Projects · TULSIANI CONSTRUCTIONS AND DEVELOPERS PVT.LTD.

Easy Homes

Tulsiani Constructions And Developers · Sector 35, Gurugram

Registered with RERA: Aug 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Tulsiani Constructions And Developers

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameEASY HOMES
Builder (promoter)TULSIANI CONSTRUCTIONS AND DEVELOPERS PVT.LTD.
LocationVILLAGE SOHNA SECTOR-35 GURUG RAM
RERA project IDRERA-GRG-751-2020
Registration certificate number144 OF 2017 DATED 28.08.2017
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to27/08/2022
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area5.0 acres
Licence69 of 2014 dt 25.07.2014
Estimated cost of the project₹12,944 lakh (₹129.44 crore)
Total units (plots, apartments, shops)768
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder1 BHK: 340 sq ft carpet, 288 units; 2 BHK: 506 sq ft carpet, 480 units (source: the builder's registration form (Form A-H))
Units booked when registered689
Units unsold when registered79
Layout plan approved on16-06-2015
Building plans approved on16-06-2015

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date27-08-2021
Revised completion date27-08-2021
Infrastructure: projected completion27-08-2021
Infrastructure: percentage complete when registered43.39%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2023 (JAN-MAR)
Latest report submitted on26-Aug-2025
Quarterly reports listed on the portal18

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2023 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹0.95 lakh (₹0.01 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹83.88 lakh (₹0.84 crore)
Spent on construction of apartments in the quarter₹80 lakh (₹0.8 crore)
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹0
Project bank account (escrow): withdrawn in the quarter₹0
Project bank account (escrow): balance at quarter end₹579.8 lakh (₹5.8 crore)
Units in the project (apartments / plots)768 apartments
Sold in the quarter707 apartments
EDC (development charges): paid / due as on date₹299 lakh (₹2.99 crore) paid; ₹656 lakh (₹6.56 crore) due
Approvals listed
  • Demarcation Plan: Obtained Approval 25-07-2014
  • Zoning Plan: Obtained Approval 25-07-2014
  • Site Plans: Obtained Approval 16-06-2015
  • Building Plans: Obtained Approval 16-06-2015
  • Fire NOC: Obtained Approval 16-05-2017

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 31 Mar 2023
By part
  • Sub structure: 100%
  • Super structure: 100%
  • MEP - Mechanical (lifts, ventilation): 40%
  • MEP - Electrical (conduiting, wiring, fixtures): 60%
  • MEP - Plumbing & Firefighting (piping, pumps, fixtures): 80%
  • Finishing - Internal (plaster, tiling, flooring, painting): 50%
  • Finishing - External (plaster, painting, facade): 85%
  • Internal roads & pavements: 65%
  • Water supply: 65%
  • Sewerage (chamber, lines, septic tanks, STP): 100%
  • Storm water drains: 100%
  • Landscaping & tree plantation: 98%
  • Parks and playgrounds: 60%
  • Fixing of children play equipment: 70%
  • Street lighting / electrification: 65%
  • Treatment and disposal of sewage and sullage water / STP: 45%
  • Solid waste management & disposal: 55%
  • Water conservation, rain water harvesting, percolating well/pit: 85%
  • Energy management (solar): 0%
  • Fire protection and fire safety requirements: 0%
  • Community centre: 0%
Unclear in the certificate
  • Quarter the certificate reports on is not named.
  • Percentages for Parking and for Benches and Shopping area are garbled in the text and could not be matched to these items with certainty, so they are left out.
  • Electrical meter room, sub-station and receiving station is marked NA and is left out.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project4
Cases
Decided cases against TULSIANI CONSTRUCTIONS AND DEVELOPERS PVT.LTD. (all its projects)8 (Complaint: 7; Execution of an earlier order: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026