Projects · EMAAR INDIA LIMITED
Emaar Business District 114 NXT
Emaar India · Sector 114, Gurugram
Registered with RERA: Feb 2023
Is it legal?
- RERA registered, valid till Aug 2027
- HRERA has not opened any case of its own against this project
- 1 complaint about this project decided by HRERA since Nov 2023 (1 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Aug 2027, never extended
- No occupation certificate yet (not ready for possession)
- Construction, as certified by the architect (Oct–Dec 2025):
- Done: 12 parts
- In progress: Plots 0%
- Money: ₹159.7 crore spent of ₹204.7 crore; ₹45 crore still to spend (CA certificate, Dec 2025)
What's on offer?
- 139 units: 134 sold, 5 unsold (builder's certificate, Dec 2025)
- 139 plots, 115–263 sq yd
Location
- Nearest metro: Yashobhoomi Dwarka Sector 25, 7.3 km by road (15 min by car)
- Cyber City 55 min · Airport 35 min by car at 9:30 am
- Within 3 km: 0 hospitals, 1 school, 1 mall
Location shown for Sector 114; the exact site was not found.
The builder: Emaar India
- 20 projects registered in Gurugram, 2 lapsed
- 0 with an occupation certificate on record
- 97 buyer complaints decided by HRERA
★ Emaar India was earlier called Emaar MGF Land Ltd. Its history under the earlier name matters too: 22 projects (19 with an occupation certificate), 1,022 decided buyer complaints.
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | EMAAR BUSINESS DISTRICT 114 NXT |
|---|---|
| Builder (promoter) | EMAAR INDIA LIMITED |
| Location | SECTOR 114, GURUGRAM |
| RERA project ID | RERA-GRG-1103-2022 |
| Registration certificate number | GGM/691/423/2023/35 DATED 02.02.2023 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 23/08/2027 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 11.40 acres |
| Licence | 130 of 2022 |
| Estimated cost of the project | ₹19,752 lakh (₹197.52 crore) |
| Total units (plots, apartments, shops) | 139 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 25-08-2022 |
| Building plans approved on | 25-08-2022 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 24-08-2022 |
|---|---|
| Likely completion date | 23-08-2027 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/12/2025 (OCT-DEC) |
| Latest report submitted on | 13-Jan-2026 |
| Quarterly reports listed on the portal | 11 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 31/12/2025 (OCT-DEC))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹5,741 lakh (₹57.41 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹0 |
| Spent on infrastructure in the quarter | ₹2,664 lakh (₹26.64 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹11,906 lakh (₹119.06 crore) |
| Project bank account (escrow): deposited in the quarter | ₹4,018.46 lakh (₹40.18 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹5,056.63 lakh (₹50.57 crore) |
| Project bank account (escrow): balance at quarter end | ₹1,438.35 lakh (₹14.38 crore) |
| Units in the project (apartments / plots) | 139 plots |
| Sold in the quarter | 0 plots |
| EDC (development charges): paid / due as on date | ₹5,520.34 lakh (₹55.2 crore) paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 09 Jan 2026, for Dec-25 |
|---|---|
| By part |
|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|---|
| Cases | |
| Decided cases against EMAAR INDIA LIMITED (all its projects) | 97 (Execution of an earlier order: 36; Complaint: 57; Compensation: 4) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in