Projects · DLF UTILITIES LIMITED
DLF Gardencity
DLF Utilities · Sector 91, Gurugram
Registered with RERA: Jun 2021
Is it legal?
- RERA registered, valid till Jun 2023 (date has passed)
- HRERA has opened 2 cases of its own against the builder over this project (2 open):
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jul 2024, open)
- Did not submit quarterly progress report (May 2022, open)
- 1 complaint about this project decided by HRERA since Nov 2023 (1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Jun 2023, never extended (date has passed)
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Jul–Sep 2026):
- Done: 8 parts
- Money: ₹134.6 crore spent of ₹143.9 crore; ₹9.3 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 109 units: 0 sold, 109 unsold (builder's certificate, Sep 2026)
- 109 plots, 199–610 sq yd
Location
- Nearest metro: Millennium City Centre Gurugram, 23 km by road (58 min by car)
- Cyber City 65 min · Airport 49 min by car at 9:30 am
- Within 3 km: 0 hospitals, 0 schools, 0 malls
The builder: DLF Utilities
- 6 projects registered in Gurugram
- 5 with an occupation certificate on record
- 9 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | DLF GARDENCITY |
|---|---|
| Builder (promoter) | DLF UTILITIES LIMITED |
| Location | DLF GARDENCITY, SECTOR 91/92 |
| RERA project ID | RERA-GRG-834-2021 |
| Registration certificate number | GGM/455/187/2021/23 DATED 15.06.2021 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 27/06/2023 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 16.25 acres |
| Licence | 13 of 2019 Dated 06.02.2019 |
| Estimated cost of the project | ₹13,456.97 lakh (₹134.57 crore) |
| Total units (plots, apartments, shops) | 109 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 06-02-2019 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 07-07-2021 |
|---|---|
| Likely completion date | 27-06-2023 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 13-Oct-2026 |
| Quarterly reports listed on the portal | 21 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹1,944.69 lakh (₹19.45 crore) |
| Spent on infrastructure in the quarter | ₹0 |
| Other costs in the quarter (EDC, taxes, etc.) | ₹11,515.21 lakh (₹115.15 crore) |
| Project bank account (escrow): deposited in the quarter | ₹0 |
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
| Project bank account (escrow): balance at quarter end | ₹0 |
| Units in the project (apartments / plots) | 109 plots |
| Sold in the quarter | 0 plots |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 08 Oct 2026, for 30 Sep 2026 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|---|
| Cases | |
| Decided cases against DLF UTILITIES LIMITED (all its projects) | 9 (Complaint: 8; Compensation: 1) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in