RERA’d by NeevHQ

Projects · EMAAR MGF LAND LTD.

Emerald Hills

Emaar MGF Land · Sector 62, Gurugram

Registered with RERA: Aug 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Emaar MGF Land

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameEMERALD HILLS
Builder (promoter)EMAAR MGF LAND LTD.
LocationSECTOR 62 AND 65, BADSHAHPUR, GURUGRAM
RERA project IDRERA-GRG-643-2020
Registration certificate number162 OF 2017 DATED 29.08.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to28/02/2030
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area55.962 acres
Licence10 of 2009 113 of 2011
Estimated cost of the project₹56,205 lakh (₹562.05 crore)
Total units (plots, apartments, shops)823
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered754
Units unsold when registered71
Layout plan approved on22-12-2011
Building plans approved on22-12-2011

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date22-08-2022
Revised completion date22-08-2022
Infrastructure: projected completion22-08-2022
Infrastructure: percentage complete when registered90%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on12-Oct-2026
Quarterly reports listed on the portal32

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹566 lakh (₹5.66 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹28,486 lakh (₹284.86 crore)
Other costs in the quarter (EDC, taxes, etc.)₹17,709 lakh (₹177.09 crore)
Project bank account (escrow): deposited in the quarter₹383.56 lakh (₹3.84 crore)
Project bank account (escrow): withdrawn in the quarter₹350 lakh (₹3.5 crore)
Project bank account (escrow): balance at quarter end₹34.36 lakh (₹0.34 crore)
Units in the project (apartments / plots)823 plots
Sold in the quarter0 plots
EDC (development charges): paid / due as on date₹9,832.04 lakh (₹98.32 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 13-12-2021
  • Zoning Plan: Obtained Approval 13-12-2021
  • Service Plans: Obtained Approval 12-12-2017
  • Electricity Plans: Obtained Approval 08-03-2017
  • Site Plans: Obtained Approval 30-05-2017
  • Fire NOC: Obtained Approval 08-03-2017

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 06 Jan 2024, for DEC-23
By part
  • Ph-1 B: Table A shows zero work done during the quarter. Cumulative value and percentage are left blank.
  • Ph-2: Table A shows zero work done during the quarter. Cumulative value and percentage are left blank.
  • Ph-3: Table A shows zero work done during the quarter. Cumulative value and percentage are left blank.
  • Phase no.-1 (progress status sheet): Sub-structure, super-structure, MEP and door and window frames are marked 100% complete. The wall plastering entry is not visible.
Unclear in the certificate
  • The Phase no.-1 status sheet is cut off after item 12 (wall plastering), so later items are not shown.
  • Table A for Ph-1 B, Ph-2 and Ph-3 gives no percentage figures, only zero work done in the quarter.
  • No single overall percentage of construction completion is stated in the certificate.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 2; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this project19
Cases
Decided cases against EMAAR MGF LAND LTD. (all its projects)1022 (Complaint: 321; Execution of an earlier order: 50; Compensation: 29); breakdown of the latest 400

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in