RERA’d by NeevHQ

Projects · EMAAR INDIA LIMITED

Emaar Business District 65NXT (EBD 65NXT)

Emaar India · Sector 65, Gurugram

Registered with RERA: Oct 2023

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Emaar India

★ Emaar India was earlier called Emaar MGF Land Ltd. Its history under the earlier name matters too: 22 projects (19 with an occupation certificate), 1,022 decided buyer complaints.

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameEMAAR BUSINESS DISTRICT 65NXT (EBD 65NXT)
Builder (promoter)EMAAR INDIA LIMITED
LocationVILLAGE - BADSHAHPUR, SECTOR 65, GURUGRAM
RERA project IDRERA-GRG-1397-2023
Registration certificate numberGGM/751/483/2023/95 DATED 16.10.2023
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to10/08/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area1.148 acres
Licence10 of 2009, 113 of 2011, 117 of 2022
Estimated cost of the project₹2,647 lakh (₹26.47 crore)
Total units (plots, apartments, shops)12
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on23-08-2023
Building plans approved on25-08-2023

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction11-11-2023
Likely completion date10-08-2027

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on12-Oct-2026
Quarterly reports listed on the portal11

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹112 lakh (₹1.12 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹316 lakh (₹3.16 crore)
Other costs in the quarter (EDC, taxes, etc.)₹1,577 lakh (₹15.77 crore)
Project bank account (escrow): deposited in the quarter₹78.54 lakh (₹0.79 crore)
Project bank account (escrow): withdrawn in the quarter₹631.89 lakh (₹6.32 crore)
Project bank account (escrow): balance at quarter end₹19.16 lakh (₹0.19 crore)
Units in the project (apartments / plots)12 plots
Sold in the quarter0 plots
EDC (development charges): paid / due as on date₹11,632.19 lakh (₹116.32 crore) paid; ₹169.83 lakh (₹1.7 crore) due
Approvals listed
  • Layout Plan: Obtained Approval 12-08-2022
  • Demarcation Plan: Obtained Approval 21-03-2023
  • Zoning Plan: Obtained Approval 21-03-2023
  • Service Plans: Obtained Approval 16-11-2023
  • Electricity Plans: Obtained Approval 26-10-2017

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 08 Oct 2026, for Sep-26
By part
  • Plots: 0%, Table A shows 0% for sub structure, super structure, MEP and finishing. Table A values are shown as nil for the quarter.
  • Internal roads & pavements: 100%
  • Parking (open): 100%
  • Water supply: 100%
  • Sewerage (chambers, lines, septic tanks, STP): 100%
  • Storm water drains: 100%
  • Landscaping & tree plantation: 100%
  • Benches: 100%
  • Street lighting/ electrification: 100%
  • Fire protection and fire safety requirements: 100%
  • Electrical meter room, sub-station, receiving station: 100%

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against EMAAR INDIA LIMITED (all its projects)97 (Execution of an earlier order: 36; Complaint: 57; Compensation: 4)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in