RERA’d by NeevHQ

Projects · HERITAGE MAX REALTECH PVT. LTD.

Elevate (Phase II)

Heritage Max Realtech · Sector 59, Gurugram

Registered with RERA: Jun 2021

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Heritage Max Realtech

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameELEVATE (PHASE II)
Builder (promoter)HERITAGE MAX REALTECH PVT. LTD.
LocationVILLAGE BEHRAMPUR, SECTOR-59, GURUGRAM
RERA project IDRERA-GRG-710-2020
Registration certificate numberGGM/459/191/2021/27 DATED 22.06.2021
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/01/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area2.96875 acres
Licence1. 16 of 2008 2. 28 of 2008 3. 44 of 2011
Estimated cost of the project₹54,349.9 lakh (₹543.5 crore)
Total units (plots, apartments, shops)248
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder3 BHK: 1,159–1,274 sq ft carpet, 155 units; 3 BHK + study: 1,217–1,432 sq ft carpet, 93 units (source: the builder's registration form (Form A-H))
Units booked when registered0
Units unsold when registered0
Layout plan approved on25-04-2019
Building plans approved on25-04-2019

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-01-2025
Revised completion date31-01-2025
Infrastructure: projected completion31-01-2025
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on14-Oct-2026
Quarterly reports listed on the portal21

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹252.7 lakh (₹2.53 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹400.74 lakh (₹4.01 crore)
Spent on infrastructure in the quarter₹25 lakh (₹0.25 crore)
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹705.01 lakh (₹7.05 crore)
Project bank account (escrow): withdrawn in the quarter₹918 lakh (₹9.18 crore)
Project bank account (escrow): balance at quarter end₹214.03 lakh (₹2.14 crore)
Units in the project (apartments / plots)248 apartments
Sold in the quarter1 apartments
EDC (development charges): paid / due as on date₹0 paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 03-11-2016
  • Zoning Plan: Obtained Approval 03-11-2016
  • Service Plans: Obtained Approval 19-05-2021
  • Site Plans: Obtained Approval 25-04-2019
  • Building Plans: Obtained Approval 25-04-2019
  • Fire NOC: Obtained Approval 13-09-2019

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 12 Oct 2026, for 30 Sep 2026
By part
  • Tower-D: 100%, Structure complete up to terrace, with 1 stilt floor, 1 service floor and 33 apartment floors. Sub-structure, MEP and finishing items are each certified at 100% of proposed work. Internal and external finishing is listed as 100%. External RCC wall work is marked NA.
Unclear in the certificate
  • Only Tower-D is shown in the pages provided. Table B and any other towers are not in the document.
  • The overall percentage for the project is not stated as one figure.
  • The units for the work done values in Table A (for example 24.0, 39, 11.8) are not stated.
  • The number of basements is left blank. Basement Level 2 is marked with an asterisk, but the note it refers to is not visible.
  • The document does not say whether the 100% figures are for the whole tower or only the listed components.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against HERITAGE MAX REALTECH PVT. LTD. (all its projects)2 (Complaint: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in