Projects · JUBILIANT MALLS PVT. LTD
Engracia By ILD ( Plotted Colony)
Jubiliant Malls · Sector 37D, Gurugram
Registered with RERA: Aug 2017
Is it legal?
- RERA registered, valid till Aug 2019 (date has passed)
- HRERA has opened 6 cases of its own against the builder over this project (6 open):
- Failed to extend registration, submit completion or occupation certificate, and requisite documents (Jun 2022, open)
- HRERA is checking whether the builder missed the completion date it declared (section 4(2)(l)(C)) (Jun 2022, open)
- Did not submit quarterly progress report (May 2022, open)
- 3 more cases: reply 4
- 1 complaint about this project decided by HRERA since Nov 2023 (1 delay interest ordered)
Will it be delivered on time?
- Occupation certificate (Jul 2022) covers: Residential plotted scheme, 3.93 acres, Basai Sector-37 D
- Quarterly progress report shown as "not uploaded" by HRERA
Location
- Nearest metro: Millennium City Centre Gurugram, 16.9 km by road (52 min by car)
- Cyber City 59 min · Airport 41 min by car at 9:30 am
- Within 3 km: 4 hospitals, 1 school, 2 malls
Location shown for Sector 37D; the exact site was not found.
The builder: Jubiliant Malls
- 1 project registered in Gurugram
- 1 with an occupation certificate on record
- 15 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ENGRACIA BY ILD ( PLOTTED COLONY) |
|---|---|
| Builder (promoter) | JUBILIANT MALLS PVT. LTD |
| Location | SECTOR- 37D, VILLAGE BASAI, G URUGRAM |
| RERA project ID | RERA-GRG-564-2020 |
| Registration certificate number | 66 OF 2017 DATED 18.8.2017 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/08/2019 |
| Registered with | INTERIM RERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | Ongoing project (under construction when registered) |
|---|---|
| Land area | 3.923 acres |
| Licence | DULB/CTP/A2/2014/4470-4473 DT 28.8.2014 |
| Estimated cost of the project | ₹2,977 lakh (₹29.77 crore) |
| Total units (plots, apartments, shops) | 27 |
| Unit sizes (carpet area, as declared) | Not found in the records checked |
| Flat types (BHK), as stated by the builder | Not stated in the builder's registration form or the plans we could read |
| Units booked when registered | 20 |
| Units unsold when registered | 7 |
| Layout plan approved on | 06-11-2015 |
| Building plans approved on | 06-11-2015 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Earlier completion date | Not found in the records checked |
|---|---|
| Revised completion date | Not found in the records checked |
| Infrastructure: projected completion | 31-03-2021 |
| Infrastructure: percentage complete when registered | 0% |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | QPR not uploaded |
|---|---|
| Latest report period | Not found in the records checked |
| Latest report submitted on | Not found in the records checked |
| Quarterly reports listed on the portal | Not found in the records checked |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | 1 |
|---|---|
| Cases | |
| Decided cases against JUBILIANT MALLS PVT. LTD (all its projects) | 15 (Execution of an earlier order: 3; Complaint: 12) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in