RERA’d by NeevHQ

Projects · ATHENA INFRASTRUCTURES LTD.

Enigma, PHASE-1A

Athena Infrastructures · Sector 110, Gurugram

Registered with RERA: Nov 2017

Is it legal?

Will it be delivered on time?

What's on offer?

Location

Location shown for Sector 110; the exact site was not found.

The builder: Athena Infrastructures

Open in Google MapsShare on WhatsApp

Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.

Registration

Project nameENIGMA, PHASE-1A
Builder (promoter)ATHENA INFRASTRUCTURES LTD.
LocationSECTOR-110, VILLAGE PAWALA KH USRUPUR, GURUGRAM, HARYANA
RERA project IDRERA-GRG-535-2019
Registration certificate number353 OF 2017 DATED 20.11.2017
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/03/2018
Registered withINTERIM RERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area80354.381 acres
Licence213 of 2007 dated 5.09.2007 10 of 2011 dated 29.01.2011 64 of 2012 dated 20.06.2012
Estimated cost of the project₹20,083 lakh (₹200.83 crore)
Total units (plots, apartments, shops)126
Unit sizes (carpet area, as declared)Not found in the records checked
Flat types (BHK), as stated by the builder4 BHK: 70 units; 5 BHK: 56 units (source: the builder's registration form (Form A-H))
Units booked when registered112
Units unsold when registered112
Layout plan approved on23-08-2013
Building plans approved on23-08-2013

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date31-03-2018
Revised completion date31-03-2018
Infrastructure: projected completion31-03-2018
Infrastructure: percentage complete when registered100%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listQPR not uploaded
Latest report periodNot found in the records checked
Latest report submitted onNot found in the records checked
Quarterly reports listed on the portalNot found in the records checked

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed6
By statusOnline Complaint Not Yet Received At Office: 1; First Hearing: 3; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against ATHENA INFRASTRUCTURES LTD. (all its projects)5 (Complaint: 5)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: info@neevhq.in