Delphine Central Park Estates Phase III

St. Nicholas Estate Development · Sector 104, Gurugram

Registered with RERA: Oct 2025

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: St. Nicholas Estate Development

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameDELPHINE CENTRAL PARK ESTATES PHASE III
Builder (promoter)ST. NICHOLAS ESTATE DEVELOPMENT PVT LTD
LocationSECTOR-104, GURUGRAM
RERA project IDRERA-GRG-2065-2025
Registration certificate numberGGM/998/730/2025/101 DATED 16.10.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/11/2032
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area2.606 acres
Licence186 of 2024 dated 16.12.2024
Estimated cost of the project₹73,860.12 lakh (₹738.6 crore)
Total units (plots, apartments, shops)536
Unit sizes (carpet area, as declared)72 units averaging about 3,500 sq ft carpet (1 tower)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on27-08-2025
Building plans approved on27-08-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-10-2025
Likely completion date31-12-2032

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal3

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹671.96 lakh (₹6.72 crore)
Spent on construction of apartments in the quarter₹291.17 lakh (₹2.91 crore)
Spent on infrastructure in the quarter₹171.18 lakh (₹1.71 crore)
Other costs in the quarter (EDC, taxes, etc.)₹209.61 lakh (₹2.1 crore)
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹0
Units in the project (apartments / plots)72 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹1,843.24 lakh (₹18.43 crore) paid; ₹0 due
Approvals listed
  • Layout Plan: Obtained Approval 27-08-2025
  • Demarcation Plan: Obtained Approval 17-12-2024
  • Zoning Plan: Obtained Approval 17-12-2024
  • Service Plans: Obtained Approval 30-09-2025

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 30 Sep 2026, for 30 Sep 2026
By part
  • Tower A - sub structure: 58.87%, Percentage of total proposed work for sub structure. Excavation shown as in progress with 0% in the sub-structure status table; no basement or raft work started. Building has G+37 floors.
  • Tower A - super structure: 2.93%, Cumulative number of slabs laid by end of quarter is 0 (inclusive of basements). Walls, staircase and lift wells at 0%.
  • Tower A - MEP: 0%, Mechanical, electrical, plumbing and HVAC works not started.
  • Tower A - finishing: 0%, Internal and external finishing not started.
  • Tower A - other items: 0%
  • Commercial - sub structure: 0%
  • Commercial - super structure: 2.93%
  • Commercial - MEP, finishing and other items: 0%, Not started, as certified.
Unclear in the certificate
  • Tower A sub-structure is certified at 58.87% in Table A, but excavation is shown as in progress at 0% in the sub-structure status table. The certificate does not explain this difference.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against ST. NICHOLAS ESTATE DEVELOPMENT PVT LTD (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in