Projects · EMAAR MGF LAND LTD
Emerald Estate
Emaar MGF Land · Sector 65, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Aug 2022 (date has passed)
- HRERA has opened 5 cases of its own against the builder over this project (5 open):
- Did not submit quarterly progress report to the Authority (May 2022, open)
- Failed to submit completion certificate status for Emerald Estate project (Jul 2023, open)
- Did not file REP-I project forms online and in hard copy, or quarterly progress reports (Nov 2019, open). At stake: decided ₹25,000 per day from 31 Dec 2019, up to 5% of project cost
- 2 more cases: reply 4
- 11 complaints about this project decided by HRERA since Nov 2023 (3 delay interest ordered, 2 refund ordered, 6 dismissed, withdrawn or settled)
Will it be delivered on time?
- Deadline Aug 2022, never extended (date has passed)
- 2 occupation certificates issued:
- Mar 2019: Blocks A, A1, B, B1, C, D and EWS block (536 flats)
- Mar 2019: 536 flats and 239 EWS flats in Sector-65 blocks (536 flats)
- Money: ₹474.4 crore spent of ₹475.8 crore; ₹1.4 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 666 units: 665 sold, 1 unsold (builder's certificate, Sep 2026)
- Flat types (BHK) as stated in the builder's registration form (Form A-H):
- 2 BHK: 748 sq ft carpet, 144 units
- 3 BHK: 901–1,270 sq ft carpet, 372 units
- 4 BHK: 1,470 sq ft carpet, 150 units
Location
- Nearest metro: Sector 55–56, 6.2 km by road (21 min by car)
- Cyber City 46 min · Airport 64 min by car at 9:30 am
- Within 3 km: 10 hospitals, 18 schools, 6 malls
The builder: Emaar MGF Land
- 22 projects registered in Gurugram, 1 lapsed
- 19 with an occupation certificate on record
- 1,022 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | EMERALD ESTATE |
|---|
| Builder (promoter) | EMAAR MGF LAND LTD |
|---|
| Location | SECTOR 65, MAIDAWAS, GURUGRAM |
|---|
| RERA project ID | RERA-GRG-442-2019 |
|---|
| Registration certificate number | 104 OF 2017 DATED 24.08.2017 |
|---|
| Registration status | Listed on HRERA Gurugram's registered projects list |
|---|
| Registration valid up to | 23/08/2022 |
|---|
| Registered with | INTERIM RERA |
|---|
| Registration certificate | View on HRERA Gurugram |
|---|
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|
| Land area | 11.69 acres |
|---|
| Licence | 06 of 2008 |
|---|
| Estimated cost of the project | ₹38,217 lakh (₹382.17 crore) |
|---|
| Total units (plots, apartments, shops) | 666 |
|---|
| Unit sizes (carpet area, as declared) | Not found in the records checked |
|---|
| Flat types (BHK), as stated by the builder | 2 BHK: 748 sq ft carpet, 144 units; 3 BHK: 901–1,270 sq ft carpet, 372 units; 4 BHK: 1,470 sq ft carpet, 150 units (source: the builder's registration form (Form A-H)) |
|---|
| Units booked when registered | 661 |
|---|
| Units unsold when registered | 5 |
|---|
| Layout plan approved on | 29-12-2009 |
|---|
| Building plans approved on | 29-12-2009 |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | 23-08-2022 |
|---|
| Revised completion date | 23-08-2022 |
|---|
| Infrastructure: projected completion | 23-08-2022 |
|---|
| Infrastructure: percentage complete when registered | 80% |
|---|
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
|---|
| Latest report submitted on | 13-Oct-2026 |
|---|
| Quarterly reports listed on the portal | 32 |
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹0 |
|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
|---|
| Put in by the builder in the quarter | ₹0 |
|---|
| Spent on construction of apartments in the quarter | ₹0 |
|---|
| Spent on infrastructure in the quarter | ₹36,464 lakh (₹364.64 crore) |
|---|
| Other costs in the quarter (EDC, taxes, etc.) | ₹9,257 lakh (₹92.57 crore) |
|---|
| Project bank account (escrow): deposited in the quarter | ₹0 |
|---|
| Project bank account (escrow): withdrawn in the quarter | ₹0 |
|---|
| Project bank account (escrow): balance at quarter end | ₹0 |
|---|
| Units in the project (apartments / plots) | 666 apartments |
|---|
| Sold in the quarter | 0 apartments |
|---|
| EDC (development charges): paid / due as on date | ₹4,795.37 lakh (₹47.95 crore) paid; ₹0 due |
|---|
| Approvals listed | - Demarcation Plan: Obtained Approval 13-08-2008
- Zoning Plan: Obtained Approval 13-08-2008
- Service Plans: Obtained Approval 14-10-2016
- Electricity Plans: Obtained Approval 18-07-2017
- Site Plans: Obtained Approval 29-08-2013
- Building Plans: Obtained Approval 29-08-2013
- Fire NOC: Obtained Approval 26-03-2015
|
|---|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 06 Jan 2024, for Dec'-23 |
|---|
| By part | - Tower A: Stilt plus 12 floors; 13 slabs cast; sub-structure, super-structure, MEP and finishing items in the status table are each shown as 100%
- Tower B: not stated
|
|---|
| Unclear in the certificate | - Table A progress values (work done, cumulative value, percentage) are blank for Tower A and Tower B
- The sub-structure status table on pages 4 and 5 does not name the tower it refers to
- No progress details are given for Tower B apart from its blank Table A
|
|---|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | - Occupation Certificate (Form BR-VII) dated 05 Mar 2019: covers Group Housing Colony on 25.499 acres in Sector-65, Gurugram (Licence No. 6 of 2008). Covers Block-A (Part-1, 17 blocks), Block-B (Part-1), Block-C (Part-1), Block-D (Part-1), each with 72 dwelling units from Ground Floor to 12th Floor. Also covers Block-A (17 blocks, Part-2) with 136 units, Block-A1 with 4 units, Block-B (1&2, 8 blocks) with 64 units, Block-B (3, 4 blocks) with 32 units, Block-B1 (3 blocks) with 12 units, all from Ground Floor to 3rd Floor, and the EWS Block with 239 flats from Ground Floor to 8th Floor. Total 536 main dwelling units and 239 EWS flats. Upper floors above Ground + 3rd Floor of Block-A (17 blocks), A1, B (12 blocks) and B1 (3 blocks) cannot be used until a second staircase is provided as per the Fire Services NOC. Basements (Part-1 and Part-2) are also listed in the non-FAR area.. Addressed to Active Promoters Pvt. Ltd. & others, c/o Emaar MGF Land Ltd.. Composition fees for variations from approved plans: ₹34,89,021. Unclear in the document: The scanned bundle also contains two other occupation certificates: one dated 15 May 2020 (124 main dwelling units in Blocks A, A1, B, B(3) and B1, Part-2, 4th to 6th Floor, composition charges Rs 8,22,267) and one dated 11 Nov 2020 (Towers E to K, Blocks C, D, E, E1, E2 and a commercial building). These are not described in this record.; The 05 Mar 2019 certificate states the number of EWS blocks and floors as shown in the table; the EWS row has no separate block count stated.
- Occupation Certificate (Form BR-VII), dated 05 Mar 2019, for the first certificate in this file dated 05 Mar 2019: covers Group housing colony of 25.499 acres in Sector-65, Gurugram. Blocks A, B, C and D (Part-1) have 72 units each, from ground floor to 12th floor. Block-A (17 blocks), A1, B (8 and 4 blocks) and B1 (3 blocks) (Part-2) have 136, 4, 64, 32 and 12 units, from ground floor to 3rd floor. The EWS block has 239 flats, from ground floor to 8th floor. Total is 536 main dwelling units and 239 EWS flats, plus basements. Upper floors above Ground + 3rd floor of Block-A (17 blocks), A1, B (12 blocks) and B1 (3 blocks) must not be used until a second staircase is provided.. Addressed to Active Promoters Pvt. Ltd. & others, c/o Emaar MGF Land Ltd.. Composition fees for variations from approved plans: ₹34,89,021. Unclear in the document: This file also contains two later occupation certificates: memo dated 15 May 2020 (124 main dwelling units, Blocks A, A1, B, B1 Part-2 from 4th to 6th floor) and memo dated 11 Nov 2020 (Towers E to K and Blocks C, D, E, E1, E2 and a commercial block). Their details are not included in these fields.; The composition fee of Rs 34,89,021 is for the first certificate only. The 15 May 2020 certificate states a separate fee of Rs 8,22,267.
|
|---|
| Corrigenda / addenda to the registration | None found in the records checked |
|---|
| Extensions of registration | None found in the records checked |
|---|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 5 |
|---|
| By status | Online Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 2 |
|---|
| Proceedings | - RERA-GRG-2735-2022: Case RERA-GRG-2735-2022, listed as HARERA Gurugram through a named representative versus Emaar MGF Land Ltd. The page does not state the reason for the case. Status: Online complaint not yet received at office. Complaint not yet dispatched. No next hearing date listed.
- RERA-GRG-3052-2022: Authority-initiated show cause notice to Emaar MGF Land Ltd (promoter) for not submitting a quarterly progress report. The notice asked the promoter to appear before the Authority on 27 Jun 2022 at 11.00 am with a written reply if it had anything to say. Status: First hearing listed for 27 Jun 2022. The page records no proceedings or order for that hearing; the bench and order fields show '---'. Latest: 27 Jun 2022, First hearing was scheduled before the Authority in Gurugram. The page shows the status as 'First Hearing' with no proceedings or order recorded.
- RERA-GRG-3235-2023: Suo motu monitoring of possible violation of Section 4(2)(l)(C) of the Real Estate (Regulation and Development) Act, 2016, regarding the project Emerald Estate, promoter Emaar MGF Land Ltd. The Authority started the case itself. The case concerns the completion certificate (CC) status of the project. Status: Pending. The matter was listed to come up on 16 Aug 2023. The promoter's representative said the occupation certificates for the complete project were obtained and copies were submitted with the reply, and the office was asked to link them to the file. Latest: 18 Aug 2023, Order uploaded on the case page.
- RERA-GRG-5150-2022: A complaint filed with HRERA Gurugram against the promoter Emaar MGF Land Ltd. The page does not state the grounds of the complaint. The page lists the complainant as a private party, not the Authority. Status: Listed for first hearing on 30 Jun 2022. The page shows no proceedings of the day and no order uploaded. Latest: 16 Jul 2022, A document was received at the Authority under Dak ID 37933, submitted by the complainant and remarked as a new complaint.
- RERA-GRG-5389-2019: Failure to file the REP-I (Part A to H) project registration form online and in hard copy, and to submit quarterly progress reports, for a registered group housing project despite repeated notices Status: Pending. The case page lists the next hearing as 24 Feb 2020 and shows a fourth notice dispatched on 20 Jul 2020. No final decision is recorded. Latest: 20 Jul 2020, Fourth notice (section 42(1)(d)) dispatched and complaint dispatched, with tracking ID recorded on the case page. Penalty: Authority decided to impose Rs 25,000 per day from 31 Dec 2019 until the default ends, which may cumulatively extend up to five percent of the estimated project cost, under section 63 of the Act.
|
|---|
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 11 |
|---|
| Cases | - RERA-GRG-775-2026 (compensation, decided 12-Oct-2026): Buyers sought Rs 73.9 lakh extra compensation for possession delay; complaint dismissed as delay compensation was already allowed.
- RERA-GRG-607-2021 (compensation, decided 26-May-2025): Buyers sought compensation for delayed possession and defects; builder ordered to pay Rs 3.46 lakh with 11.50% interest.
- RERA-GRG-2480-2023 (complaint, decided 10-Dec-2024): Buyers sought delayed possession charges; HRERA declined the complaint as barred by limitation, filed years after possession offer.
- RERA-GRG-13-2024 (compensation, decided 20-Nov-2024): Buyers sought extra compensation after a 4-year possession delay; authority dismissed it as belated and already compensated.
- RERA-GRG-3369-2023 (complaint, decided 20-Sep-2024): Buyer sought delay compensation and PLC refund; HRERA ordered builder to pay delay interest at 11.10% from endorsement date.
- RERA-GRG-2873-2021 (complaint, decided 13-Aug-2024): Buyers sought PLC refund and compensation for possession delay; authority dismissed complaint as not maintainable after conveyance deed
- RERA-GRG-6933-2022 (complaint, decided 02-Aug-2024): Buyers sought delay interest on flat paid for; HRERA ordered 11% delay interest from 20 Feb 2013 to 17 Mar 2020, adjusting Rs 6.35 lakh already paid.
- RERA-GRG-7545-2022 (complaint, decided 08-May-2024): Buyer sought delay interest and refunds; HRERA ordered builder to pay 10.85% delay interest from June 2014 and refund wrongly collected GST.
- RERA-GRG-6124-2022 (complaint, decided 16-Apr-2024): Buyer sought delay interest and refunds after buying an offered flat; authority rejected the complaint as the buyer suffered no delay.
- RERA-GRG-2042-2021 (complaint, decided 02-Apr-2024): Buyers sought delay compensation and refunds after a 2018 settlement; HRERA dismissed the complaint, finding the settlement binding and compensation already paid.
- RERA-GRG-1780-2023 (complaint, decided 01-Mar-2024): Buyer sought delay possession interest after a 7-year delay; builder ordered to pay 10.85% interest, less compensation already paid.
|
|---|
| Decided cases against EMAAR MGF LAND LTD (all its projects) | 1022 (Complaint: 321; Execution of an earlier order: 50; Compensation: 29); breakdown of the latest 400 |
|---|
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in