Projects · MAX ESTATES GURGAON LIMITED
Estate 360
Max Estates Gurgaon · Sector 36, Gurugram
Registered with RERA: Aug 2024
Is it legal?
- RERA registered, valid till Aug 2030
- HRERA has not opened any case of its own against this project
Will it be delivered on time?
- Deadline Aug 2030, never extended
- No occupation certificate yet (not ready for possession)
- Money: ₹947.6 crore spent of ₹4,315.2 crore; ₹3,367.6 crore still to spend (CA certificate, Sep 2026)
What's on offer?
- 1,025 units: 858 sold, 167 unsold (builder's certificate, Sep 2026)
- Flat types (BHK) as stated in the builder's floor plans uploaded to HRERA:
- 2.5 BHK
- 3 BHK
- 1,025 units in 25 sizes, as declared to HRERA:
- 112 units of 205 sq ft carpet (1 tower)
- 144 units of 1,324 sq ft carpet (2 towers)
- 140 units of 1,404 sq ft carpet (2 towers)
- 134 units of 1,507 sq ft carpet (2 towers)
- 134 units of 1,530 sq ft carpet (2 towers)
- 140 units of 1,899 sq ft carpet (2 towers)
- 19 less common sizes: see the full list below
Location
- Nearest metro: Millennium City Centre Gurugram, 17.3 km by road (47 min by car)
- Cyber City 53 min · Airport 37 min by car at 9:30 am
- Within 3 km: 1 hospital, 1 school, 0 malls
The builder: Max Estates Gurgaon
- 1 project registered in Gurugram
- 0 with an occupation certificate on record
- 0 buyer complaints decided by HRERA
Open in Google MapsShare on WhatsApp
Full details and sources are below. Drive times: Google Maps. Nearby places: © OpenStreetMap contributors.
Registration
| Project name | ESTATE 360 |
|---|---|
| Builder (promoter) | MAX ESTATES GURGAON LIMITED |
| Location | VILLAGE-HARSARU, SECTOR 36-A, |
| RERA project ID | RERA-GRG-1675-2024 |
| Registration certificate number | GGM/860/592/2024/87 DATED 16.08.2024 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 31/08/2030 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 11.80 acres |
| Licence | 38 of 2013 Valid upto 03.06.2026 97 of 2013 Valid upto 07.11.2024 167 of 2023 Valid upto 17.08.2028 |
| Estimated cost of the project | ₹4,31,517.37 lakh (₹4,315.17 crore) |
| Total units (plots, apartments, shops) | 1025 |
| Unit sizes (carpet area, as declared) | 1 unit of 202 sq ft carpet (1 tower); 112 units of 205 sq ft carpet (1 tower); 41 units of 206 sq ft carpet (1 tower); 1 unit of 215 sq ft carpet (1 tower); 1 unit of 232 sq ft carpet (1 tower); 1 unit of 264 sq ft carpet (1 tower); 1 unit of 266 sq ft carpet (1 tower); 1 unit of 471 sq ft carpet (1 tower); 1 unit of 704 sq ft carpet (1 tower); 1 unit of 961 sq ft carpet (1 tower); 6 units of 1,152 sq ft carpet (2 towers); 72 units of 1,162 sq ft carpet (2 towers); 6 units of 1,213 sq ft carpet (2 towers); 144 units of 1,324 sq ft carpet (2 towers); 140 units of 1,404 sq ft carpet (2 towers); 6 units of 1,450 sq ft carpet (2 towers); 134 units of 1,507 sq ft carpet (2 towers); 134 units of 1,530 sq ft carpet (2 towers); 66 units of 1,760 sq ft carpet (2 towers); 140 units of 1,899 sq ft carpet (2 towers); 2 units of 2,746 sq ft carpet (2 towers); 4 units of 2,815 sq ft carpet (2 towers); 4 units of 2,985 sq ft carpet (2 towers); 2 units of 3,030 sq ft carpet (2 towers); 4 units of 3,689 sq ft carpet (2 towers) |
| Flat types (BHK), as stated by the builder | 2.5 BHK; 3 BHK (source: the builder's floor plans uploaded to HRERA) |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 07-06-2024 |
| Building plans approved on | 07-06-2024 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-11-2024 |
|---|---|
| Likely completion date | 31-08-2030 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 13-Oct-2026 |
| Quarterly reports listed on the portal | 8 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Latest quarterly report: figures as filed by the builder (quarter ending 30/09/2026 (JUL-SEP))
These are the builder's own figures for that quarter, as filed with HRERA. They are not checked by HRERA or by us.
| Collected from buyers in the quarter | ₹6,214.01 lakh (₹62.14 crore) |
|---|---|
| Borrowed from banks / financial institutions in the quarter | ₹0 |
| Put in by the builder in the quarter | ₹0 |
| Spent on construction of apartments in the quarter | ₹3,991.52 lakh (₹39.92 crore) |
| Spent on infrastructure in the quarter | ₹425 lakh (₹4.25 crore) |
| Other costs in the quarter (EDC, taxes, etc.) | ₹16,246.55 lakh (₹162.47 crore) |
| Project bank account (escrow): deposited in the quarter | ₹6,246.94 lakh (₹62.47 crore) |
| Project bank account (escrow): withdrawn in the quarter | ₹20,696 lakh (₹206.96 crore) |
| Project bank account (escrow): balance at quarter end | ₹42,848.34 lakh (₹428.48 crore) |
| Units in the project (apartments / plots) | 1025 apartments |
| Sold in the quarter | 0 apartments |
| EDC (development charges): paid / due as on date | ₹0 paid; ₹0 due |
| Approvals listed |
|
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Construction progress certified by the project's architect
From the registered architect's certificate attached to the latest quarterly report, read by our software. Percentages are as certified; they are not checked by HRERA or by us.
| Certificate | dated 08 Oct 2026 |
|---|---|
| Unclear in the certificate |
|
Source: Architect's certificate, HRERA Gurugram quarterly report, checked 17 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: not checked yet
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against MAX ESTATES GURGAON LIMITED (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: info@neevhq.in