DLF Privana North

DLF · Sector 76, Gurugram

Registered with RERA: Jun 2025

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: DLF

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameDLF PRIVANA NORTH
Builder (promoter)DLF LIMITED
LocationSECTOR 76/77
RERA project IDRERA-GRG-1781-2024
Registration certificate numberGGM/954/686/2025/57 DATED 05.06.2025
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/09/2034
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area17.701 acres
Licence219 of 2023 granted by DTCP valid till 24.10.2028
Estimated cost of the project₹5,45,734.69 lakh (₹5,457.35 crore)
Total units (plots, apartments, shops)1164
Unit sizes (carpet area, as declared)1,152 units of 2,236 sq ft carpet (6 towers); 12 units of 4,847 sq ft carpet (6 towers)
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on07-05-2025
Building plans approved on07-05-2025

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-07-2025
Likely completion date31-03-2034

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal5

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹64,735.36 lakh (₹647.35 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹52,334.05 lakh (₹523.34 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹42,074.69 lakh (₹420.75 crore)
Project bank account (escrow): deposited in the quarter₹45,629.6 lakh (₹456.3 crore)
Project bank account (escrow): withdrawn in the quarter₹-19,383 lakh (₹-193.83 crore)
Project bank account (escrow): balance at quarter end₹2,21,158.92 lakh (₹2,211.59 crore)
Units in the project (apartments / plots)1169 apartments
Sold in the quarter6 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 06-05-2025
  • Zoning Plan: Obtained Approval 06-05-2025
  • Service Plans: Obtained Approval 01-10-2025
  • Site Plans: Obtained Approval 07-05-2025
  • Building Plans: Obtained Approval 07-05-2025

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 08 Oct 2026, for 30 Sep 2026
By part
  • Towers A, B, C, D, E and F (Table A, combined): 30%, Sub structure: excavation and raft completed; basement level 3 work in progress at 56%; basement levels 1 and 2 and super structure items shown as TBS or not started
  • Common areas and facilities (Table B): 0%, All listed services and common area items show 0% work done
Unclear in the certificate
  • Many entries in the super-structure and finishing tables (for example walls, plastering, MEP, flooring and lifts) read 'TBS' with no percentage, so their progress is not stated.
  • Basement levels 1 and 2 and waterproofing of sub structure read 'TBS' with no percentage.
  • Table A gives a single 30% figure for sub structure across all towers, not a separate figure for each tower.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against DLF LIMITED (all its projects)18 (Complaint: 15; Compensation: 3)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in