Commercial Project

Elan · Sector 80, Gurugram

Registered with RERA: Sep 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 80; the exact site was not found.

The builder: Elan

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameCOMMERCIAL PROJECT
Builder (promoter)ELAN LIMITED
LocationSECTOR 80, VILLAGE NAURANGPUR , GURUGRAM
RERA project IDRERA-GRG-398-2019
Registration certificate number189 OF 2017 DATED 14.09.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to13/09/2022
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area2.9875 acres
Licence82 OF 2009 DATED 08.12.2009
Estimated cost of the project₹16,607 lakh (₹166.07 crore)
Total units (plots, apartments, shops)531
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered430
Units unsold when registered101
Layout plan approved on08-05-2019
Building plans approved on08-05-2019

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date13-09-2022
Revised completion date13-09-2022
Infrastructure: projected completion13-09-2022
Infrastructure: percentage complete when registered85%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal32

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹2.6 lakh (₹0.03 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹10,900 lakh (₹109 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹3,321 lakh (₹33.21 crore)
Project bank account (escrow): deposited in the quarter₹1.82 lakh (₹0.02 crore)
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹1.89 lakh (₹0.02 crore)
Units in the project (apartments / plots)539 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹967 lakh (₹9.67 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 08-12-2009
  • Zoning Plan: Obtained Approval 02-12-2010
  • Service Plans: Obtained Approval 18-10-2022
  • Electricity Plans: Obtained Approval 01-09-2015
  • Site Plans: Obtained Approval 08-05-2019
  • Building Plans: Obtained Approval 08-05-2019
  • Fire NOC: Obtained Approval 19-02-2020

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 06 Oct 2026, for July to September 2026
By part
  • Elan Mercado (entire project is one building, 18 floors): 100%, All listed sub-structure, super-structure, MEP, finishing and common area items shown as 100% complete; 18 floors of slabs laid by end of quarter
Unclear in the certificate
  • The HARERA registration date is written as '14.09.207' in the certificate, which appears to be a typing error and is not clear.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusOnline Complaint Not Yet Received At Office: 1; Pending: 2; First Hearing: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against ELAN LIMITED (all its projects)35 (Complaint: 32; Execution of an earlier order: 1; Compensation: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026