Emerald Ray

Puri Constructions · Sector 104, Gurugram

Registered with RERA: Aug 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

The builder: Puri Constructions

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameEMERALD RAY
Builder (promoter)PURI CONSTRUCTIONS LTD.
LocationSECTOR - 104, DHANWAPUR,GURUG RAM
RERA project IDRERA-GRG-259-2019
Registration certificate number136 OF 2017 DATED 28.08.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to28/02/2020
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area17.1745 acres
Licence32 of 2013 (dated 17-5-2013) and 68 of 2012 (dated 21-6-2012)
Estimated cost of the project₹52,614.06 lakh (₹526.14 crore)
Total units (plots, apartments, shops)498
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builderNot stated in the builder's registration form or the plans we could read
Units booked when registered342
Units unsold when registered156
Layout plan approved on17-01-2013
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date23-08-2018
Revised completion date23-08-2018
Infrastructure: projected completion23-08-2018
Infrastructure: percentage complete when registered100%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2026 (JAN-MAR)
Latest report submitted on02-Jul-2026
Quarterly reports listed on the portal30

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Latest quarterly report: figures as filed by the builder (quarter ending 31/03/2026 (JAN-MAR))

These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.

Collected from buyers in the quarter₹375.88 lakh (₹3.76 crore)
Borrowed from banks / financial institutions in the quarter₹0
Put in by the builder in the quarter₹0
Spent on construction of apartments in the quarter₹0
Spent on infrastructure in the quarter₹0
Other costs in the quarter (EDC, taxes, etc.)₹0
Project bank account (escrow): deposited in the quarter₹375.88 lakh (₹3.76 crore)
Project bank account (escrow): withdrawn in the quarter₹392.14 lakh (₹3.92 crore)
Project bank account (escrow): balance at quarter end₹10.42 lakh (₹0.1 crore)
Units in the project (apartments / plots)498 apartments
Sold in the quarter0 apartments
EDC (development charges): paid / due as on date₹5,149.05 lakh (₹51.49 crore) paid; ₹0 due
Approvals listed
  • Demarcation Plan: Obtained Approval 17-11-2017
  • Zoning Plan: Obtained Approval 17-11-2017
  • Service Plans: Obtained Approval 17-11-2017
  • Fire NOC: Obtained Approval 17-11-2017

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Construction progress certified by the project's architect

From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.

Certificatedated 31 Mar 2026
Overall work complete100%
By part
  • Sub structure: 100%
  • Super structure: not stated
  • MEP (mechanical, electrical, plumbing and firefighting): 100%
  • Finishing (internal and external): 100%
  • Internal roads and pavements: 100%
  • Water supply, sewerage, storm, STP and rain water harvesting: not stated
  • Play grounds and parks, circulation road: not stated
  • Street light, renewable energy, security and fire fighting: not stated
  • Other internal development works (including laying of cable): 100%
  • Club house / community centre: 100%
  • Others (electrification cost up to project): 100%
Unclear in the certificate
  • Super structure percentage is blurred in the scanned copy; not stated.
  • Water supply, play grounds and street light percentages are blurred in the scanned copy; not stated.
  • The report covers the full year 01-04-2025 to 31-03-2026, not a single quarter, and no quarterly figure is stated.

Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 4; Pending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against PURI CONSTRUCTIONS LTD. (all its projects)19 (Complaint: 16; Compensation: 3)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026