Projects · COSMOS INFRA ENGINEERING INDIA PVT LTD
Cosmos EXPRESS99 / Cascade Garden
Cosmos Infra Engineering India · Sector 99, Gurugram
Registered with RERA: Oct 2019
Is it legal?
- RERA registered, valid till Mar 2025 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (4 open, 1 closed):
- Did not apply to extend registration and did not submit completion or occupation certificate (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- Did not submit renewal of license needed to meet registration certificate conditions (Jun 2022, closed)
- 2 more cases: reply 4
- 1 complaint about this project decided by HRERA since Nov 2023 (1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Original deadline Sep 2021, extended to Mar 2025
- The order keeps buyers' right to a refund or interest for the delay
- Occupation certificate (Aug 2025) covers: Towers 1, 2, 4, 5, S and part EWS (398 flats)
- Construction, as certified by the architect (Jan–Mar 2026):
- Done: 17 parts
- In progress: Shopping area 99%, Electrical 98%, Plumbing and firefighting 98%, Internal finishing 98%, Fixing of children play equipment 96%
- Money: ₹224.8 crore spent of ₹254.8 crore; ₹30 crore still to spend (CA certificate, Mar 2026)
Location
- Nearest metro: Millennium City Centre Gurugram, 16.4 km by road (53 min by car)
- Cyber City 55 min · Airport 35 min by car at 9:30 am
- Within 3 km: 2 hospitals, 0 schools, 1 mall
The builder: Cosmos Infra Engineering India
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 17 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | COSMOS EXPRESS99 / CASCADE GARDEN |
|---|---|
| Builder (promoter) | COSMOS INFRA ENGINEERING INDIA PVT LTD |
| Location | VILLAGE DHANKOT, SECTOR-99 |
| RERA project ID | RERA-GRG-276-2019 |
| Registration certificate number | GGM/368/100/2019/62 DATED 14.10.2019 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/03/2025 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 5.468 acres |
| Licence | 70 of 2011 dt. 22.07.2011 and 82 of 2012 dt. 27.08.2012 |
| Estimated cost of the project | ₹22,362 lakh (₹223.62 crore) |
| Total units (plots, apartments, shops) | 401 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 237 |
| Units unsold when registered | 164 |
| Layout plan approved on | 07-07-2017 |
| Building plans approved on | 07-07-2017 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 30-09-2017 |
|---|---|
| Revised completion date | 30-09-2021 |
| Infrastructure: projected completion | 30-09-2021 |
| Infrastructure: percentage complete when registered | 25% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/03/2026 (JAN-MAR) |
| Latest report submitted on | 23-Jun-2026 |
| Quarterly reports listed on the portal | 25 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2026 (JAN-MAR))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹48.23 lakh (₹0.48 crore) |
| Spent on infrastructure in the quarter | ₹39.24 lakh (₹0.39 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹18.64 lakh (₹0.19 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 401 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹1,168.18 lakh (₹11.68 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 04 Apr 2026, for 31 Mar 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|---|
| Cases | |
| Decided cases against COSMOS INFRA ENGINEERING INDIA PVT LTD (all its projects) | 17 (Execution of an earlier order: 2; Complaint: 15) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in