Commercial Colony

Elan Buildcon · Sector 84, Gurugram

Registered with RERA: Sep 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Elan Buildcon

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameCOMMERCIAL COLONY
Builder (promoter)ELAN BUILDCON PVT. LTD.
LocationSECTOR 84, VILLAGE HAYATPUR, GURUGRAM
RERA project IDRERA-GRG-400-2019
Registration certificate number190 OF 2017 DATED 14.09.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to13/09/2023
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area5.91875 acres
Licence34 of 2014 dated 12.06.2014
Estimated cost of the project₹31,062 lakh (₹310.62 crore)
Total units (plots, apartments, shops)396
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered76
Units unsold when registered320
Layout plan approved on24-08-2017
Building plans approved on24-08-2017

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date13-09-2023
Revised completion date13-09-2023
Infrastructure: projected completion13-09-2023
Infrastructure: percentage complete when registered42%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on13-Oct-2026
Quarterly reports listed on the portal32

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹168.82 lakh (₹1.69 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹19,969.82 lakh (₹199.7 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹7,818.73 lakh (₹78.19 crore)
Project bank account (escrow): deposited in the quarter₹118.17 lakh (₹1.18 crore)
Project bank account (escrow): withdrawn in the quarter₹118.32 lakh (₹1.18 crore)
Project bank account (escrow): balance at quarter end₹0.01 lakh (₹0 crore)
Units in the project (apartments / plots)1000 apartments
Sold in the quarter2 apartments
EDC (development charges): paid / due as on date₹3,984 lakh (₹39.84 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 12-06-2014
  • Demarcation Plan: Obtained Approval 12-06-2014
  • Zoning Plan: Obtained Approval 12-06-2014
  • Service Plans: Obtained Approval 17-12-2021
  • Electricity Plans: Obtained Approval 05-10-2021
  • Fire NOC: Obtained Approval 01-09-2021

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 07 Oct 2026, for July to September 2026
By part
  • Elan Miracle (entire project is one building): 100%, 08 floors slabs laid; sub-structure, super-structure, MEP and finishing are each certified at 100% of proposed work; open parking, parks, play equipment and benches show NIL
Unclear in the certificate
  • No single overall percentage is stated; the certificate gives percentages per work component and per common area item.
  • Work done during the quarter is shown as a dash for every component, so quarter-wise progress cannot be read.
  • Some flat-level items show NIL (fixing of door and window frames in flats, flooring in units) while the same table's totals show 100%; the certificate does not explain this.
  • Electrical wiring within flats is recorded as 'Conducting' and plumbing as 'All Piping', yet both are shown at 100%.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against ELAN BUILDCON PVT. LTD. (all its projects)94 (Complaint: 90; Compensation: 3; Execution of an earlier order: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026