Projects · MILLENNIUM DIPLOMATS PVT.LTD.

Diplomats Golf Link

Millennium Diplomats · Sector 110, Gurugram

Registered with RERA: Aug 2021

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Millennium Diplomats

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameDIPLOMATS GOLF LINK
Builder (promoter)MILLENNIUM DIPLOMATS PVT.LTD.
LocationVILLAGE SARAI ALWARDI,SECTOR- 110
RERA project IDRERA-GRG-763-2020
Registration certificate numberGGM/465/197/2021/33 DATED 10.08.2021
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to04/09/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area40610.14 acres
Licence100 of 2019
Estimated cost of the project₹36,805.16 lakh (₹368.05 crore)
Total units (plots, apartments, shops)1517
Unit sizes (carpet area, as declared)72 units averaging about 350 sq ft carpet (2 towers); 1,445 units averaging about 600 sq ft carpet (11 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on15-03-2021
Building plans approved on15-03-2021

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-07-2021
Likely completion date31-03-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2026 (JAN-MAR)
Latest report submitted on25-Jun-2026
Quarterly reports listed on the portal18

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2026 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹421.83 lakh (₹4.22 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹883.82 lakh (₹8.84 crore)
Spent on infrastructure in the quarter₹45 lakh (₹0.45 crore)
Other costs in the quarter (EDC, taxes, etc.)₹111.13 lakh (₹1.11 crore)
Project bank account (escrow): deposited in the quarter₹302.22 lakh (₹3.02 crore)
Project bank account (escrow): withdrawn in the quarter₹714 lakh (₹7.14 crore)
Project bank account (escrow): balance at quarter end₹377.88 lakh (₹3.78 crore)
Units in the project (apartments / plots)1445 apartments
Sold in the quarter5 apartments
EDC (development charges): paid / due as on date₹1,576.12 lakh (₹15.76 crore) paid; ₹0 due
Approvals listedNot found in the records checked

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 05 Apr 2026, for 31 Mar 2026
By part
  • Towers 1 to 11 (Table A, as listed in the certificate): Basement RCC and raft 100%; terrace slab casted; ground to terrace walls and staircase RCC 100%; lifts installation 90%; overhead tanks 100%; underground water tank 70%; internal plaster 60%; external plaster 40%; flooring in units 95%; waterproofing of bathroom, kitchen and balcony 95%; door and window frame fittings completed; electrical conduiting 75%; plumbing 80%
Unclear in the certificate
  • The certificate gives no single overall percentage of completion for the project.
  • Table A gives rupee values in lakh for each component but leaves the percentage column blank.
  • Table A covers towers 1 to 11, but the activity status table refers to a single building with G+23 floors, so it is not clear which tower each status applies to.
  • The percentage of work done column in Table B is blank for most items; only text status is given.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed3
By statusFirst Hearing: 2; Scrutinized: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project3
Cases
Decided cases against MILLENNIUM DIPLOMATS PVT.LTD. (all its projects)3 (Complaint: 3)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in