RERA’d by NeevHQ

Projects · ELAN LIMITED

Elan Paradise

Elan · Sector 50, Gurugram

Registered with RERA: Jul 2022

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Elan

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameELAN PARADISE
Builder (promoter)ELAN LIMITED
LocationREVENUE ESTATE OF VILLAGE ADA MPUR, SUB TEHSIL- WAZIRABAD, SECTOR-50, DISTRICT GURUGRAM, HARYANA
RERA project IDRERA-GRG-1062-2022
Registration certificate numberGGM/584/316/2022/59 DATED 04.07.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to16/06/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area3.35 acres
Licence32 of 2020 and 29 of 2021
Estimated cost of the project₹37,573.1 lakh (₹375.73 crore)
Total units (plots, apartments, shops)457
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered228
Units unsold when registered229
Layout plan approved on27-04-2022
Building plans approved on27-04-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date30-09-2025
Revised completion date16-06-2026
Infrastructure: projected completion01-06-2024
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on15-Oct-2026
Quarterly reports listed on the portal16

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹86.87 lakh (₹0.87 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹25,808 lakh (₹258.08 crore)
Spent on infrastructure in the quarter₹623 lakh (₹6.23 crore)
Other costs in the quarter (EDC, taxes, etc.)₹7,922 lakh (₹79.22 crore)
Project bank account (escrow): deposited in the quarter₹60.81 lakh (₹0.61 crore)
Project bank account (escrow): withdrawn in the quarter₹60.9 lakh (₹0.61 crore)
Project bank account (escrow): balance at quarter end₹0.01 lakh (₹0 crore)
Units in the project (apartments / plots)609 apartments
Sold in the quarterNot found in the records checked
EDC (development charges): paid / due as on date₹1,955.96 lakh (₹19.56 crore) paid; ₹0 due
Approvals listed
  • Zoning Plan: Obtained Approval 01-09-2021
  • Electricity Plans: Obtained Approval 15-03-2022
  • Site Plans: Obtained Approval 27-04-2022
  • Fire NOC: Obtained Approval 01-09-2021

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 10 Oct 2026, for July to September 2026
By part
  • Tower A and Tower B (Table A, combined): Not given as one figure. Sub structure 100%, super structure 100%, mechanical MEP 93%, electrical MEP 90%, plumbing and firefighting 92%, internal finishing 92%, external finishing 96%.
  • Sub structure: 100%, Completed
  • Super structure: 100%, Completed
  • Mechanical MEP: 93%
  • Electrical MEP: 90%
  • Plumbing and firefighting: 92%
  • Internal finishing: 92%
  • External finishing: 96%
  • Lift installation: 70%, Work in progress
  • Overhead tanks: 75%, Work in progress
  • Underground water tank: 100%, Completed
  • Firefighting fittings and equipment as per CFO NOC: 79%, Work in progress
  • Electrical fittings in common areas: 39%, Work in progress
  • Compliance with environment/CRZ NOC conditions: 42%, Work in progress
  • Waterproofing of terraces: 35%, Work in progress
  • Compound wall: 50%, Work in progress
  • Covered parking: 99%, Work in progress
  • Internal roads and pavements: 0%
  • Sewerage (chambers, lines, septic tanks, STP): 96%, Work in progress
  • Storm water drains: 45%, Work in progress
  • Treatment and disposal of sewage and sullage water (STP): 90%, Work in progress
  • Water conservation and rainwater harvesting: 91%, Work in progress
Unclear in the certificate
  • Table A gives one set of figures for Tower A and Tower B together. It does not give separate figures for each tower.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against ELAN LIMITED (all its projects)35 (Complaint: 32; Execution of an earlier order: 1; Compensation: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in