Projects · EMINENCE TOWNSHIPS INDIA PVT. LTD
Commercial Colony
Eminence Townships India · Sector 112, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Dec 2020 (date has passed)
- HRERA has opened 7 cases of its own against the builder over this project (7 open):
- Did not file REP-I (Parts A to H) on web portal for offline project (Jun 2022, open)
- Did not submit quarterly progress report (May 2022, open)
- Did not submit completion, part completion or occupation certificate after registration extension lapsed (Jun 2022, open)
- 4 more cases: reply 4
Will it be delivered on time?
- Deadline Jul 2019, never extended (date has passed)
- Occupation certificate (Jul 2019) covers: Commercial colony towers and basement in Sector 112 (no flats listed)
- Money: ₹162.4 crore spent of ₹173.6 crore; ₹11.2 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 473 units: 335 sold, 138 unsold (builder's certificate, Quarter ending September 2026)
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 5.9 km by road (12 min by car)
- Cyber City 49 min · Airport 30 min by car at 9:30 am
- Within 3 km: 3 hospitals, 1 school, 1 mall
Location shown for Sector 112; the exact site was not found.
The builder: Eminence Townships India
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 25 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | COMMERCIAL COLONY |
|---|---|
| Builder (promoter) | EMINENCE TOWNSHIPS INDIA PVT. LTD |
| Location | SECTOR 112, SECTOR ROAD, BAJG HERA, GURUGRAM |
| RERA project ID | RERA-GRG-426-2019 |
| Registration certificate number | 74 OF 2017 DATED 21.08.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/12/2020 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 11634.69 acres |
| Licence | 35 of 2012 |
| Estimated cost of the project | ₹14,071 lakh (₹140.71 crore) |
| Total units (plots, apartments, shops) | 485 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 274 |
| Units unsold when registered | 211 |
| Layout plan approved on | 08-02-2018 |
| Building plans approved on | 08-02-2018 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 11-07-2019 |
|---|---|
| Revised completion date | 11-07-2019 |
| Infrastructure: projected completion | 11-07-2019 |
| Infrastructure: percentage complete when registered | 0% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 14-Oct-2026 |
| Quarterly reports listed on the portal | 32 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹293.76 lakh (₹2.94 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹-112 lakh (₹-1.12 crore) |
| Put in by the builder in the quarter | ₹-20 lakh (₹-0.2 crore) |
| Spent on construction of apartments in the quarter | ₹55.12 lakh (₹0.55 crore) |
| Spent on infrastructure in the quarter | ₹66.45 lakh (₹0.66 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹37.33 lakh (₹0.37 crore) |
| Project bank account (escrow): deposited in the quarter | ₹213.15 lakh (₹2.13 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹212.5 lakh (₹2.13 crore) |
| Project bank account (escrow): balance at quarter end | ₹1 lakh (₹0.01 crore) |
| Units in the project (apartments / plots) | 473 apartments |
| Sold in the quarter | Not found in the records checked |
| EDC (development charges): paid / due as on date | ₹1,194 lakh (₹11.94 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Sep 2026, for September 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against EMINENCE TOWNSHIPS INDIA PVT. LTD (all its projects) | 25 (Complaint: 20; Execution of an earlier order: 5) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in