Projects · ROF HOUSING & INFRASTRUCTURE PVT. LTD.
Commercial Project Of Area 0.4875 Acres
ROF Housing & Infrastructure · Sector 43, Gurugram
Registered with RERA: Jan 2018
Is it legal?
- RERA registered, valid till Jan 2021 (date has passed)
- HRERA has opened 4 cases of its own against the builder over this project (4 open):
- Did not file REP-I (Part A to H) on the Authority's web portal, despite a notice to do so (Jun 2022, open)
- Did not submit quarterly progress report (May 2022, open)
- Failed to file REP-I project updates on portal, including quarterly progress reports (Nov 2019, open). At stake: ₹25,000 per day from 31 Dec 2019, up to five percent of project cost
- 1 more case: reply 4
Will it be delivered on time?
- Deadline Dec 2019, never extended (date has passed)
- Occupation certificate (Dec 2019) covers: Commercial building in Sector-43, Gurugram (no flats listed)
- Construction, as certified by the architect (Apr–Jun 2024):
- Done: 11 parts
What's on offer?
- 77 units: 15 sold, 62 unsold (builder's certificate, June 2024 quarter)
- Sizes declared at registration (70 units):
- 70 units averaging about 450 sq ft carpet (1 tower)
- The builder gave each tower's total carpet area, not each flat's size; averages divide that total by the number of units. HRERA lists flats, shops and other buildings together and does not say which size is 2, 3 or 4 BHK.
Location
- Nearest metro: Millennium City Centre Gurugram, 1.6 km by road (8 min by car)
- Cyber City 15 min · Airport 33 min by car at 9:30 am
- Within 3 km: 23 hospitals, 26 schools, 21 malls
Location shown for Sector 43; the exact site was not found.
The builder: ROF Housing & Infrastructure
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | COMMERCIAL PROJECT OF AREA 0.4875 ACRES |
|---|---|
| Builder (promoter) | ROF HOUSING & INFRASTRUCTURE PVT. LTD. |
| Location | SECTOR-43, VILLAGE KANHAI, GU RUGRAM, HARYANA |
| RERA project ID | RERA-GRG-589-2020 |
| Registration certificate number | 03 OF 2018 DATED 01.01.2018 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 01/01/2021 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 0.4875 acres |
| Licence | 41 of 2017(06.07.2017) |
| Estimated cost of the project | ₹1,745 lakh (₹17.45 crore) |
| Total units (plots, apartments, shops) | 70 |
| Unit sizes (carpet area, as declared) | 70 units averaging about 450 sq ft carpet (1 tower) |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 01-01-2018 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-01-2018 |
|---|---|
| Likely completion date | 17-12-2019 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/06/2024 (APR-JUN) |
| Latest report submitted on | 31-Aug-2024 |
| Quarterly reports listed on the portal | 23 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/06/2024 (APR-JUN))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | Not found in the records checked |
| Sold in the quarter | Not found in the records checked |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 30 Jun 2024, for 30 Jun 2024 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against ROF HOUSING & INFRASTRUCTURE PVT. LTD. (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in