Projects · VICTORY INFRAEDGE PVT.LTD.
Commercial Project Of Area 2 Acres
Victory Infraedge · Sector 48, Gurugram
Registered with RERA: Dec 2017
Is it legal?
- RERA registered, valid till Dec 2028
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Did not submit a quarterly progress report (May 2022, open)
- Did not apply to extend registration or submit completion or occupancy certificate or required documents (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- 3 more cases: reply 4
Will it be delivered on time?
- Original deadline Sep 2025, extended to Dec 2028
- The order keeps buyers' right to a refund or interest for the delay
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jan–Mar 2026):
- In progress: Internal roads & pavements 15%, Water supply 10%, Water conservation, rain water harvesting, percolating well/pit 4%, Fire protection and fire safety requirements 4%, Sewerage 1%, Storm water drains 1%, and 7 more
- Money: ₹104.8 crore spent of ₹190.5 crore; ₹85.6 crore still to spend (CA certificate, Mar 2026)
What's on offer?
- 322 units: 129 sold, 193 unsold (builder's certificate, Mar 2026)
- Registration now covers 322
Location
- Nearest metro: Millennium City Centre Gurugram, 7.4 km by road (35 min by car)
- Cyber City 44 min · Airport 49 min by car at 9:30 am
- Within 3 km: 14 hospitals, 15 schools, 7 malls
Location shown for Sector 48; the exact site was not found.
The builder: Victory Infraedge
- 1 project registered in Gurugram
- 0 with an occupation certificate on record
- 5 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | COMMERCIAL PROJECT OF AREA 2 ACRES |
|---|
| Builder (promoter) | VICTORY INFRAEDGE PVT.LTD. |
|---|
| Location | SECTOR 48,FAZILPUR JHARSA, GU RUGRAM, HARYANA |
|---|
| RERA project ID | RERA-GRG-616-2020 |
|---|
| Registration certificate number | 390 OF 2017 DATED 22.12.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 31/12/2028 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 2 acres |
|---|
| Licence | 04 OF 2011 |
|---|
| Estimated cost of the project | ₹11,300 lakh (₹113 crore) |
|---|
| Total units (plots, apartments, shops) | 256 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
|---|
| Units booked when registered | 176 |
|---|
| Units unsold when registered | 80 |
|---|
| Layout plan approved on | 01-10-2015 |
|---|
| Building plans approved on | Not found in the records checked |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 31-12-2018 |
|---|
| Revised completion date | 30-09-2025 |
|---|
| Infrastructure: projected completion | 30-09-2025 |
|---|
| Infrastructure: percentage complete when registered | 50% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 31/03/2026 (JAN-MAR) |
|---|
| Latest report submitted on | 14-Apr-2026 |
|---|
| Quarterly reports listed on the portal | 30 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2026 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹1,481.88 lakh (₹14.82 crore) |
|---|
| Put in by the builder in the quarter | ₹326.09 lakh (₹3.26 crore) |
|---|
| Spent on construction of apartments in the quarter | ₹325.82 lakh (₹3.26 crore) |
|---|
| Spent on infrastructure in the quarter | ₹0 |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹131 lakh (₹1.31 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0.02 lakh (₹0 crore) |
|---|
| Units in the project (apartments / plots) | 322 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹1,966.07 lakh (₹19.66 crore) paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 22-06-2011
- Zoning Plan: Obtained Approval 22-06-2011
- Service Plans: Obtained Approval 24-02-2015
- Electricity Plans: Obtained Approval 05-03-2025
- Site Plans: Obtained Approval 16-06-2014
- Building Plans: Obtained Approval 16-06-2014
- Fire NOC: Obtained Approval 27-09-2025
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 02 Apr 2026, for 31 Mar 2026 |
|---|
| By part | - Vantaje (Table A, building/tower): Sub-structure 75%, super-structure 45%, mechanical MEP 10%, electrical MEP 8%, plumbing and firefighting MEP 7%, internal finishing 2%, external finishing 5% of total proposed work. Lifts, roof waterproofing and entrance lobby finishing not yet commenced.
- Internal roads & pavements: 15%
- Water supply: 10%
- Sewerage (chamber, lines, septic tanks, STP): 1%
- Storm water drains: 1%
- Landscaping & tree plantation: 0%
- Parks and playgrounds: 0%
- Street lighting/electrification: 1%
- Treatment and disposal of sewage and sullage water/STP: 1%
- Solid waste management & disposal: 1%
- Water conservation, rain water harvesting, percolating well/pit: 4%
- Fire protection and fire safety requirements: 4%
- Electrical meter room, sub-station, receiving station: 0%
- Underground water tank: 1%
|
|---|
| Unclear in the certificate | - The certificate gives percentages by activity (Table A) and by common area (Table B), not one overall figure for the project.
- Table A is headed as one building/tower, 'Vantaje'; no separate tower-wise figures are given.
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | - Extension 390 of 2017 / 7(3) / 95 / 2025 / 37 dated 23 Dec 2025: registration extended from 31 Dec 2018 to 31 Dec 2028. Conditions include: Registration is granted under section 7(3) of the Real Estate (Regulation & Development) Act, 2016, and remains in force subject to the terms and conditions stated.; Sale must be on a carpet area basis, not super area basis, and the total sale consideration must include all charges. No separate EDC/IDC is payable except the total sale consideration.; The promoter must enter into a written agreement for sale with allottees and must not accept more than ten percent of the cost as advance payment before that agreement is registered.; The promoter must offer to execute and register a conveyance deed in favour of the allottee or association of allottees as per section 17 of the Act.; The promoter must deposit one hundred percent of amounts realised from allottees in a separate schedule bank account to cover construction and proportionate land cost.; The authority imposed a penalty of Rs. 25 lakhs for violation of sections 3 and 4 of the Act. The promoter deposited this amount before the certificate was issued (DD dated 04.11.2025).; The registration is without prejudice to allottees' rights under section 18(1) for delay possession charges. The promoter must pay delay possession charges from its own funds, and project cash inflow must not be used for this purpose.; The promoter declared completion of the entire project by 31.12.2028. Licences and approvals may expire within the declared completion period, and the promoter must renew them when due.; The promoter must submit monthly comparison of proposed work (as per the PERT chart) and actual work on the 7th day of every consecutive month.; The promoter must submit quarterly progress reports and an occupation certificate once granted.; Sale through real estate agents is not permitted without a prospectus or brochure and drawings, and agents must be registered with HARERA.; No subvention or assured return scheme is allowed without prior approval of the authority.; The promoter must not create further encumbrance on future receivables or separate RERA accounts, except the existing charge in favour of an existing lender.; If conditions are not fulfilled, the authority may take action, including revoking the registration.
|
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 6 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 3; Pending: 2 |
|---|
| Proceedings | - RERA-GRG-3041-2022: Case RERA-GRG-3041-2022 lists HARERA Gurugram as the party, with Victory Infraedge Pvt. Ltd. named against it. The page does not state what the case is about. Status: The page shows 'Online complaint not yet received at office'. The next hearing date is 'Not Yet'. No hearing or order is listed.
- RERA-GRG-3557-2022: Show cause notice to the promoter, Victory Infraedge Pvt Ltd, for not submitting a quarterly progress report. The Authority listed a first hearing on 27 Jun 2022. Status: First hearing listed for 27 Jun 2022. The page shows no proceedings of the day and no order uploaded. Latest: 27 Jun 2022, First hearing listed. Status shown as First Hearing. Proceedings and bench order fields are blank.
- RERA-GRG-3865-2022: Show cause notice to the promoter for not applying to extend the registration, and for not submitting a completion certificate, part completion certificate or occupation certificate, and for not submitting the required documents. The Authority started this case itself. Status: First hearing listed for 28 Jun 2022. The case page shows the status as FIRST HEARING, with no proceedings, bench order or order uploaded. Latest: 28 Jun 2022, First hearing listed. No proceedings or order are recorded on the case page.
- RERA-GRG-3867-2022: Suo motu proceedings by the Authority against Victory Infraedge Pvt. Ltd. for allegedly not completing its Commercial Colony project within the time it declared, under section 4(2)(l)(C) of the RERA Act, 2016. The Authority issued show-cause notices and has been listing hearings since 2022. Status: Pending. The next hearing is listed for 23 Jul 2025. The promoter has not appeared at most hearings. The case page also shows the registration certificate as expired. Latest: 10 Jun 2025, Matter listed to come up on 23 Jul 2025.
- RERA-GRG-4960-2022: A complaint numbered RERA-GRG-4960-2022, listed as HARERA Gurugram versus Victory Infraedge Pvt. Ltd. (the promoter). The document does not state the grievance or the relief sought. Status: At first hearing stage. A first notice was dispatched on 03 Jun 2022 and the matter was listed for hearing on 30 Jun 2022. The page records no proceedings or order for that hearing. Documents were submitted on 16 Jul 2022. Latest: 16 Jul 2022, Documents submitted by the complainant's side under Dak ID 38112, marked as a new complaint.
- RERA-GRG-5326-2019: Promoter Victory Infraedge Pvt. Ltd. did not file the project updates (REP-I Part A to H) on the Authority's web portal as required by law. The Authority directed filing, imposed a per-day penalty, and issued a show cause notice on why the registration certificate should not be revoked. Status: Pending. The case page lists the next hearing as 24 Feb 2020 and shows the status as PENDING. A fourth notice was dispatched on 20 Jul 2020. Latest: 20 Jul 2020, Fourth notice dispatched and complaint marked as dispatched. The notice refers to a section 42 provision. Penalty: Rs 25,000 per day from 31 Dec 2019 while the default continues, cumulatively up to five percent of the estimated project cost as determined by the Authority. Ordered on 22 Jan 2020.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|
| Decided cases against VICTORY INFRAEDGE PVT.LTD. (all its projects) | 5 (Complaint: 5) |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026