Projects · ADHIKAANSH REALTORS PRIVATE LIMITED ,AAWAM RESIDENCY PRIVATE LIMITED
DDJAY Residential Plotted Colony
Adhikaansh Realtors · Sector 89, Gurugram
Registered with RERA: Oct 2021
Is it legal?
- RERA registered, valid till Oct 2027
- HRERA opened a case of its own against the builder in Jun 2022 (still open)
Will it be delivered on time?
- Original deadline Oct 2024, extended 2 times to Oct 2025
- The order keeps buyers' right to a refund or interest for the delay
- 13 occupation certificates issued:
- Aug 2024: Six buildings on Plots A-117 to A-122, Sector 89 (4 flats)
- Aug 2024: Plots A-137 to A-142: flats above stilt parking (4 flats)
- Aug 2024: Six plots A-157 to A-162, Sector 89, Hayatpur (4 flats)
- Jul 2024: Plots B-22 to B-27, Sector 89, residential floors (4 flats)
What's on offer?
- Registration now covers 960 residential units and 10 commercial units
- 930 plots, 1,30,349 sq yd
Location
- Nearest metro: Millennium City Centre Gurugram, 19.8 km by road (52 min by car)
- Cyber City 58 min · Airport 41 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 0 malls
Location shown for Sector 89; the exact site was not found.
The builder: Adhikaansh Realtors
- 2 projects registered in Gurugram
- 1 with an occupation certificate on record
- 3 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | DDJAY RESIDENTIAL PLOTTED COLONY |
|---|---|
| Builder (promoter) | ADHIKAANSH REALTORS PRIVATE LIMITED ,AAWAM RESIDENCY PRIVATE LIMITED |
| Location | SECTOR-89, GURUGRAM MANESAR U RBAN COMPLEX, GURUGRAM, HARYANA. |
| RERA project ID | RERA-GRG-920-2021 |
| Registration certificate number | GGM/500/232/2021/68 DATED 25.10.2021 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/10/2027 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 52.275 acres |
| Licence | 32 of 2021 dated 03.07.2021 |
| Estimated cost of the project | ₹53,328.28 lakh (₹533.28 crore) |
| Total units (plots, apartments, shops) | 930 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 03-07-2021 |
| Building plans approved on | 03-07-2021 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-09-2021 |
|---|---|
| Likely completion date | 31-10-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 01-Oct-2026 |
| Quarterly reports listed on the portal | 19 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹0 |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | Not found in the records checked |
| Sold in the quarter | Not found in the records checked |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Unclear in the certificate |
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 1 |
|---|---|
| By status | Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against ADHIKAANSH REALTORS PRIVATE LIMITED ,AAWAM RESIDENCY PRIVATE LIMITED (all its projects) | 3 (Complaint: 3) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in