to extend registration or file completion/occupation certificate; required documents not submitted (Jun 2022, open)
- 4 more cases: reply 4
Will it be delivered on time?
- Deadline Mar 2021, never extended (date has passed)
- 3 occupation certificates issued:
- Jan 2019: Commercial building: ground to 12th floor and basements (no flats listed)
- Jan 2019: Commercial block: ground to 12th floor and basements (no flats listed)
- May 2022: Banquet Hall (ground and first floor) and basements (no flats listed)
- Construction, as certified by the architect (Jan–Mar 2024):
- Done: Commercial building, Common services
- Money: ₹300.9 crore spent of ₹300.9 crore (CA certificate, Mar 2024)
What's on offer?
- 1 unit sold (builder's certificate, Mar 2024)
Location
- Nearest metro: Millennium City Centre Gurugram, 5.3 km by road (21 min by car)
- Cyber City 26 min · Airport 34 min by car at 9:30 am
- Within 3 km: 52 hospitals, 10 schools, 1 mall
Location shown for Sector 15; the exact site was not found.
The builder: Experion Developers Pvt. Ltd. & Others
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 10 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | COMMERCIAL COLONY |
|---|
| Builder (promoter) | EXPERION DEVELOPERS PVT. LTD. & OTHERS |
|---|
| Location | PART-II, SECTOR-15, GURUGRAM, HARYANA |
|---|
| RERA project ID | RERA-GRG-1318-2023 |
|---|
| Registration certificate number | 329 OF 2017 DATED 23.10.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 22/10/2018 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 3.95 acres |
|---|
| Licence | . 63 of 2008 dated 20.03.2008 and License No. 92 of 2010 dated 30.10.2010 |
|---|
| Estimated cost of the project | ₹30,085.27 lakh (₹300.85 crore) |
|---|
| Total units (plots, apartments, shops) | 553 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 381 |
|---|
| Units unsold when registered | 172 |
|---|
| Layout plan approved on | 23-10-2017 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 22-10-2018 |
|---|
| Revised completion date | 31-03-2021 |
|---|
| Infrastructure: projected completion | 31-03-2021 |
|---|
| Infrastructure: percentage complete when registered | 100% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/03/2024 (JAN-MAR) |
|---|
| Latest report submitted on | 06-Jun-2025 |
|---|
| Quarterly reports listed on the portal | 22 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2024 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹2,766.86 lakh (₹27.67 crore) |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
|---|
| Project bank account (escrow): deposited in the quarter | ₹1,936.8 lakh (₹19.37 crore) |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹1,936.8 lakh (₹19.37 crore) |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 553 apartments |
|---|
| Sold in the quarter | 1 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
|---|
| Approvals listed | - Layout Plan: Obtained Approval 11-07-2013
- Demarcation Plan: Obtained Approval 18-01-2012
- Zoning Plan: Obtained Approval 18-01-2012
- Service Plans: Obtained Approval 11-09-2018
- Electricity Plans: Obtained Approval 21-10-2016
- Site Plans: Obtained Approval 06-07-2017
- Building Plans: Obtained Approval 07-12-2015
- Fire NOC: Obtained Approval 29-03-2017
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 27 May 2025, for 31st March 2024 |
|---|
| By part | - Commercial Building: 100%, GF + 12 floors, 3 basements; all slabs, walls, MEP, finishing and external works shown as completed
- Common services (internal roads, parking, water supply, sewerage, storm water drains, landscaping, street lighting, STP, solid waste management, fire protection, compound wall and others listed as Yes): 100%
|
|---|
| Unclear in the certificate | - The certificate is dated 27 May 2025 but reports on the quarter ending 31st March 2024. Stated as written.
- Progress is stated as 100% based on occupancy certificates dated 2019 and 2022. The physical progress percentage was calculated from estimated and incurred construction cost, as the note says.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Occupation Certificate (Form BR-VII) dated 15 Jan 2019: covers A commercial building with ground floor to 12th floor plus existing area, in a commercial colony of 3.95 acres at Sector-15-Part-II, Gurugram. Basements 1 to 3 are also covered as non-FAR area.. Addressed to Experion Developers Pvt. Ltd. (and others). Composition fees for variations from approved plans: ₹5,07,435. Unclear in the document: The tower or block number is not stated. The table lists only 'Commercial'.
- Occupation Certificate (Form BR-VII), commercial colony, Sector-15, Gurugram dated 15 Jan 2019: covers Commercial tower in a commercial colony of 3.95 acres in Sector-15, Gurugram. Covers ground floor to 12th floor plus existing area, and basements 1 to 3 (non-FAR area). Commercial use only. Conditions include no residential use on the commercial spaces and mandatory registration of commercial spaces under the Haryana Apartment Ownership Act, 1983.. Addressed to Experion Developers Pvt. Ltd. and the promoter group (Sh. Anumod Sharma & others). Composition fees for variations from approved plans: ₹5,07,435. Unclear in the document: The same PDF also contains a second Occupation Certificate (Memo No. ZP-757-Vol.-II/AD(RA)/2022/15704, dated 31 May 2022) for a Banquet Hall (Ground + 1st Floor) in the same commercial colony. It mentions composition fees of Rs 4,31,57,430. This form records only the 2019 certificate.; The FAR area figures in the 2019 certificate were not used in this form because the schema has no field for them.; The 'Dated' field for the endorsement copy list in the 2019 certificate is blank, so only the memo date is recorded.
- Occupation Certificate (Form BR-VII) dated 31 May 2022: covers Banquet Hall (ground and first floor) in the Commercial Colony measuring 3.95 acres in Sector-15, Gurugram Manesar Urban Complex, under Licence no. 63 of 2008 and Licence no. 92 of 2010. Also covers Basement-1, Basement-2 and the mumty and machine room, shown as non-FAR area.. Addressed to The promoters, in collaboration with Experion Developers Pvt. Ltd.. Composition fees for variations from approved plans: ₹4,31,57,430. Unclear in the document: The endorsement date on the certificate is blank.; The date in the District Town Planner's endorsement reference (Endst. no. 6437) is written as '08.0.2021', which appears incomplete.
|
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 7 |
|---|
| By status | First Hearing: 4; Online Complaint Not Yet Received At Office: 1; Pending: 2 |
|---|
| Proceedings | - RERA-GRG-2563-2022: Non-filing of REP-I (Part A to H) on the Authority's web portal for an offline registered project, with a show-cause notice issued to the promoter and others Status: A show-cause notice was dispatched on 01 Jun 2022 and the first hearing was listed for 29 Jun 2022. The listing shows status 'First Hearing' with no proceedings or order recorded. A filing of REP-I (Part A-H) was received on 21 Mar 2023 and is listed as made against the show-cause notice. Latest: 21 Mar 2023, Filing of REP-I (Part A-H) for the project recorded, submitted against the show-cause notice.
- RERA-GRG-3001-2022: The Authority's case RERA-GRG-3001-2022 is titled 'HARERA Gurugram through [a named individual] v/s Experion Developers Pvt. Ltd. & others'. The page does not describe the reason for the case. The user's note says the Authority started it against the promoter, but the page does not state this. Status: The page shows 'Online complaint not yet received at office'. Complaint dispatched shows 'Not Yet'. Next date of hearing is 'NA'. The complaint listing details table is empty.
- RERA-GRG-3502-2022: The Authority started this case itself by issuing a show cause notice to the promoter, Experion Developers Pvt. Ltd. and others, for not submitting quarterly progress reports (QPRs). Status: The case is at the first hearing stage. A first hearing was listed for 27 Jun 2022. The page shows no proceedings or order for that hearing. Replies from the promoter's side were received up to 08 Aug 2022. Latest: 08 Aug 2022, Further replies to the show cause notice for non-submission of QPRs were received, covering QPR periods from 01.04.2019 to 31.03.2020 and from 01.04.2020 to 31.03.2021.
- RERA-GRG-3777-2022: Show cause notice to the promoter for not applying to extend its project registration, and for not submitting a completion, part completion or occupation certificate, and for not submitting the required documents. The Authority started this case itself, on its own motion. Status: First hearing was listed for 28 Jun 2022. The status shows 'First Hearing'. No proceedings of the day, bench order or order upload are recorded. Latest: 28 Jun 2022, First hearing was listed. No proceedings of the day or order are recorded on the page.
- RERA-GRG-3778-2022: Suo motu case by the Authority against Experion Developers Pvt. Ltd. for allegedly not finishing its Commercial Colony project in the time it had declared, which is a violation of section 4(2)(l)(C) of the Real Estate (Regulation and Development) Act, 2016. Status: Pending. The latest proceedings are dated 20 Sep 2024. The promoter had no representative present. The Authority directed that the status of the occupation certificate for the registered area be examined and that the matter be put up on file. Latest: 20 Sep 2024, No one appeared for the promoter. The Authority noted a reply dated 02 Aug 2024 in which the promoter submitted occupation certificate copies dated 15 Jan 2019 and 31 May 2022. The Authority directed that the status of the occupation certificate with respect to the registered area be examined and the matter put up on file.
- RERA-GRG-5120-2022: A complaint numbered RERA-GRG-5120-2022, titled HARERA Gurugram through a named representative versus Experion Developers Pvt. Ltd. and others. The page shows only the notice, first hearing listing and document submission. The grounds of the complaint are not stated. Status: Listed at the first hearing stage. The first hearing was listed for 30 Jun 2022. The page records no proceedings or order for that hearing. Documents were submitted by the complainant side on 16 Jul 2022. Latest: 16 Jul 2022, Documents were submitted by the complainant side under dak ID 37963, marked as a new complaint.
- RERA-GRG-5469-2019: The Authority's own proceeding against the promoter (Experion Developers Pvt. Ltd. and others) for not filing project updates (REP-I Part A to H) online and in hard copy, under section 11(1) of the Act and related rules. Status: Pending on the case page. The last recorded hearing was 22 Jan 2020, and the next hearing was fixed for 24 Feb 2020 with no proceedings shown. A fourth notice under section 42(1D) was dispatched on 20 Jul 2020. Latest: 20 Jul 2020, Fourth notice under section 42(1D) dispatched, with a tracking ID recorded. Penalty: The Authority decided to impose a penalty of 25000 rupees per day from 31 Dec 2019 while the default continues, up to five percent of the estimated project cost, for non-compliance with its directions (order of 22 Jan 2020). The case page does not show that any penalty has been paid or finally imposed.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|
| Decided cases against EXPERION DEVELOPERS PVT. LTD. & OTHERS (all its projects) | 10 (Complaint: 10) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in